This course plan, its lessons and its assessments has not yet been verified by a licensed professional engineer or master tradesperson or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.
VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.
10 courses · 2,700 clock hours · 12–18 mo full-time. Grading is competency-based: each course requires the written exam, a competent skills demonstration with zero safety faults, a signed log, and a passed safety audit; percentage weights only rank performance above the competency floor.
This foundational course equips adult learners entering the electrical trade with the safety knowledge, mathematical skills, technical literacy, and professional habits required before touching live systems or entering a job site. Learners complete OSHA 10 construction outreach training, first aid/CPR, and the trade-specific math and communication skills that underpin every subsequent electrical course. Successful completion is a prerequisite for all hands-on electrical coursework in this program.
OutcomesThis foundational course equips adult learners entering the electrical trade with the safety knowledge, mathematical skills, technical literacy, and professional habits required before touching live systems or entering a job site. Learners complete OSHA 10 construction outreach training, first aid/CPR, and the trade-specific math and communication skills that underpin every subsequent electrical course. Successful completion is a prerequisite for all hands-on electrical coursework in this program.
How the course runs. 7 blocks: Electrical Trade Orientation: Hazards, PPE, and OSHA 10 Construction Safety; Lockout/Tagout, First Aid, and Emergency Response; Trade Math I: Whole Numbers, Fractions, Decimals, and Measurement; Trade Math II: Percentages, Ratios, Basic Algebra, and Electrical Formulas; Technical Reading: Schematics, Specifications, Safety Data Sheets, and Trade Documents; Digital Tools, Professional Communication, and NCCER Registry; Career Pathways in the Electrical Trade: Credentials, Licensure, and Professionalism.
What competent looks like. Demonstrate OSHA 10 construction safety principles by correctly identifying and controlling common electrical and construction site hazards, achieving a passing score on the OSHA 10 outreach course assessment. Perform trade math calculations—including fractions, decimals, percentages, area, volume, and basic algebraic expressions—accurately enough to support load calculations, conduit bending, and material takeoffs introduced in later courses. Read and interpret electrical trade documents including simple schematics, specification sheets, material lists, and safety data sheets at a level sufficient to follow job-site instructions independently. Apply lockout/tagout (LOTO) procedures and select correct personal protective equipment (PPE) for simulated electrical work scenarios without prompting. Use digital tools—job-site apps, e-mail, time-tracking software, and the NCCER Registry portal—to manage credentials, communicate professionally, and document work. Articulate a personal career pathway in the electrical trade, identifying the role of NCCER credentials and state licensure in advancing from apprentice to journeyman.
| # | Lesson | Hr | Type | Objective | Activities | Materials | Check |
|---|---|---|---|---|---|---|---|
| 1 | Electrical Trade Orientation: Hazards, PPE, and OSHA 10 Construction Safety | 30 | theory | Learners will complete OSHA 10 Construction outreach training and correctly identify the leading hazards on electrical job sites—struck-by, caught-in, falls, and electrocution—and the controls that mitigate each. |
| OSHA 10 Construction student materials (authorized trainer packet), OSHA 29 CFR 1926 Subpart K reference, job-site hazard photographs, blank JHA forms, class-set PPE samples (hard hat Class E, safety glasses ANSI Z87.1, Class 00 rubber gloves, leather protectors, voltage-rated footwear) | Learners must pass the OSHA 10 Construction final assessment at the level required by the authorized trainer program to receive the OSHA 10 card; additionally, the JHA must correctly identify at least four hazards and assign an appropriate control for each — both items must be satisfactory to advance. |
| 2 | Lockout/Tagout, First Aid, and Emergency Response | 16 | demo | Learners will demonstrate a complete six-step OSHA-compliant lockout/tagout procedure on a training panel and perform hands-only CPR and AED use to the standard required for a nationally recognized CPR/AED/First Aid certification. |
| LOTO training panel with hasp, locks, and tags (non-energized training unit), OSHA 29 CFR 1910.147 reference card, CPR manikins (at least one per four learners), AED trainer unit, first aid kit (bandages, gloves, face shields), CPR/First Aid certification provider student workbook | Learners must complete every step of the LOTO skills checklist without prompting and without skipping any step (100% completion required, as any missed step is a life-safety failure); CPR/First Aid certification skills test must be passed at the certifying organization's published standard. |
| 3 | Trade Math I: Whole Numbers, Fractions, Decimals, and Measurement | 20 | theory | Learners will solve electrical trade problems involving whole-number arithmetic, fractions, decimals, unit conversion, and ruler/tape-measure reading with at least 80% accuracy on a timed written assessment. |
| 25-foot tape measure and 6-foot folding rule (one each per learner), scientific calculator, NCCER Core Curriculum textbook (current edition) math chapters, instructor-prepared worksheets, pencils and graph paper | Timed 20-question written quiz; learners must score 80% or higher to advance; learners scoring below 80% receive targeted tutoring and one retake within the same week. |
| 4 | Trade Math II: Percentages, Ratios, Basic Algebra, and Electrical Formulas | 20 | theory | Learners will apply Ohm's Law (V = IR), the power formula (P = IV), and percentage-based calculations to solve entry-level electrical problems with at least 80% accuracy. |
| Scientific calculator, Ohm's Law wheel reference card, instructor-prepared problem sets, smartphones or tablets with Desmos app installed, NCCER Core Curriculum textbook math and electrical theory chapters | Timed 20-question written quiz covering percentages, ratios, Ohm's Law, and power formula; learners must score 80% or higher; one tutored retake available within the week. |
| 5 | Technical Reading: Schematics, Specifications, Safety Data Sheets, and Trade Documents | 22 | theory | Learners will correctly interpret a single-line electrical diagram, a section of a manufacturer specification sheet, and an OSHA-format Safety Data Sheet (SDS), demonstrating comprehension by answering written questions about each document with at least 80% accuracy. |
| Sample residential one-line diagram (instructor-prepared, one per learner), colored pencils, printed SDS for wire-pulling lubricant or conduit cement, printed Division 26 specification extract, structured summary forms, NCCER Core Curriculum textbook technical reading chapter | Written comprehension quiz on all three document types (20 questions total); learners must answer 80% correctly; any learner who cannot locate critical SDS safety information is flagged for remediation before progressing. |
| 6 | Digital Tools, Professional Communication, and NCCER Registry | 20 | lab | Learners will send a properly formatted professional e-mail, create a personal account in the NCCER Registry, and demonstrate use of at least two digital job-site tools, producing a short written summary of each tool's purpose in the electrical trade. |
| Computers or tablets with internet access, NCCER Registry website, school e-mail accounts, instructor-provided e-mail rubric, smartphones with app store access, instructor-prepared digital tool exploration guide | Active NCCER Registry account screenshot submitted; e-mail scored using the rubric — must meet all five rubric criteria to pass; written tool summary must be at least 150 words and accurately describe both tools to earn credit. |
| 7 | Career Pathways in the Electrical Trade: Credentials, Licensure, and Professionalism | 20 | theory | Learners will construct a written personal career plan identifying the steps from current enrollment through NCCER Level 4, OSHA 10, state journeyman licensure, and potential advancement, demonstrating understanding of how each credential is earned and why each matters to employers. |
| State licensing board website access, computers or tablets, blank career timeline template (instructor-provided), poster board or PowerPoint/Google Slides, NCCER program brochure, guest speaker or pre-recorded video | Career plan document scored on a four-criterion rubric (accuracy of credential requirements, logical sequencing, personal goal specificity, professional writing quality); learners must score 3 out of 4 or higher on each criterion to pass. |
| Assessment | Type | Weight | Pass standard | Method & rubric |
|---|---|---|---|---|
| OSHA 10 Construction Outreach Final Assessment | Written exam | 25% | Pass at the level required by the authorized OSHA outreach trainer's program to receive the official OSHA 10 Construction wallet card; the card itself is the evidence of passing. | Administered by the OSHA-authorized outreach trainer at the conclusion of the OSHA 10 module sequence, this assessment covers all required construction safety topics including electrical hazards, fall protection, and struck-by hazards. Learners who do not pass must complete remediation with the trainer and retake before receiving credit for the lesson. Accuracy · Safety · Communication · Professionalism |
| Trade Math and Technical Reading Cumulative Written Exam | Written exam | 25% | Score of 80% or higher (32 out of 40 questions); one retake is permitted after a documented tutoring session. | A 40-question timed written exam covering whole numbers, fractions, decimals, percentages, Ohm's Law, the power formula, unit conversions, and interpretation of a one-line diagram and SDS excerpt — all contextualized to realistic electrical trade scenarios. This exam maps to NCCER Core Curriculum academic skill areas assessed in the NCCER Level 1 written test. Accuracy · Safety · Communication · Professionalism |
| Professional Readiness Portfolio and Career Plan | Project | 25% | All four required artifacts submitted and each scoring 3 out of 4 or higher on the program rubric: (1) NCCER Registry account screenshot, (2) professional e-mail, (3) digital tool summary, (4) written career plan with credential pathway. | Learners assemble a portfolio demonstrating digital literacy, professional communication, and career planning competence; artifacts are collected across Lessons 6 and 7 and submitted together at the end of the course. This project mirrors the documentation habits expected throughout the externship and the full program. Accuracy · Safety · Communication · Professionalism |
| Safety and Professionalism Oral Defense | Oral / panel | 25% | Learner must answer at least four of five questions correctly and demonstrate LOTO procedure without any missed steps; a missed step in LOTO results in an automatic retake of that component. | In a 10-minute individual session with the instructor, the learner draws three random scenario cards (e.g., 'You arrive on site and find a panel door open with exposed bus bars — what do you do?') and answers two additional questions about their personal career plan, defending their reasoning in plain spoken language. This oral format mirrors the type of safety questioning used by supervisors and inspectors on real job sites. Accuracy · Safety · Communication · Professionalism |
This course builds the foundational electrical theory required for every subsequent trade course and for the NCCER Electrical Level 1 written exam. Students master direct-current and alternating-current principles, circuit analysis, magnetism, and the behavior of resistive, inductive, and capacitive loads. All theory is grounded in practical measurements taken with hand tools and test instruments used daily on construction jobsites.
OutcomesThis course builds the foundational electrical theory required for every subsequent trade course and for the NCCER Electrical Level 1 written exam. Students master direct-current and alternating-current principles, circuit analysis, magnetism, and the behavior of resistive, inductive, and capacitive loads. All theory is grounded in practical measurements taken with hand tools and test instruments used daily on construction jobsites.
How the course runs. 12 blocks: Electrical Safety Fundamentals for the Lab; Atomic Structure, Charge, and Electron Flow; Voltage, Current, Resistance, and Ohm's Law; Series DC Circuits; Parallel and Series-Parallel DC Circuits; Magnetism and Electromagnetic Induction; AC Waveforms, Frequency, and RMS Values; Inductance, Inductive Reactance, and RL Circuits; Capacitance, Capacitive Reactance, and RC Circuits; RLC Circuits, Resonance, and Power Factor; Three-Phase AC Systems; Circuit Troubleshooting, Schematic Reading, and Review.
What competent looks like. Calculate voltage, current, resistance, and power in series, parallel, and series-parallel DC circuits using Ohm's Law and Kirchhoff's Laws to within ±5% of the correct value. Explain the generation, waveform characteristics, and phase relationships of single-phase and three-phase AC, including RMS values, frequency, and peak voltage. Analyze resistive, inductive, and capacitive AC circuits to determine impedance, reactance, power factor, and true vs. apparent power. Use a digital multimeter, clamp-on ammeter, and oscilloscope correctly and safely to measure DC and AC quantities, recording results in a calibrated lab log. Apply electrical safety practices—including shock-hazard awareness, PPE selection, and lockout/tagout procedures—to every laboratory activity without prompting. Interpret schematic diagrams, wiring diagrams, and component datasheets to predict and verify circuit behavior on a standard breadboard or terminal-strip trainer.
| # | Lesson | Hr | Type | Objective | Activities | Materials | Check |
|---|---|---|---|---|---|---|---|
| 1 | Electrical Safety Fundamentals for the Lab | 16 | theory | Students will state the physiological effects of electrical current on the human body, select correct PPE for voltage levels encountered in lab work, and demonstrate the lockout/tagout sequence before touching any energized trainer. |
| NCCER Electrical Level 1 module on electrical safety; OSHA 29 CFR 1910.333 reference sheet; Class 00 and Class 0 insulating gloves; voltage-rated safety glasses; personal padlocks and tags; digital multimeter (Fluke 117 or equivalent) | Written safety quiz (20 questions, multiple-choice and short-answer): 80% or higher required to proceed to any energized lab work. LOTO checklist signed off by instructor with zero steps skipped. |
| 2 | Atomic Structure, Charge, and Electron Flow | 18 | theory | Students will explain how atomic structure determines electrical conductivity, define conventional vs. electron current flow, and differentiate conductors, insulators, and semiconductors using standard definitions. |
| NCCER Electrical Level 1 textbook, Chapter on atomic structure; periodic-table reference card; whiteboard and colored markers; printed Bohr-model worksheets | Exit-ticket quiz (10 items, matching and fill-in): 80% correct. Instructor checks that every student's Bohr model for copper is accurate before the lesson ends. |
| 3 | Voltage, Current, Resistance, and Ohm's Law | 22 | lab | Students will apply Ohm's Law (V = IR) to calculate an unknown quantity when two are known, then verify each calculation by measuring a resistive circuit built on a terminal-strip trainer to within ±5%. |
| Terminal-strip trainers; resistor assortment (1/4 W carbon film, various values); DC regulated bench power supply (0–30 V); digital multimeter; jumper leads; lab log notebooks; NCCER Level 1 textbook | All four circuits measured with results within ±5% of calculated values; lab log entries complete and signed by instructor. Students who exceed ±5% on any circuit must rebuild and re-measure before advancing. |
| 4 | Series DC Circuits | 22 | lab | Students will apply Kirchhoff's Voltage Law to verify that voltage drops around a series circuit sum to the source voltage, and calculate total resistance and individual voltage drops for circuits with up to five resistors. |
| Terminal-strip trainers; resistor assortment; DC bench power supply; digital multimeter; jumper leads; lab log; NCCER Electrical Level 1 textbook | Calculated vs. measured values within ±5%; KVL verified on measurement sheet; fault located correctly and diagnostic steps documented. Score below standard requires a second build-and-measure attempt. |
| 5 | Parallel and Series-Parallel DC Circuits | 24 | lab | Students will apply Kirchhoff's Current Law and the reciprocal-resistance formula to calculate total resistance, branch currents, and node voltages in parallel and series-parallel circuits, then verify results by measurement. |
| Terminal-strip trainers; resistor assortment; DC bench power supply; digital multimeter; clamp-on ammeter (Fluke 323 or equivalent); lab log; NCCER Level 1 textbook | Completed lab log table with ±5% accuracy on all calculated vs. measured values; KCL verified at every node and signed off by instructor. Incomplete or inaccurate logs must be corrected and resubmitted within one class session. |
| 6 | Magnetism and Electromagnetic Induction | 20 | demo | Students will explain how a changing magnetic field induces a voltage in a conductor, describe the relationship between the number of turns, core material, and induced EMF, and identify the principle underlying transformer and generator operation. |
| Permanent bar magnets; demonstration solenoid coils (various turn counts); analog galvanometer; small step-down demonstration transformer; AC variac; digital multimeter; concept-map template; NCCER Level 1 textbook | Concept map graded against an instructor rubric: all six terms present, all relationships correctly explained, 80% of connection statements accurate. Transformer voltage calculation within ±5% of measured value. |
| 7 | AC Waveforms, Frequency, and RMS Values | 24 | lab | Students will use an oscilloscope to measure peak voltage, period, and frequency of an AC waveform and convert between peak, peak-to-peak, and RMS values using standard formulas. |
| Dual-trace oscilloscope (analog or digital storage); function generator; true-RMS digital multimeter; BNC-to-banana adapters; probe leads; lab log; NCCER Level 1 textbook; RMS conversion formula card | All six RMS calculations (three frequencies × two methods) within ±5% of each other; oscilloscope screenshots or sketches accurate and labeled; written explanation present and coherent. Instructor signs lab log. |
| 8 | Inductance, Inductive Reactance, and RL Circuits | 24 | lab | Students will calculate inductive reactance (XL = 2πfL) for a given inductor at two frequencies, measure the resulting impedance with a meter, and explain why voltage leads current by 90° in a pure inductor. |
| Known-value air-core inductors; resistors; AC bench power supply and/or function generator; dual-trace oscilloscope; true-RMS DMM; breadboard or terminal-strip trainer; lab log; NCCER Level 1 and Level 2 textbooks | Calculated XL vs. measured impedance within ±10% (inductor tolerance is wider than resistor); phase-lag sketch present and labeled correctly; lab log signed by instructor. Students with errors >10% must repeat the measurement with instructor guidance. |
| 9 | Capacitance, Capacitive Reactance, and RC Circuits | 22 | lab | Students will calculate capacitive reactance (XC = 1/2πfC), explain why current leads voltage in a capacitor, and measure the time constant (τ = RC) of a charging circuit using an oscilloscope. |
| Electrolytic and film capacitors (various values); resistors; function generator; dual-trace oscilloscope; true-RMS DMM; breadboard; lab log; NCCER Level 1 textbook; capacitor safety data (discharge warning for electrolytics) | Measured τ within ±15% of calculated value (capacitor tolerance accepted); XC comparison within ±10%; phasor diagram correctly labeled; lab log complete and signed. Students must demonstrate safe capacitor discharge procedure before handling electrolytics. |
| 10 | RLC Circuits, Resonance, and Power Factor | 24 | lab | Students will calculate impedance, power factor, true power, reactive power, and apparent power for a series RLC circuit at a given frequency, then verify results by measurement and identify the resonant frequency. |
| Resistors, inductors, and capacitors; AC bench power supply and function generator; true-RMS DMM; clamp-on ammeter; breadboard or trainer; scientific calculator; lab log; NCCER Level 1 and Level 2 textbooks; power-triangle reference card | Calculated vs. measured impedance within ±10%; power factor correct in sign and magnitude; resonant frequency identified and within ±15% of formula value; lab log complete and signed by instructor. |
| 11 | Three-Phase AC Systems | 30 | theory | Students will calculate line and phase voltages and currents for wye and delta configurations, explain why three-phase power is used in commercial and industrial construction, and read a three-phase phasor diagram correctly. |
| NCCER Electrical Level 2 textbook (three-phase chapter); animated phasor-diagram video; three-phase phasor-diagram printed worksheet; scientific calculator; whiteboard | Eight-problem calculation set scored by instructor: 7 of 8 correct required. Reference table checked for accuracy on all entries; peer-correction sheet reviewed by instructor. |
| 12 | Circuit Troubleshooting, Schematic Reading, and Review | 22 | practice | Students will trace current paths on unfamiliar DC and AC schematics, isolate an instructor-inserted fault in a multi-component circuit using a systematic half-split or voltage-drop method, and document the procedure in a written fault report. |
| Printed schematic packets; terminal-strip trainers with pre-inserted faults; digital multimeter; diagnostic-worksheet template; 30-question practice exam printout; NCCER Level 1 and Level 2 textbooks | All five schematics traced without errors (instructor spot-checks); fault located and documented with correct diagnostic steps on the worksheet; practice exam self-scored and submitted — score below 70% requires targeted review session before final exam. |
| Assessment | Type | Weight | Pass standard | Method & rubric |
|---|---|---|---|---|
| DC/AC Theory Knowledge Exam | Written exam | 25% | 75% correct (NCCER standard passing threshold for written module exams) | A 50-question written exam covering atomic structure, Ohm's Law, Kirchhoff's Laws, series and parallel DC circuits, AC waveform characteristics, RMS values, inductance, capacitance, RLC circuits, power factor, and three-phase systems — mapped directly to NCCER Electrical Level 1 and Level 2 module exam content areas. Questions are multiple-choice and short-answer; students have up to two attempts, with mandatory remediation between attempts. Standard met · Safety · Time · Quality/finish · Documentation |
| Circuit Build and Measurement Skills Demonstration | Skills demonstration | 45% | All five circuits built correctly with measurements within ±5% of calculated values; LOTO and PPE procedures followed without prompting — any safety violation is an automatic fail | Students receive a printed schematic packet with five circuits (one series DC, one parallel DC, one series-parallel DC, one RL AC, and one RC AC) and 45 minutes to build, measure, and record results for each on a structured score sheet. The evaluating instructor observes the entire demonstration, checking tool use, meter technique, and PPE compliance, then signs off on the completed measurement sheet. Standard met · Safety · Time · Quality/finish · Documentation |
| Cumulative Lab Log Portfolio | Log | 15% | All 12 lesson lab logs submitted, complete, legible, and signed; at least 10 of 12 logs with measurement accuracy within stated tolerances; no unsanctioned corrections (corrections must be single-lined and initialed) | Students maintain a bound lab log throughout the course in which they record pre-lab predictions, raw measurements, calculated values, percent-error analyses, phasor diagrams, oscilloscope sketches, and fault-diagnosis narratives for every lab and demo lesson. The portfolio is collected at the end of the course, reviewed against the lesson rubric, and returned with instructor comments; it serves as a professional documentation sample for the NCCER portfolio requirement. Standard met · Safety · Time · Quality/finish · Documentation |
| Electrical Safety and PPE Compliance Check | Safety audit | 15% | 100% on every required safety step — no partial credit; any missed step requires immediate remediation and a full re-check before the student may continue lab work | Conducted twice — once at the end of Lesson 1 and once unannounced during Lesson 9 or 10 — the instructor uses a standardized 15-item checklist to observe each student performing LOTO on a lab trainer, selecting and donning correct PPE, verifying absence of voltage, and demonstrating safe capacitor-discharge procedure. The checklist maps to OSHA 10 Construction safety topics and NCCER Electrical Level 1 safety module objectives. Standard met · Safety · Time · Quality/finish · Documentation |
This course develops the ability to locate, interpret, and apply the National Electrical Code (NEC) to residential, commercial, and industrial electrical installations. Students work directly from the current adopted edition of the NEC, learning article structure, definitions, wiring methods, protection requirements, and load calculations used daily on the job. Lesson content maps directly to NCCER Electrical Level 1–4 core knowledge areas and supports the electrical theory and code sections tested on state journeyman licensing exams.
OutcomesThis course develops the ability to locate, interpret, and apply the National Electrical Code (NEC) to residential, commercial, and industrial electrical installations. Students work directly from the current adopted edition of the NEC, learning article structure, definitions, wiring methods, protection requirements, and load calculations used daily on the job. Lesson content maps directly to NCCER Electrical Level 1–4 core knowledge areas and supports the electrical theory and code sections tested on state journeyman licensing exams.
How the course runs. 12 blocks: How the NEC Is Organized: Purpose, Scope, and Navigation; NEC Article 100 — Definitions That Drive Compliance; Chapters 1 and 2 — General Requirements and Wiring Design; Article 220 — Load Calculations for Residential Occupancies; Article 220 — Load Calculations for Small Commercial Occupancies; Chapter 3 — Wiring Methods: Cable Assemblies and Raceways; NEC Table 310 — Conductor Ampacity and Sizing; Overcurrent Protection — Articles 240 and 230; Grounding, Bonding, and Equipment Protection — Articles 250 and Related; GFCI, AFCI, and Special Protection Requirements; Reading Electrical Drawings and Panel Schedules for Code Compliance; Code Compliance Review: Integrated Case Study and Mock Inspection.
What competent looks like. Navigate the NEC article and section structure to locate any requirement within 3 minutes using the index and table of contents. Apply NEC Chapter 1 definitions, Chapter 2 wiring design rules, and Chapter 3 wiring method requirements to plan a code-compliant installation. Calculate branch-circuit, feeder, and service loads for a residential or small commercial occupancy using NEC Article 220 and standard load tables. Select and size conductors, overcurrent protective devices, conduit fill, and grounding/bonding components in accordance with applicable NEC tables and articles. Identify GFCI, AFCI, and equipment-grounding requirements for required locations under the NEC and explain the safety rationale for each. Read a set of electrical drawings and panel schedule, verify compliance with the NEC, and document any code deficiencies in writing.
| # | Lesson | Hr | Type | Objective | Activities | Materials | Check |
|---|---|---|---|---|---|---|---|
| 1 | How the NEC Is Organized: Purpose, Scope, and Navigation | 18 | theory | Students will locate any NEC requirement by using the code's chapter structure, article numbering system, index, and informational annexes. |
| Current adopted edition of the NFPA 70 (NEC) — one copy per student; NEC Quick-Card reference guide; highlighters and tabs; laptops or tablets with NFPA LiNK or equivalent digital code access | Timed navigation quiz: student finds 10 assigned code sections in under 15 minutes and states the mandatory requirement in plain language for each; 80% correct (8/10) to pass. |
| 2 | NEC Article 100 — Definitions That Drive Compliance | 20 | theory | Students will correctly define and distinguish the NEC Article 100 terms that appear most frequently in journeyman exam questions and field inspections. |
| NEC (current edition), Article 100; NCCER Electrical Level 1 module on electrical safety and theory; field photos of residential and commercial panels; index cards or digital flashcard app | Written definition quiz covering 20 Article 100 terms selected from the journeyman exam blueprint; student must score 80% or higher to proceed. |
| 3 | Chapters 1 and 2 — General Requirements and Wiring Design | 22 | theory | Students will apply NEC Articles 110, 200, 210, and 215 rules on working clearances, conductor identification, branch-circuit ratings, and feeder requirements to evaluate sample installation plans. |
| NEC Articles 110, 200, 210, 215; tape measure; chalk or painter's tape for mock panel area; assorted scrap wire and cable in multiple colors; residential floor plan handout; NCCER Electrical Level 2 wiring methods module | Completed branch-circuit planning worksheet reviewed by instructor; student must correctly rate and identify all circuits and cite the correct NEC article/section for each decision; 80% of items correct to pass. |
| 4 | Article 220 — Load Calculations for Residential Occupancies | 26 | theory | Students will complete a full Article 220 residential load calculation — general lighting, small appliance circuits, laundry, and major appliances — to size a service entrance correctly. |
| NEC Article 220 and associated tables; scientific calculator; load calculation worksheets (instructor-prepared); sample residential floor plans with appliance schedules; NCCER Electrical Level 2 load calculation section | Individual load calculation exam: student completes a full standard-method residential load calculation from a provided dwelling description; must arrive at the correct service size (within one standard service amperage step) and cite the correct table or section for every demand factor applied; 80% of calculation steps correct to pass. |
| 5 | Article 220 — Load Calculations for Small Commercial Occupancies | 22 | theory | Students will calculate the computed load for a small commercial occupancy (retail or office) using NEC Article 220 part III demand factors and size the service or feeder accordingly. |
| NEC Article 220 Part III and associated tables; commercial panel schedule handout; scientific calculator; NCCER Electrical Level 3 commercial wiring module; graph paper for panel schedule sketching | Graded commercial load calculation problem completed individually in class; correct service/feeder size with all demand factors applied and cited; 80% of steps correct to pass. |
| 6 | Chapter 3 — Wiring Methods: Cable Assemblies and Raceways | 24 | demo | Students will identify the permitted uses, prohibited uses, and installation requirements for the most common NEC Chapter 3 wiring methods — NM cable, AC cable, MC cable, EMT, rigid PVC, and RMC — by reading the applicable articles. |
| NEC Chapter 3 articles (e.g., 320, 330, 334, 342, 344, 352, 358); physical samples of each wiring method; NEC Annex C tables; installation scenario cards (instructor-prepared); NCCER Electrical Level 2 wiring methods module | Wiring method identification quiz: 15 scenario questions; student must identify a compliant wiring method and cite the article; 80% (12/15) correct to pass. |
| 7 | NEC Table 310 — Conductor Ampacity and Sizing | 22 | lab | Students will select the correct conductor size, insulation type, and ampacity correction/adjustment factors from NEC Table 310 and associated notes for a given circuit load and installation condition. |
| NEC Article 310 and Tables 310.12, 310.15, and associated correction/adjustment factor tables; scientific calculator; conductor sizing worksheets; assorted conductor samples labeled by AWG and insulation type | Conductor sizing lab sheet: all five scenarios graded; correct AWG, insulation type, and table references required for each; 80% of scenarios fully correct to pass. |
| 8 | Overcurrent Protection — Articles 240 and 230 | 22 | theory | Students will select the correct overcurrent protective device (fuse or circuit breaker) type, ampere rating, and interrupting rating for a given circuit, and identify NEC requirements for service entrance overcurrent protection. |
| NEC Articles 230 and 240; physical samples of fuses and circuit breakers (various types); load calculation from Lesson 4; NCCER Electrical Level 2 overcurrent protection section | Written quiz: 10 OCPd selection problems; student must choose the correct device type, standard ampere rating, and cite the applicable NEC section; 80% correct (8/10) to pass. |
| 9 | Grounding, Bonding, and Equipment Protection — Articles 250 and Related | 26 | lab | Students will distinguish between grounding and bonding, identify NEC Article 250 requirements for grounding electrode systems, equipment grounding conductors, and main bonding jumpers, and verify compliance on a sample service installation. |
| NEC Article 250; mock service entrance setup (instructor-built or commercial training board) with labeled grounding components; grounding electrode conductor sizing table (NEC Table 250.66); equipment grounding conductor sizing table (NEC Table 250.122); inspection photo handout with embedded violations | Compliance inspection worksheet: all five violations identified with correct code citations and corrections written; student must identify at least 4 of 5 violations with correct citations to pass. |
| 10 | GFCI, AFCI, and Special Protection Requirements | 20 | demo | Students will identify every NEC-required GFCI and AFCI location in a residential occupancy and explain the protection technology that makes each device effective. |
| NEC Articles 210.8 and 210.12; GFCI receptacles and GFCI breakers (samples); AFCI breakers (samples); GFCI outlet tester; residential floor plan handout; colored pencils or markers; NCCER Electrical Level 2 branch-circuit protection section | Color-coded floor plan reviewed by instructor: all NEC-required GFCI and AFCI locations correctly marked with article citations; no missed required locations and no false positives; 80% of required locations correct to pass. |
| 11 | Reading Electrical Drawings and Panel Schedules for Code Compliance | 24 | practice | Students will interpret a set of residential or light-commercial electrical drawings and a panel schedule, verify that the design meets NEC requirements, and document deficiencies in a written inspection report. |
| Full set of residential electrical drawings (instructor-prepared or from a public domain plan set); current NEC; NCCER Electrical Level 2 and 3 print reading sections; inspection report template; pencils and rulers | Inspection report graded for accuracy: student must identify at least 4 of the 6 seeded deficiencies with correct NEC citations and present one additional compliant item with explanation; 80% of seeded deficiencies found to pass. |
| 12 | Code Compliance Review: Integrated Case Study and Mock Inspection | 22 | practice | Students will apply all NEC content from the course to evaluate a complete residential installation case study — including load calculation, conductor sizing, OCPD selection, grounding, and protection device placement — and defend their findings in a structured oral review. |
| Integrated case study packet (instructor-prepared, unseen by students); current NEC; scientific calculator; peer review rubric; oral defense scoring rubric; all previously used reference tables | Oral defense rubric score: student must correctly cite NEC articles for at least 80% of decisions challenged during questioning and demonstrate the ability to look up any challenged section in the NEC in real time; 80% rubric score to pass. |
| Assessment | Type | Weight | Pass standard | Method & rubric |
|---|---|---|---|---|
| NEC Written Knowledge Examination | Written exam | 25% | 80% (40 of 50 questions correct) | A 50-question closed-book written exam covering NEC navigation, Article 100 definitions, load calculation principles, conductor sizing, OCPD selection, grounding and bonding, and GFCI/AFCI requirements; questions are drawn from NCCER Electrical Level 1–4 knowledge check items and representative state journeyman exam topics. Students may use a physical copy of the NEC (tabbed, highlighted, but not pre-answered) to reflect real open-book licensing exam conditions. Standard met · Safety · Time · Quality/finish · Documentation |
| Code Application Skills Demonstration | Skills demonstration | 45% | Instructor rates all five tasks as Satisfactory; any Unsatisfactory rating requires a single retake of that task within one week | The student is given an unseen residential installation scenario and must complete five tasks in sequence — NEC navigation to a specified requirement, load calculation, conductor and OCPD sizing, identification of all required GFCI/AFCI locations, and identification of a grounding electrode conductor size — with all answers cited to the correct NEC section. The instructor observes the process and scores each task on a Satisfactory/Unsatisfactory rubric. Standard met · Safety · Time · Quality/finish · Documentation |
| NEC Reference Log (Lab Log) | Log | 15% | Log is complete for all 12 lessons (no missing entries), at least 80% of cited section numbers verified as accurate by instructor review | Students maintain a cumulative NEC reference log throughout the course, recording for every lesson the code situations encountered, the article and section that applies, the mandatory rule in plain language, and a sketch or note illustrating the real-world application. The log is collected at the end of the course and reviewed for completeness, accuracy of citations, and quality of plain-language summaries. Standard met · Safety · Time · Quality/finish · Documentation |
| Electrical Safety and Code Safety Check | Safety audit | 15% | All critical safety items scored Compliant; any Non-Compliant item is an automatic failure requiring immediate remediation before the student may continue practical work | The instructor conducts a structured safety observation during the lab lessons (Lessons 7 and 9 in particular), using a checklist that covers: correct use of PPE when handling energized or recently energized equipment; proper lockout/tagout procedure acknowledgment when working on the mock service setup; correct identification of shock hazard zones around the simulated service entrance; and accurate verbal identification of the NEC's intent behind GFCI, AFCI, and grounding requirements as life-safety measures. The check is pass/fail on each line item. Standard met · Safety · Time · Quality/finish · Documentation |
Students master the layout, measurement, and hand-bending of electrical metallic tubing (EMT), intermediate metal conduit (IMC), and rigid metal conduit (RMC) using manual and mechanical benders, applying trade math and NEC installation requirements throughout. Emphasis is placed on producing code-compliant conduit runs with accurate offsets, saddles, back-to-back bends, and stub-ups in realistic residential and commercial framing scenarios. Safe work practices, proper PPE, and OSHA requirements govern every lab session.
OutcomesStudents master the layout, measurement, and hand-bending of electrical metallic tubing (EMT), intermediate metal conduit (IMC), and rigid metal conduit (RMC) using manual and mechanical benders, applying trade math and NEC installation requirements throughout. Emphasis is placed on producing code-compliant conduit runs with accurate offsets, saddles, back-to-back bends, and stub-ups in realistic residential and commercial framing scenarios. Safe work practices, proper PPE, and OSHA requirements govern every lab session.
How the course runs. 12 blocks: Conduit Types, Properties, and NEC Installation Requirements; Trade Math for Bending: Developed Length, Multipliers, and Shrink; Safety and OSHA Requirements for Conduit Work; Hand Bender Fundamentals: 90-Degree Stub-Ups in EMT; Offsets: Calculation, Layout, and Hand Bending; Back-to-Back Bends and Four-Point Saddles; Mechanical and Hydraulic Benders: IMC and RMC; Conduit Threading, Reaming, and Coupling Assembly for RMC; Reading Conduit Drawings, Schedules, and Riser Diagrams; Conduit Support, Strapping, and Penetration Sealing; Wire Pulling Through Conduit Systems; Conduit System Integration: Full-Run Design, Bend, Install, and Document.
What competent looks like. Calculate and lay out accurate 90-degree stubs, offsets, saddles, and back-to-back bends using developed-length formulas and the multiplier method for EMT, IMC, and RMC. Operate hand benders, mechanical (Chicago-type) benders, and hydraulic benders safely and correctly to produce bends within industry-accepted tolerances. Apply relevant NEC requirements governing conduit fill, bend radius, number of bends per run, and support spacing when designing and installing conduit systems. Read and interpret construction drawings, riser diagrams, and conduit schedules to plan and execute a complete multi-conduit run with correct terminations. Demonstrate lockout/tagout procedures, proper PPE selection, and safe material-handling practices for conduit installation work on active construction sites. Produce accurate field sketches and conduit schedules documenting a completed conduit system, consistent with documentation practices required by NCCER Electrical curriculum.
| # | Lesson | Hr | Type | Objective | Activities | Materials | Check |
|---|---|---|---|---|---|---|---|
| 1 | Conduit Types, Properties, and NEC Installation Requirements | 16 | theory | Students identify EMT, IMC, RMC, PVC, and FMC by physical characteristics, list NEC requirements for trade size selection, conduit fill, bend count, and support spacing, and match conduit type to occupancy and environment. |
| Sample conduit section board (EMT, IMC, RMC, PVC, FMC in ½″–2″ trade sizes), dial calipers, current NFPA 70 NEC codebook, NEC Annex C fill-table worksheets, NCCER Electrical Level 1 & 2 modules on raceways | 10-question written quiz on conduit types and NEC fill/support rules; 80% or higher to pass. |
| 2 | Trade Math for Bending: Developed Length, Multipliers, and Shrink | 24 | theory | Students apply trigonometry-based multipliers, shrink constants, and developed-length formulas to calculate cutting lengths and bend marks for stubs, offsets, and saddles before touching a bender. |
| Scientific calculators, multiplier and shrink-constant reference card (NCCER), graph paper, tape measures, sample bent EMT pieces, whiteboard for instructor demonstration | Math problem set graded by instructor; all 12 problems must be set up correctly with final answer within ±1/8″ of the accepted solution; 80% score to pass. |
| 3 | Safety and OSHA Requirements for Conduit Work | 16 | theory | Students identify all OSHA and site safety requirements specific to conduit installation—PPE, lockout/tagout, manual material handling, elevated work, and struck-by hazards—and correctly demonstrate a LOTO procedure before beginning any lab. |
| OSHA 10 Construction outreach reference cards, LOTO station mock-up with hasp and locks, non-contact voltage tester, LOTO permit forms, PPE samples (glasses, gloves, hard hat, boots), instructor-developed hazard-identification checklist | LOTO procedure performed in correct sequence with zero steps skipped; all PPE correctly identified for each sub-task; any missed critical safety step requires repeat demonstration before proceeding to lab sessions. |
| 4 | Hand Bender Fundamentals: 90-Degree Stub-Ups in EMT | 28 | lab | Students use a hand bender to produce a 90-degree stub-up in ½″ and ¾″ EMT that lands within ±¼″ of a specified finished stub height with no kinks, flattening, or dog-legs. |
| Klein and Ideal hand benders (½″ and ¾″ sets), ½″ and ¾″ EMT stock (pre-cut 10-foot sticks), tape measures, combination squares, pipe cutters, de-burring reamers, safety glasses, leather gloves, student bending logs | Final stub-up graded by instructor: 90° ± 2°, stub height within ±¼″ of target, no visible kinks or flattening; two passing bends per trade size required to advance. |
| 5 | Offsets: Calculation, Layout, and Hand Bending | 28 | lab | Students calculate shrink and mark positions, then hand-bend accurate two-bend offsets in ½″ and ¾″ EMT at 22½°, 30°, and 45° to clear obstacles of specified heights without introducing twists or dog-legs. |
| Hand benders, ½″ and ¾″ EMT, tape measures, torpedo levels, combination squares, pre-drilled plywood offset-practice panel, multiplier reference cards, bending logs, pipe cutters, reamers | Offset height within ±¼″, legs parallel within 2° per torpedo level, no visible twist; instructor measures all three dimensions; must pass two of three offset sizes to advance. |
| 6 | Back-to-Back Bends and Four-Point Saddles | 24 | lab | Students lay out and bend accurate back-to-back 90-degree bends and four-point saddles in ¾″ EMT to bridge a round obstacle, with each segment length within ±¼″ of the design dimension. |
| Hand benders, ¾″ EMT, tape measures, 2″ pipe obstacle clamped to workbench, combination squares, bending logs, markers, pipe cutters, reamers, safety glasses | Back-to-back center-to-center within ±¼″; four-point saddle seats flush on round pipe with less than 1/8″ gap at any contact point; instructor verifies both; one passing attempt of each type required. |
| 7 | Mechanical and Hydraulic Benders: IMC and RMC | 28 | demo | Students safely set up and operate a mechanical (Chicago-type) bender and a hydraulic bender to produce 90-degree bends and offsets in 1″ IMC and 1″ RMC within accepted tolerances. |
| Mechanical (Chicago-type) bender with 1″ shoe set, hydraulic bender with 1″ die, 1″ IMC and RMC stock, tape measures, combination squares, torpedo levels, inspection checklists, bending logs, PPE (safety glasses, gloves, steel-toed boots) | Pre-operation inspection checklist completed with zero critical items missed; 90° stub within ±¼″ height and ±2° angle; offset within ±¼″ height; instructor signs off bending log after observing each student operate both machines. |
| 8 | Conduit Threading, Reaming, and Coupling Assembly for RMC | 20 | lab | Students cut, ream, thread, and couple rigid metal conduit using a threading machine and hand dies, producing NPT threads that engage a coupling fully without cross-threading or insufficient thread engagement. |
| 1″ RMC stock, pipe cutters, reamer, hand die set (1″ NPT), power threading machine with 1″ die head, cutting oil, pipe wrenches, ring gauges or coupling samples, pipe joint compound, safety glasses, gloves, face shield for threading machine | Threads engage coupling at least 3 full threads with hand pressure; coupling can be run to full engagement with wrench without cross-threading; instructor checks each threaded end; any stripped or inadequate threads must be re-cut on a new section. |
| 9 | Reading Conduit Drawings, Schedules, and Riser Diagrams | 20 | theory | Students interpret a full set of electrical construction drawings including a floor plan, conduit schedule, and riser diagram to extract conduit type, trade size, routing, and support requirements needed to plan a real installation. |
| Sample commercial electrical drawings (floor plan, riser, conduit schedule), architectural drawing set for coordination reference, architectural scale rules, conduit schedule templates, pencils, current NEC codebook | Conduit schedule completed with correct type, size, and routing for all runs (checked against answer key); minimum 80% accuracy; drawing mark-up reviewed by instructor for code-compliant routing. |
| 10 | Conduit Support, Strapping, and Penetration Sealing | 20 | lab | Students install EMT and RMC conduit runs on a framed wall mock-up using correct straps, hangers, and support spacing per NEC requirements, and properly seal conduit penetrations through a fire-rated assembly. |
| Metal stud framed wall mock-up, ½″ and ¾″ EMT and 1″ RMC, one-hole and two-hole straps, unistrut channel, conduit clamps, threaded rod hangers, nuts and bolts, drill with bits, listed firestop putty, torpedo level, tape measure, NEC codebook, PPE | Supports placed within NEC-required spacing (no unsupported span exceeds the code maximum for each conduit type and size); penetration sealed with zero visible gap; instructor measures all span distances and inspects seal; any violation must be corrected. |
| 11 | Wire Pulling Through Conduit Systems | 24 | lab | Students calculate conductor fill, pull string through a completed multi-bend conduit run, and hand-pull THWN conductors without damaging insulation, using pulling lubricant and documenting pull tension observations. |
| Completed conduit run assemblies from prior labs (EMT, ¾″), pull string, pulling grip or electrical tape, THWN 12 AWG conductors, listed wire-pulling lubricant, NEC Annex C fill tables, clean cloths, bending logs, pipe putty for open conduit ends | Fill calculation verified correct by instructor before pulling begins; conductors pulled completely through without damage; cloth inspection reveals no discoloration or torn insulation; student documents pull in bending log with instructor initials. |
| 12 | Conduit System Integration: Full-Run Design, Bend, Install, and Document | 20 | practice | Students independently design, calculate, bend, install, and document a complete conduit system—including at least one 90° stub, one offset, and one saddle—connecting two panel locations on a full-size mock-up wall, producing a conduit schedule and as-built sketch. |
| Full-size mock-up wall with panel knockout locations, hand benders, EMT and IMC stock, pipe cutters, reamers, straps, drill, conductors, pull string, lubricant, tape measure, combination square, graph paper, ruler, NEC codebook, bending log | All bends within ±¼″ of design dimensions; conduit schedule accurate and complete; as-built sketch legible and dimensionally consistent with installed run; 5-minute stand-up explanation addresses all instructor questions; instructor uses a 10-point rubric with 80% required to pass. |
| Assessment | Type | Weight | Pass standard | Method & rubric |
|---|---|---|---|---|
| Conduit Bending Theory and Code Written Exam | Written exam | 25% | 80% or higher (32 of 40 questions correct) | A 40-question closed-book exam covering conduit types and applications, NEC fill and support requirements, multiplier and developed-length math, threading standards, and conduit-drawing interpretation, aligned to NCCER Electrical Level 2 knowledge areas on raceways and conduit bending. Standard met · Safety · Time · Quality/finish · Documentation |
| Practical Bending Skills Demonstration | Skills demonstration | 45% | All four bends must meet dimensional tolerance; any single failing bend requires one remedial attempt before a second evaluation | Each student produces four bends—a 90° stub-up in ¾″ EMT, a 30° offset in ¾″ EMT, a four-point saddle in ¾″ EMT, and a 90° bend in 1″ IMC on the mechanical bender—evaluated by the instructor against a dimensional rubric (stub height ±¼″, angle ±2°, no kinks or dog-legs), directly matching NCCER Electrical Level 2 performance task requirements. Standard met · Safety · Time · Quality/finish · Documentation |
| Bending and Installation Lab Log | Log | 15% | Log accepted when all 12 lesson entries are present, all calculations are shown with correct units, and instructor initials appear on each entry; incomplete or uncorrected entries are returned for revision before passing | Students maintain a running bending log throughout the course recording all pre-bend calculations, measured results, percent errors, NEC references used, and reflections on technique corrections; the complete log is submitted at course end and reviewed for accuracy, completeness, and evidence of learning from errors. Standard met · Safety · Time · Quality/finish · Documentation |
| Safety and LOTO Compliance Check | Safety audit | 15% | 100% on all critical safety steps; any missed critical step is an automatic fail requiring full repeat of the safety demonstration before the student may continue lab work | Instructor observes each student perform a complete lockout/tagout sequence on the panel mock-up, verify absence of voltage with a non-contact tester, don correct PPE for a conduit-cutting task, and state the NEC or OSHA requirement for one randomly selected safety scenario; this check is administered before the Practical Bending Skills Demonstration and must be passed first. Standard met · Safety · Time · Quality/finish · Documentation |
Students apply NEC-compliant wiring methods to both residential and light-commercial installations, from rough-in through finish trim, using cable assemblies, conduit systems, and device wiring. Emphasis is placed on box fill calculations, circuit layout, load calculations, and safe work practices consistent with OSHA 10 standards. This course bridges code knowledge and conduit skills learned previously into complete, inspectable electrical systems.
OutcomesStudents apply NEC-compliant wiring methods to both residential and light-commercial installations, from rough-in through finish trim, using cable assemblies, conduit systems, and device wiring. Emphasis is placed on box fill calculations, circuit layout, load calculations, and safe work practices consistent with OSHA 10 standards. This course bridges code knowledge and conduit skills learned previously into complete, inspectable electrical systems.
How the course runs. 12 blocks: Residential Wiring Systems Overview and Job-Site Safety Review; Reading Residential Electrical Plans and Specifications; NEC Branch-Circuit Requirements and Box Fill Calculations; Residential Rough-In: Cable Installation with NM-B Cable; Device Wiring: Receptacles, Switches, GFCI, and AFCI Devices; Luminaire Installation: Recessed, Surface, and Ceiling Fan Boxes; Residential Service Entrance and Panel Load Calculations; Panel Wiring: Circuit Breaker Installation and Panel Schedule; Light-Commercial Wiring: EMT Branch Circuits and Feeders; Commercial Device Wiring: 20-Amp Commercial-Grade Devices, Exit and Emergency Lighting; Wiring Deficiencies, Troubleshooting, and Inspection Readiness; Integrated Wiring Project: Plan, Build, and Inspect a Complete Rough-In and Trim-Out.
What competent looks like. Plan and execute a complete residential branch-circuit rough-in, including proper box placement, cable routing, and stapling intervals per NEC Article 334 requirements. Wire and trim out receptacles, switches, GFCI and AFCI devices, luminaires, and panels in residential and light-commercial occupancies to NEC standards. Perform service-entrance and panel load calculations for a single-family dwelling using NEC Article 220 methods. Install branch circuits and feeders in a light-commercial occupancy using EMT conduit, including proper support, connections, and wire fill per NEC Chapter 3. Identify and correct common wiring deficiencies that cause failed rough-in and final inspections. Demonstrate safe working procedures—including lockout/tagout, appropriate PPE, and first-aid awareness—throughout all wiring tasks.
| # | Lesson | Hr | Type | Objective | Activities | Materials | Check |
|---|---|---|---|---|---|---|---|
| 1 | Residential Wiring Systems Overview and Job-Site Safety Review | 14.5 | theory | Students will describe the components of a residential wiring system and apply OSHA 10 and site-specific safety rules—including PPE selection, lockout/tagout, and fall protection—to residential wiring tasks. |
| Sample residential electrical plan set, OSHA 29 CFR 1926 Subpart K summary card, NFPA 70 (NEC) current edition, NCCER Electrical Level 1–2 trainee guides, PPE samples (safety glasses, gloves, hard hat, GFCI-protected extension cord), whiteboard | 10-question written quiz covering system components, PPE selection, and LOTO steps; passing score 70%. |
| 2 | Reading Residential Electrical Plans and Specifications | 16 | theory | Students will interpret a complete set of residential electrical drawings and specifications to identify circuit quantities, panel schedules, device locations, and wiring notes. |
| Full-size residential electrical plan set (minimum 1,500 sq ft house), architectural scale ruler, highlighters, NEC current edition, NCCER Electrical Level 2 trainee guide, takeoff worksheet | Completed takeoff worksheet checked against instructor answer key; all quantities within ±5% and all circuit breaker sizes correct for 100% pass. |
| 3 | NEC Branch-Circuit Requirements and Box Fill Calculations | 20 | theory | Students will apply NEC Articles 210 and 314 to determine required circuit quantities, receptacle placement rules, and box fill for residential and light-commercial branch circuits. |
| NEC current edition (Articles 210, 314), sample assortment of electrical boxes (single-gang, double-gang, 4-inch square, old-work), conductors (12 AWG and 14 AWG scrap), box fill calculation worksheet, calculator | Eight-problem box fill quiz; all eight answers correct using correct NEC table references for 100% pass (any error triggers remediation and retest). |
| 4 | Residential Rough-In: Cable Installation with NM-B Cable | 25 | lab | Students will rough-in branch circuits in a framed wall mock-up using NM-B cable, meeting NEC stapling, bending, and protection requirements and passing a simulated rough-in inspection checklist. |
| Framed wall mock-ups (2×4 stud, 8 ft), NM-B cable 14/2, 12/2, and 12/3, plastic boxes (new-work), hammer, drill with spade bits, cable staples, nail plates, tape measure, NEC current edition, rough-in inspection checklist | Rough-in inspection checklist: all items must pass (no stapling violations, correct hole depths, nail plates installed, cable secured within required distance of boxes); any failed item requires correction before sign-off. |
| 5 | Device Wiring: Receptacles, Switches, GFCI, and AFCI Devices | 21.5 | lab | Students will correctly wire standard receptacles, single-pole and three-way switches, GFCI receptacles, and AFCI breakers and verify device operation with a plug-in tester and multimeter. |
| Device wiring boards (pre-drilled plywood panels with boxes), duplex receptacles, GFCI receptacles, AFCI breakers, single-pole and three-way switches, 14/2 and 14/3 NM-B, plug-in circuit tester, digital multimeter, NEC current edition, NCCER Electrical Level 2 trainee guide | All eight wiring stations verified with plug-in tester showing correct polarity and ground, GFCI trips on TEST, AFCI breaker installs without nuisance trip; lab log entries show correct multimeter readings (120 V ±5%). All stations must pass. |
| 6 | Luminaire Installation: Recessed, Surface, and Ceiling Fan Boxes | 18 | demo | Students will install recessed IC-rated fixtures, surface-mounted luminaires, and ceiling-fan-rated boxes in compliance with NEC Articles 410 and 314, including correct support and wiring connections. |
| Ceiling mock-up (framed joist section), IC-rated and non-IC recessed housings, ceiling-fan-rated adjustable brace bar, surface-mount luminaire, wire connectors, 14/2 NM-B, NEC current edition (Articles 314, 410), luminaire installation checklist | Instructor checklist: correct box rating for application, all connections secure (pull test—no loosening), luminaire trim installed flush; all three items pass required for sign-off. |
| 7 | Residential Service Entrance and Panel Load Calculations | 23.5 | theory | Students will perform a standard method load calculation for a single-family dwelling per NEC Article 220 and select a service size to serve that load. |
| NEC current edition (Article 220, Tables 220.12, 220.42, 220.55, 220.82), load calculation worksheet, calculator, sample house data sheet, NCCER Electrical Level 3 trainee guide | Completed load calculation worksheet: final ampacity within ±5% of instructor answer key and correct service size selected; any arithmetic error that changes the service size requires full remediation and retest. |
| 8 | Panel Wiring: Circuit Breaker Installation and Panel Schedule | 20 | lab | Students will land branch-circuit conductors in a residential load center, install breakers of specified sizes and types, and complete an accurate panel schedule matching the circuit layout. |
| 200-amp residential load centers (one per student or pair), assorted breakers (15 A, 20 A single-pole; 30 A double-pole), conductors (14 AWG, 12 AWG, 10 AWG), LOTO locks and tags, plastic cable ties, panel schedule form, torque screwdriver, NEC current edition, NCCER Electrical Level 2 trainee guide | All conductors landed at correct breaker size and torqued to manufacturer specification; panel schedule matches wiring with no errors; LOTO procedure followed throughout (observed by instructor). Any untorqued connection or LOTO violation = immediate stop and full remediation. |
| 9 | Light-Commercial Wiring: EMT Branch Circuits and Feeders | 32.5 | lab | Students will install a light-commercial branch-circuit and feeder system in EMT conduit—including supports, couplings, connectors, and wire pulling—meeting NEC Chapter 3 and Article 358 requirements. |
| EMT conduit (½-inch and ¾-inch), threadless couplings and connectors, EMT straps and hangers, fish tape, wire-pulling lubricant, THWN-2 conductors (12 AWG), commercial panel mock-up, NEC current edition (Article 358, Chapter 9 tables), digital multimeter, commercial rough-in checklist | Light-commercial rough-in checklist: supports within required spacing, all fittings tight, ground continuity <1 ohm end-to-end on multimeter, no insulation damage visible; all items pass required for sign-off. |
| 10 | Commercial Device Wiring: 20-Amp Commercial-Grade Devices, Exit and Emergency Lighting | 20 | lab | Students will wire 20-amp commercial-grade receptacles, exit signs with battery backup, and emergency lighting units correctly and verify operation per manufacturer instructions. |
| Commercial-grade 20-amp duplex receptacles, exit sign with battery backup, emergency lighting unit, 12/2 THWN-2, junction boxes, digital multimeter, NEC current edition (Articles 406, 700), lab log forms | All devices operate correctly under normal power; emergency units illuminate within required time after power interruption (per manufacturer specification); lab log entries complete. Any wiring error must be corrected and retested before sign-off. |
| 11 | Wiring Deficiencies, Troubleshooting, and Inspection Readiness | 18 | practice | Students will identify, diagnose, and correct a minimum of eight NEC-code and workmanship deficiencies planted in a residential/commercial mock-up wiring installation. |
| Pre-wired deficiency mock-up, deficiency log form, NEC current edition, hand tools, digital multimeter, plug-in circuit tester, inspection checklist | Students must correctly identify and document at least 8 of 10 deficiencies with correct NEC citation, and physically correct all identified deficiencies; fewer than 8 requires remediation. |
| 12 | Integrated Wiring Project: Plan, Build, and Inspect a Complete Rough-In and Trim-Out | 39 | lab | Students will independently plan, rough-in, trim out, and submit for mock inspection a complete wiring installation—including panel, branch circuits, devices, and luminaires—for a supplied residential/light-commercial floor plan, demonstrating integrated mastery of all course skills. |
| Assigned floor plan and panel schedule template, full tool kit (drills, fish tape, conduit benders, hand tools), NM-B and EMT materials, load center, breakers, devices, luminaires, NEC current edition, box fill and load calculation worksheets, daily work log, inspection checklist | Mock inspection checklist: zero unresolved deficiencies after corrections; plan package complete and accurate (load calc within ±5%, all box fills correct); daily work log complete; inspector sign-off required to pass. |
| Assessment | Type | Weight | Pass standard | Method & rubric |
|---|---|---|---|---|
| Written Knowledge Exam: NEC Requirements and Wiring Theory | Written exam | 25% | 70% or higher | A 60-question multiple-choice exam drawn from NEC Articles 210, 220, 314, 334, 358, 406, and 410, covering branch-circuit requirements, box fill, load calculations, cable and conduit wiring methods, device ratings, and luminaire installation rules. Questions are aligned with NCCER Electrical Levels 2 and 3 module exam content areas and State Journeyman Electrician exam topic domains. Standard met · Safety · Time · Quality/finish · Documentation |
| Skills Demonstration: Device Wiring and Panel Landing | Skills demonstration | 45% | All required tasks completed correctly with no unresolved errors; LOTO procedure followed throughout | The student wires a GFCI receptacle, a three-way switch pair, and an AFCI breaker on a dead panel section within a set time limit, with LOTO applied and verified before any panel work begins; the instructor uses a standardized task checklist and a plug-in circuit tester to verify correct polarity, ground, GFCI trip function, and torque on all breaker and neutral/ground connections. Standard met · Safety · Time · Quality/finish · Documentation |
| Lab Log Portfolio | Log | 15% | All 12 lesson entries present; at least 10 of 12 entries rated Satisfactory or above on the rubric | Students maintain a running lab log throughout the course documenting materials used, NEC sections applied, measurements and test readings recorded, and any deficiencies found and corrected in each lab or practice session; entries are evaluated on completeness, accuracy of NEC citations, and legibility using a four-level rubric (Excellent, Satisfactory, Needs Revision, Unsatisfactory). Standard met · Safety · Time · Quality/finish · Documentation |
| Safety Compliance Check | Safety audit | 15% | Zero critical safety violations across all observed sessions; 100% on final PPE and LOTO checklist | The instructor records any safety violation observed during labs and practice sessions throughout the course using an incident log; at course end, the student completes a live PPE selection and LOTO demonstration on a de-energized panel with the instructor scoring each step on a binary pass/fail checklist—any single critical violation (working on energized conductors without authorization, missing LOTO lock, no eye protection when drilling) during the course requires an immediate safety conference and documented remediation plan before the student may continue. Standard met · Safety · Time · Quality/finish · Documentation |
Students learn to select, install, wire, and troubleshoot single-phase and three-phase AC motors along with the motor control circuits—contactors, starters, relays, and variable-frequency drives—that govern them in commercial and industrial settings. Instruction follows NEC Article 430 requirements and NCCER Electrical Level 2 and Level 3 motor and controls content. Emphasis is placed on safe lockout/tagout practice, proper PPE selection for energized work, and systematic troubleshooting using schematics and ladder logic.
OutcomesStudents learn to select, install, wire, and troubleshoot single-phase and three-phase AC motors along with the motor control circuits—contactors, starters, relays, and variable-frequency drives—that govern them in commercial and industrial settings. Instruction follows NEC Article 430 requirements and NCCER Electrical Level 2 and Level 3 motor and controls content. Emphasis is placed on safe lockout/tagout practice, proper PPE selection for energized work, and systematic troubleshooting using schematics and ladder logic.
How the course runs. 12 blocks: Motor Theory and Nameplate Data; LOTO and Electrical Safety for Motor Work; NEC Article 430 — Sizing and Code Compliance; Schematic and Wiring Diagram Reading; Contactors, Starters, and Overload Relays — Installation Lab; Reversing Starters and Interlocking; Pilot Devices and Control Circuits; Reduced-Voltage and Soft-Start Methods; Variable-Frequency Drive (VFD) — Principles and Parameter Setting; VFD Installation, Wiring, and Fault Diagnosis; Motor Troubleshooting Methods; Integrated Motors & Controls Project.
What competent looks like. Identify, connect, and verify the operation of single-phase and three-phase AC motors in accordance with nameplate data and NEC Article 430. Read and draw motor control schematic and wiring diagrams, including ladder logic for two-wire, three-wire, and reversing starter circuits. Select and size motor branch-circuit conductors, overcurrent protection, and disconnecting means using NEC Article 430 tables. Install and wire magnetic contactors, motor starters, overload relays, push-button stations, and pilot devices following manufacturer specifications and applicable code. Program and commission a variable-frequency drive for a basic speed-control application and interpret drive fault codes. Apply lockout/tagout procedures and appropriate PPE before any work on motor or control circuits and document each step in a written LOTO record.
| # | Lesson | Hr | Type | Objective | Activities | Materials | Check |
|---|---|---|---|---|---|---|---|
| 1 | Motor Theory and Nameplate Data | 17 | theory | Students interpret AC motor nameplate data—voltage, FLA, service factor, insulation class, and NEMA frame—to determine correct application and NEC sizing requirements. |
| NCCER Electrical Level 2 and Level 3 modules on motors; current NEC codebook (Article 430); assorted motor nameplates or laminated facsimiles; NEC Table 430.52 and Table 430.250 handouts; dry-erase boards | Nameplate worksheet scored against answer key; student must correctly size conductors, overcurrent protection, and disconnect for at least 4 of 5 motors (80%) to pass. |
| 2 | LOTO and Electrical Safety for Motor Work | 18.5 | demo | Students demonstrate a complete NFPA 70E- and OSHA 29 CFR 1910.147-compliant lockout/tagout sequence on a de-energized motor control panel before any hands-on motor wiring begins. |
| Training motor control panel with lockable disconnect; personal locks and tags (one per student); calibrated non-contact voltage tester; clamp-type ammeter; NFPA 70E current edition reference; OSHA 29 CFR 1910.147 summary card; arc-flash PPE set (Class 00 gloves, face shield, FR shirt and pants) | Instructor-observed LOTO checklist: all six steps performed in correct order with zero omissions; any missed step = immediate repeat; must pass before progressing to wiring labs. |
| 3 | NEC Article 430 — Sizing and Code Compliance | 20.5 | theory | Students apply NEC Article 430 to calculate branch-circuit conductor ampacity, select overcurrent protection devices, and size disconnecting means for a given motor load. |
| Current NEC codebook; NCCER Electrical Level 2 Motors module; NEC Tables 430.52, 430.248, 430.250, 430.52 (condensed handout); scientific calculators | Eight-problem quiz scored by instructor; minimum 80% (7 of 8 correct) required; students who score below 80% complete an alternate problem set with instructor coaching before the next lesson. |
| 4 | Schematic and Wiring Diagram Reading | 18.5 | theory | Students trace current flow through ladder-logic schematic diagrams and translate them into wiring diagrams for two-wire and three-wire motor control circuits. |
| Printed schematic packets; NCCER Electrical Level 2 motor controls module; colored pencils; blank wiring diagram templates; Allen-Bradley or similar catalog for contactor terminal identification | Diagram translation reviewed by instructor; student must correctly identify all current paths and produce a wiring diagram with no crossed-polarity or missing connections (100% accuracy on safety-critical connections; 80% overall). |
| 5 | Contactors, Starters, and Overload Relays — Installation Lab | 24 | lab | Students wire a full-voltage magnetic starter with a thermal overload relay to a three-phase motor using a provided schematic, then verify correct operation and overload trip. |
| NEMA size-1 magnetic starter with integral overload relay; 120 V control transformer; start-stop push-button station; three-phase training motor (fractional or 1 HP); training panel board; insulated screwdrivers; wire strippers; 14 AWG THHN wire; clamp ammeter; multimeter; ladder diagram handout | Instructor inspects wiring for correct terminal connections, conductor routing, and secure terminations before energizing (100% safety check); functional test: motor starts and stops on command and overload trips within one attempt; any wiring fault must be corrected and retested. |
| 6 | Reversing Starters and Interlocking | 22.5 | lab | Students wire a forward-reverse motor starter circuit with both mechanical and electrical interlocks to prevent simultaneous closure of forward and reverse contactors. |
| Two NEMA-size 1 contactors with mechanically interlocked mounting kit; overload relay; forward-reverse-stop push-button station; three-phase training motor; training panel; wiring materials; multimeter; reversing starter schematic | Pre-energization continuity check by instructor (zero tolerance for missing interlock wiring); operational test: all three functions demonstrated correctly; lab log entry complete with diagram sketch and test data — pass requires all functions correct. |
| 7 | Pilot Devices and Control Circuits | 18.5 | demo | Students connect and test a variety of pilot devices—limit switches, pressure switches, float switches, and photoelectric sensors—as discrete inputs that control a motor starter coil. |
| Control circuit trainers (one per station); limit switch; pressure switch (pneumatic simulator); float switch; photoelectric sensor and reflector; NCCER Electrical Level 2 motor controls module; wiring materials; multimeters | Instructor observes each station; motor must respond correctly to pilot device actuation; application matching exercise scored at 80% minimum (4 of 5 correct). |
| 8 | Reduced-Voltage and Soft-Start Methods | 17 | theory | Students explain the purpose of reduced-voltage starting, describe star-delta and part-winding starter operation, and identify the conditions under which a solid-state soft starter is selected. |
| NCCER Electrical Level 3 motor controls module; manufacturer soft-starter and star-delta technical documentation; comparison chart worksheet; projector for video; calculators | Comparison chart and scenario defense reviewed; student must correctly identify the starting method and provide a valid technical reason for all five scenarios (100%) to pass; minor calculation errors acceptable if reasoning is sound. |
| 9 | Variable-Frequency Drive (VFD) — Principles and Parameter Setting | 26 | demo | Students program a variable-frequency drive with basic parameters—motor nameplate data, acceleration/deceleration ramps, minimum and maximum frequency—and run a motor through a defined speed profile. |
| Training VFD (1–2 HP, suitable for 208–240 V three-phase training motor); three-phase training motor; parameter checklist handout; tachometer; clamp ammeter; manufacturer VFD programming manual; NCCER Electrical Level 3 motor controls module | Parameter checklist signed off by instructor; speed profile test: measured RPM within 5% of calculated value at each frequency; all three speeds verified — pass requires all three within tolerance. |
| 10 | VFD Installation, Wiring, and Fault Diagnosis | 24 | lab | Students install and wire a variable-frequency drive in a training enclosure per the manufacturer's wiring diagram and NEC requirements, then diagnose and clear three simulated drive faults. |
| Training VFD with remote keypad option; three-phase training motor; training enclosure; conduit and fittings; THHN wire; disconnect switch; fuses; speed potentiometer; manufacturer fault code reference; lab log forms; multimeter | Wiring inspected by instructor before energizing (all input/output conductor separation requirements met — zero tolerance error); all three faults correctly identified and cleared with documented lab log entries; pass requires correct fault diagnosis and corrective action on all three faults. |
| 11 | Motor Troubleshooting Methods | 30 | practice | Students use a systematic, meter-based troubleshooting process to locate and document faults in motor windings and control circuits within 20 minutes per scenario. |
| Six pre-faulted motor/control training stations; digital multimeter; 500 V megohmmeter; clamp ammeter; LOTO kit; personal PPE; troubleshooting procedure card; lab log forms | Timed competency round: correct fault identified and repair described within 20 minutes with LOTO applied throughout — pass requires correct diagnosis and no LOTO violations; LOTO violation = automatic fail and repeat. |
| 12 | Integrated Motors & Controls Project | 31.5 | lab | Students design, wire, test, and document a complete motor control system—full-voltage reversing starter with pilot device and VFD speed control—from a project specification sheet, then present their work. |
| Reversing contactor set; overload relay; VFD; three-phase training motor; pilot device of student choice; push-button station; training enclosure and panel; complete wiring materials; NEC codebook; multimeter; clamp ammeter; tachometer; project specification sheet; documentation template | Pre-energization wiring inspection by instructor (100% pass required before energizing); all specified functions operate correctly on first or second attempt; written summary and oral defense scored on a rubric (NEC calculations correct, diagram accurate, test data recorded, safety steps described) — minimum 80% on rubric to pass. |
| Assessment | Type | Weight | Pass standard | Method & rubric |
|---|---|---|---|---|
| Motors & Controls Written Exam | Written exam | 25% | 80% (40 of 50 questions correct) | A 50-question written exam covering motor theory, nameplate interpretation, NEC Article 430 sizing, schematic diagram reading, starter types, VFD operation, and troubleshooting principles, aligned to NCCER Electrical Level 2 and Level 3 motor and controls module objectives. Questions are multiple-choice and short-answer; students may use a tabbed NEC codebook. Standard met · Safety · Time · Quality/finish · Documentation |
| Practical Skills Demonstration | Skills demonstration | 45% | All critical safety steps (LOTO, PPE, pre-energization inspection) completed without error; all specified circuit functions correct on first or second attempt; any LOTO violation = automatic fail | The instructor assigns each student a novel motor control wiring task—chosen from among two-wire control, three-wire reversing, or VFD-with-pilot-device configurations—not used in regular labs; the student reads the schematic, performs LOTO, wires the circuit, and demonstrates correct operation under observation, mirroring the NCCER performance profile for motor controls. Standard met · Safety · Time · Quality/finish · Documentation |
| Lab Log Portfolio | Log | 15% | 80% of scored entries rated Satisfactory or above on the rubric; all LOTO records present | Students submit a complete lab log containing entries from every lab and practice session, including schematic sketches, measured data, LOTO procedure records, fault diagnosis notes, and the integrated project documentation; entries are evaluated for accuracy of data, completeness of LOTO documentation, and clear technical writing using a four-criterion rubric. Standard met · Safety · Time · Quality/finish · Documentation |
| LOTO and Electrical Safety Check | Safety audit | 15% | Zero critical errors (a critical error is any step that would expose a worker to stored energy); must pass before lab work in any session | At two unannounced points during the course, the instructor evaluates each student performing a LOTO sequence on a training panel using a standardized, step-by-step observation checklist aligned to OSHA 29 CFR 1910.147 and NFPA 70E; any critical error stops the evaluation, the student is retrained, and the check is repeated within two class days. Standard met · Safety · Time · Quality/finish · Documentation |
This course introduces learners to the fundamentals of programmable logic controllers as used in industrial and commercial electrical systems, covering hardware identification, ladder logic programming, I/O wiring, and basic troubleshooting. Students connect PLC theory to real control panel wiring, building on the motor and control knowledge from the prior course. Lessons map to NCCER Electrical Level 3 instrumentation and control content areas and reinforce OSHA electrical safety practices required for the OSHA 10 credential.
OutcomesThis course introduces learners to the fundamentals of programmable logic controllers as used in industrial and commercial electrical systems, covering hardware identification, ladder logic programming, I/O wiring, and basic troubleshooting. Students connect PLC theory to real control panel wiring, building on the motor and control knowledge from the prior course. Lessons map to NCCER Electrical Level 3 instrumentation and control content areas and reinforce OSHA electrical safety practices required for the OSHA 10 credential.
How the course runs. 12 blocks: Introduction to Automated Control Systems and PLC History; PLC Hardware: Power Supplies, CPUs, and Chassis; Electrical Safety for PLC Work: LOTO, PPE, and Control Voltage Hazards; PLC I/O Modules: Discrete and Analog Signals; Wiring Field Devices to PLC Inputs and Outputs; Ladder Logic Fundamentals: Contacts, Coils, and Program Scan; Programming Software: Entering, Downloading, and Monitoring a Program; Timers and Counters in Ladder Logic; PLC Troubleshooting: Fault Codes, I/O Diagnostics, and Online Tools; Reading and Creating PLC I/O Wiring Diagrams and Program Documentation; Industrial Networking Basics: How PLCs Communicate; Integrated PLC Project: Design, Wire, Program, Test, and Document a Control Circuit.
What competent looks like. Identify PLC hardware components—CPU, power supply, input/output modules, and communication ports—and explain the function of each in a control system. Wire discrete input and output devices to a PLC trainer safely, following lockout/tagout procedures and applicable NEC requirements for control wiring. Write, enter, and test basic ladder logic programs containing contacts, coils, timers, and counters using industry-standard programming software. Interpret PLC status indicators and use online monitoring to locate and correct wiring faults and logic errors in a simulated control circuit. Read and create simple PLC I/O wiring diagrams and program documentation that meet professional drawing standards. Describe industrial network basics and explain how PLCs communicate with operator interfaces and other field devices in a plant environment.
| # | Lesson | Hr | Type | Objective | Activities | Materials | Check |
|---|---|---|---|---|---|---|---|
| 1 | Introduction to Automated Control Systems and PLC History | 15 | theory | Students will explain the role of PLCs in modern industrial control, contrast relay-based and PLC-based control, and identify the major PLC families used in US industry. |
| Whiteboard, projector, NCCER Electrical Level 3 module on instrumentation and control, manufacturer overview literature (Allen-Bradley/Rockwell, Siemens, AutomationDirect), sample relay panel photo set | Exit quiz of 10 multiple-choice questions on PLC history, hardware families, and advantages over relay control; pass mark 70%. |
| 2 | PLC Hardware: Power Supplies, CPUs, and Chassis | 20.5 | demo | Students will identify and describe the function of every major hardware component on a rack-mounted PLC system, including CPU indicators and power supply ratings. |
| PLC trainer stations (rack-mounted fixed or modular PLC, e.g., Allen-Bradley MicroLogix or CompactLogix or equivalent), manufacturer hardware installation manuals, hardware ID worksheets, datasheets for CPU and power supply modules | Completed and correctly labeled hardware diagram (all components accurately identified); instructor spot-checks each student's form; 100% of major components must be correctly identified to pass. |
| 3 | Electrical Safety for PLC Work: LOTO, PPE, and Control Voltage Hazards | 16.5 | theory | Students will apply OSHA lockout/tagout procedures and select correct PPE for de-energizing and re-energizing a PLC control panel before any wiring or maintenance task. |
| OSHA 29 CFR 1910.147 summary card, NFPA 70E arc flash reference table (current edition), lockout hasps and tags, PLC trainer panel, PPE samples (safety glasses, insulated gloves Class 00/0, voltage-rated screwdrivers) | Students must score 80% or higher on a 10-question written safety quiz AND demonstrate the complete LOTO sequence on the trainer with zero procedural errors observed by the instructor before any hands-on wiring lab begins. |
| 4 | PLC I/O Modules: Discrete and Analog Signals | 20.5 | demo | Students will distinguish between discrete and analog I/O modules, read an I/O wiring diagram, and explain how field device signals are converted to values the CPU can process. |
| PLC trainer stations with discrete and analog I/O modules, 24 VDC power supply, bench-top current source or signal simulator, digital multimeters, I/O wiring diagrams, lab notebooks | Completed signal-tracing worksheet with measured values and explanations; instructor verifies analog scaling readings match expected percentage of span within ±5%; pass requires all discrete readings correct and analog readings within tolerance. |
| 5 | Wiring Field Devices to PLC Inputs and Outputs | 26 | lab | Students will safely wire a set of discrete field devices—push buttons, a limit switch, and a pilot light—to the correct terminals on a PLC I/O module using an instructor-supplied wiring diagram. |
| PLC trainer stations, 22–18 AWG control wire (multiple colors), wire ferrules and crimping tool, wire labels, terminal screwdrivers, digital multimeter, continuity tester, push buttons, limit switch, 24 VDC pilot light, I/O wiring diagram handouts, lockout/tagout equipment | Instructor performs a final point-to-point wiring inspection and powers up the circuit; all three field devices must function correctly on first power-up with no reversed polarity or missed connections; any wiring error that could damage equipment requires full correction and re-inspection before a pass is recorded. |
| 6 | Ladder Logic Fundamentals: Contacts, Coils, and Program Scan | 22.5 | theory | Students will explain how the PLC program scan works and write basic ladder logic rungs using normally open contacts, normally closed contacts, and output coils to satisfy a given control narrative. |
| Whiteboard or projector with scan cycle animation, NCCER Electrical Level 3 PLC module, blank ladder diagram worksheets, pencils, answer key for instructor use | Students complete a five-rung ladder diagram drawing exercise from written narratives; pass mark is 80% of rungs logically correct as judged by the instructor against the answer key. |
| 7 | Programming Software: Entering, Downloading, and Monitoring a Program | 26 | lab | Students will use industry-standard PLC programming software to enter a ladder logic program, download it to the PLC, and use online monitoring to verify correct operation of each rung. |
| Computer workstations with PLC programming software installed (e.g., Studio 5000 Logix Designer, RSLogix Micro, or equivalent free/educational version), PLC trainer stations with USB/Ethernet communication cables, printed ladder diagram exercise sheets, lab notebooks, troubleshooting reference card | Student's five-rung program must download without errors and all outputs must respond correctly to input conditions during a live demonstration to the instructor; any rung that fails to operate as specified must be corrected before a pass is awarded. |
| 8 | Timers and Counters in Ladder Logic | 22.5 | lab | Students will configure and program TON timer and CTU counter instructions to control the sequence and count of output events in a PLC application. |
| Computer workstations with PLC programming software, PLC trainer stations, stopwatch or phone timer, printed timer/counter instruction reference sheets, lab notebooks | Both the timer and counter programs are tested live by the instructor; timer delay must be within ±0.5 seconds of the programmed preset and the counter output must activate at the correct count; lab notebook entries must be complete; pass requires both functions operating correctly. |
| 9 | PLC Troubleshooting: Fault Codes, I/O Diagnostics, and Online Tools | 22.5 | lab | Students will use PLC fault tables, I/O status indicators, and software online monitoring to diagnose and correct instructor-introduced wiring faults and logic errors within a defined time limit. |
| PLC trainer stations with instructor-introduced faults, digital multimeters, computer workstations with programming software, fault symptom/cause/remedy reference card (student-created in activity 1), lab notebooks | All three faults must be correctly identified and corrected with the system operating normally; fault report must accurately describe each fault and the corrective action; pass requires all three faults resolved and complete written reports. |
| 10 | Reading and Creating PLC I/O Wiring Diagrams and Program Documentation | 18.5 | theory | Students will interpret a multi-page PLC control drawing set and produce a correctly formatted one-page I/O wiring diagram and address table for a simple control application. |
| Sample PLC control drawing set (multi-page, printed), blank drafting paper or computer with CAD or drawing software, NEMA symbol reference chart, documentation checklist handout, ruler, pencils | Student-created I/O wiring diagram is evaluated against the documentation checklist; all required elements (title block, correct symbols, addresses, wire labels) must be present and accurate; pass mark is 80% of checklist items correct with no safety-critical labeling errors. |
| 11 | Industrial Networking Basics: How PLCs Communicate | 13 | theory | Students will describe the purpose and basic operation of common industrial networks used with PLCs—including EtherNet/IP and DeviceNet—and explain how an operator interface panel exchanges data with a PLC. |
| Projector, blank network hierarchy diagram worksheet, industrial Ethernet switch, DeviceNet cable sample, HMI operator panel connected to PLC trainer, manufacturer network overview documents, whiteboard | Students complete a 10-question written quiz on network types, hierarchy, and HMI data exchange; pass mark 70%; students unable to pass on the first attempt receive a review session and one re-attempt. |
| 12 | Integrated PLC Project: Design, Wire, Program, Test, and Document a Control Circuit | 43.5 | lab | Students will independently design, wire, program, test, and document a complete PLC-controlled circuit that meets a written control narrative, demonstrating integration of all course skills. |
| PLC trainer stations, full set of control wiring components (push buttons, switches, pilot lights, contactor coil), computer workstations with programming software, lockout/tagout equipment, digital multimeters, lab notebooks, drafting materials or CAD software, grading rubric | Circuit must satisfy all requirements in the control narrative during the live demonstration; documentation package must include all required elements; graded on a rubric covering wiring quality, program correctness, documentation completeness, and ability to explain design decisions; pass mark is 75% overall with no safety violations; any LOTO procedure error results in an automatic fail and must be remediated before re-demonstration. |
| Assessment | Type | Weight | Pass standard | Method & rubric |
|---|---|---|---|---|
| PLC Theory Knowledge Exam | Written exam | 25% | 70% or higher on a 50-question written exam | A 50-question multiple-choice and short-answer exam covering PLC hardware identification, scan cycle operation, ladder logic instruction types (contacts, coils, timers, counters), I/O signal types, industrial network basics, and OSHA electrical safety principles; questions are drawn from NCCER Electrical Level 3 PLC module content areas to prepare students for the NCCER credential assessment. Standard met · Safety · Time · Quality/finish · Documentation |
| Practical Skills Demonstration | Skills demonstration | 45% | All critical tasks completed correctly with zero LOTO violations; rubric score of 75% or higher | Each student is given a written control narrative and must perform the complete LOTO procedure on a trainer, wire three specified field devices to the I/O module, enter and download a ladder logic program meeting the narrative, and demonstrate correct system operation to the instructor within a set time limit; rubric evaluates wiring quality, program accuracy, and professional documentation. Standard met · Safety · Time · Quality/finish · Documentation |
| Lab Notebook and Documentation Log | Log | 15% | 80% or higher on the lab log rubric; all 12 lessons must have entries | Students maintain a running lab notebook throughout the course capturing signal measurements, test results, fault diagnoses, timer and counter settings, and the integrated project documentation package (I/O list, address table, wiring diagram, commented program printout); the log is evaluated for completeness, accuracy of recorded data, and clarity of written explanations. Standard met · Safety · Time · Quality/finish · Documentation |
| Electrical Safety and LOTO Compliance Check | Safety audit | 15% | 100% of critical safety steps performed correctly with no errors; any critical error requires immediate remediation and a second full evaluation | The instructor conducts a direct observation safety evaluation at the start of the wiring lab unit and again during the integrated project demonstration, verifying that the student correctly performs all steps of the written lockout/tagout procedure, selects and dons appropriate PPE, and verifies absence of voltage before touching any conductors; this evaluation is a prerequisite gate for continued hands-on participation and maps to OSHA 10 control-of-hazardous-energy competencies. Standard met · Safety · Time · Quality/finish · Documentation |
Students design, install, and commission a full-scale residential/light-commercial electrical mock-up that integrates all prior coursework: NEC-compliant circuit layouts, conduit systems, motor controls, and a PLC-driven branch circuit. The project culminates in a documented inspection package and a formal defense before a panel of licensed electricians and an NCCER-credentialed instructor. Successful completion demonstrates job-entry readiness across NCCER Electrical Levels 1–4 competency areas and reinforces the safety culture required for OSHA 10 compliance.
OutcomesStudents design, install, and commission a full-scale residential/light-commercial electrical mock-up that integrates all prior coursework: NEC-compliant circuit layouts, conduit systems, motor controls, and a PLC-driven branch circuit. The project culminates in a documented inspection package and a formal defense before a panel of licensed electricians and an NCCER-credentialed instructor. Successful completion demonstrates job-entry readiness across NCCER Electrical Levels 1–4 competency areas and reinforces the safety culture required for OSHA 10 compliance.
How the course runs. 4 blocks: Project Design and NEC Compliance Planning; Conduit Fabrication, Rough-In, and Box Installation; Panelboard Wiring, Motor Control Circuit, and PLC Integration; Final Inspection, Documentation, and Project Defense Preparation.
What competent looks like. Design a NEC-compliant single-family/light-commercial electrical system from a set of architectural drawings, including load calculations, panel schedule, and circuit layout. Fabricate and install EMT and rigid conduit runs—including offsets, saddles, and box connections—that meet dimensional tolerances specified in NCCER Electrical Level 2 performance profiles. Wire, test, and document a motor control circuit incorporating a magnetic starter, overload relay, and a basic PLC input/output sequence that operates to design intent. Complete a project documentation package—including as-built drawings, inspection checklist, and test-record forms—that meets journeyman-level worksite documentation standards. Apply OSHA General Industry and Construction standards throughout the project, demonstrating correct lockout/tagout procedures and appropriate PPE selection for each task phase. Defend design decisions, code references, and troubleshooting methodology before a review panel, communicating at the level expected of a journeyman candidate.
| # | Lesson | Hr | Type | Objective | Activities | Materials | Check |
|---|---|---|---|---|---|---|---|
| 1 | Project Design and NEC Compliance Planning | 60 | theory | Given a set of architectural floor plans and a load schedule, the student will produce a complete electrical design package—including a panel schedule, circuit directory, conduit-fill calculations, and a written NEC code-reference log—that a licensed electrician would accept for permit submission. |
| Current edition NEC codebook, architectural floor plan sets (instructor-prepared), engineering calculator, graph paper or CAD workstation, panel-schedule template, conduit-fill tables (NEC Chapter 9 and Annex C), NCCER Electrical Level 1–3 modules for reference | Instructor approves the design package using a 20-point rubric: load calculation accuracy (±5% tolerance), correct wire and breaker sizing, valid conduit-fill percentages, accurate panel schedule, and at least 15 correct NEC citations. Students must score 16/20 (80%) to advance to fabrication. |
| 2 | Conduit Fabrication, Rough-In, and Box Installation | 96 | lab | Students will fabricate and install a complete conduit system—including at least two stub-ups, one three-bend saddle, one offset, and all required junction and device boxes—on the program's full-scale wall-frame mockup, achieving dimensional accuracy within ±1/4 inch and full NEC support-spacing compliance. |
| EMT conduit (1/2-inch and 3/4-inch), rigid conduit sections, hand benders, conduit level, tape measure, chalk line, torpedo level, cable staples, NM cable, THWN conductors (12 AWG and 10 AWG), wire strippers, fish tape, conduit reamer, metallic device and junction boxes, box connectors and locknuts, megohmmeter, continuity tester, PPE (safety glasses, work gloves, hard hat), NCCER Electrical Level 2 module, NEC codebook | Instructor uses a pass/fail field inspection checklist (modeled on a municipal rough-in inspection): all boxes at correct height (±1/4 inch), conduit support spacing within NEC limits, conduit fill within allowed percentage, all conductors color-coded correctly, continuity confirmed on every circuit, insulation resistance ≥1 MΩ. Students must pass all checklist items; any failure item must be corrected and re-inspected before proceeding. |
| 3 | Panelboard Wiring, Motor Control Circuit, and PLC Integration | 108 | lab | Students will wire a residential/light-commercial panelboard from a completed rough-in, then build and commission a motor control circuit—incorporating a magnetic starter, overload relay, and a PLC input/output sequence—that starts, stops, and protects a three-phase motor load according to the design ladder diagram. |
| Residential panelboard (training unit, 120/240 V single-phase, 100 A or 200 A), THWN conductors (various gauges), torque screwdriver (calibrated), LOTO kit (lockout hasp, tags, padlocks), clamp meter, multimeter, three-phase motor-control training board, magnetic starter, overload relay, momentary pushbutton station, PLC trainer unit with ladder-logic software, motor nameplate data sheet, motor-control test record form, NEC codebook, NCCER Electrical Levels 3–4 modules, PPE (safety glasses, arc-flash face shield rated for the task, insulated gloves, hard hat) | Two-part competency check: (1) Panelboard—instructor verifies torque marks on all terminals, correct LOTO documentation, proper grounding, and matching panel schedule before energizing; (2) Motor/PLC—student must demonstrate correct start/stop operation, successful overload-relay trip test, and accurate PLC documentation. Both parts scored on a 10-point rubric each; student must score ≥8/10 on each part to pass. |
| 4 | Final Inspection, Documentation, and Project Defense Preparation | 60 | practice | Students will compile a complete project documentation package—as-built drawings, inspection checklist, test records, LOTO log, and a written reflection—and rehearse a 20-minute defense presentation in which they explain design decisions, code references, and troubleshooting steps to a mock review panel. |
| Completed project binder (all prior documents), as-built drawing set, NEC codebook, NCCER Electrical Levels 1–4 modules, presentation slides or poster board, project defense evaluation rubric, peer-review feedback forms, word processor or drafting tools | Documentation binder must pass all 15 items on the completeness checklist (100% required; missing items must be corrected before defense). Technical reflection scored on a 10-point rubric (accuracy of troubleshooting narrative, correct code/standard citation, professional writing); 8/10 required. Rehearsal peer panel must confirm the student is defense-ready using a simple ready/not-ready determination before the formal defense is scheduled. |
| Assessment | Type | Weight | Pass standard | Method & rubric |
|---|---|---|---|---|
| Integrated Electrical Build — Final Project Inspection | Project | 60% | Student must pass all items on the formal inspection checklist (modeled on NEC-based rough-in and final inspection criteria) with zero uncorrected deficiencies; any deficiency must be corrected within 48 hours and re-inspected. Panelboard, conduit, motor control, and PLC subsystems are each scored on a 10-point rubric; an overall score of 32/40 (80%) is required. | A licensed electrician (or NCCER-credentialed instructor acting as inspector) conducts a formal inspection of the student's completed wall-frame mockup system—conduit runs, boxes, panelboard, motor control station, and PLC interface—using a structured inspection checklist drawn from NEC requirements and NCCER Level 1–4 performance profiles. This assessment verifies that the student can produce installation work of journeyman quality across all trade systems addressed in the program. Meets specification · Within estimate · Workmanship · Safety · Documentation |
| Project Documentation Portfolio | Portfolio | 20% | Portfolio must be complete (all 15 checklist items present) and earn a combined score of at least 80% across the rubrics for the design package (16/20), as-built drawings and records (8/10), and technical reflection (8/10). | The student submits a bound project binder containing the original approved design package, as-built drawings, panel schedule, circuit directory, bend logs, test records, LOTO log, and a 2–3 page technical reflection on a problem encountered and resolved during the build. The portfolio is evaluated for technical accuracy, NEC code citation correctness, completeness, and professional presentation—mirroring the documentation a journeyman would submit on a permitted job. Completeness · Organization · Evidence quality |
| Project Defense — Panel Oral Examination | Oral / panel | 20% | Student must score at least 24/30 (80%) on the panel's oral evaluation rubric; rubric domains are: explanation of design decisions and NEC compliance (10 pts), demonstration and explanation of installed systems (10 pts), and professional communication and response to questions (10 pts). A score below 24 requires a second defense within one week. | The student presents the completed project to a panel of at least two evaluators (a licensed electrician and an NCCER-credentialed instructor) in a 20-minute defense: five minutes of prepared presentation, ten minutes of live system demonstration, and five minutes of panel questions. Questions may cover any topic from the full project—design rationale, code references, safety procedures, troubleshooting decisions, and motor or PLC logic—to confirm that the student understands and owns every aspect of the work. Explains decisions · Answers technical questions · Professional communication |
Students complete a minimum of 486 supervised hours with a licensed electrical contractor, applying classroom knowledge to live commercial or residential jobsites under the direct oversight of a journeyman or master electrician. Work experience is documented through structured field logs, employer evaluations, and a mid-placement check-in with program faculty. This externship satisfies the practical hours component supporting NCCER Electrical L1–4 portfolio documentation and provides verified field experience required by most state journeyman licensure applications.
OutcomesStudents complete a minimum of 486 supervised hours with a licensed electrical contractor, applying classroom knowledge to live commercial or residential jobsites under the direct oversight of a journeyman or master electrician. Work experience is documented through structured field logs, employer evaluations, and a mid-placement check-in with program faculty. This externship satisfies the practical hours component supporting NCCER Electrical L1–4 portfolio documentation and provides verified field experience required by most state journeyman licensure applications.
How the course runs. 4 blocks: Externship Orientation and Jobsite Entry Readiness; Supervised Field Work — Phase 1: Rough-In and Infrastructure; Supervised Field Work — Phase 2: Trim-Out, Device Installation, and Testing; Final Employer Evaluation, Faculty Site Visit, and Externship Closeout.
What competent looks like. Perform assigned electrical rough-in, trim-out, and service tasks safely and correctly under journeyman supervision on a live jobsite. Apply NEC code requirements, conduit bending techniques, and wiring methods learned in prior coursework to actual field conditions. Demonstrate consistent compliance with OSHA 10 hazard recognition, lockout/tagout, and required PPE protocols throughout every shift. Maintain accurate, daily field logs that record tasks performed, hours worked, tools and materials used, and code references applied. Receive a satisfactory or above rating from the site supervisor on all competency dimensions of the employer evaluation form at the final review. Identify at least one area of professional growth observed during the placement and articulate a plan for continued skill development.
| # | Lesson | Hr | Type | Objective | Activities | Materials | Check |
|---|---|---|---|---|---|---|---|
| 1 | Externship Orientation and Jobsite Entry Readiness | 16 | field | Students will complete all pre-placement requirements — site safety orientation, employer paperwork, PPE inspection, and a faculty site-visit briefing — so that they are legally and physically ready to work on day one. |
| Externship learning agreement, employer site-safety orientation materials, OSHA 10 card (carried on person), personal PPE kit, program field-log booklet, faculty site-visit checklist | All pre-placement documents signed and submitted to faculty; PPE checklist signed by supervising journeyman; student present and on time for joint faculty–supervisor kickoff meeting. Pass = 100% of required documents submitted within the first scheduled shift week. |
| 2 | Supervised Field Work — Phase 1: Rough-In and Infrastructure | 180 | field | Students will assist journeyman electricians with conduit installation, wire pulling, box setting, panel rough-in, and grounding tasks, producing work that meets NEC requirements and passes site inspection. |
| Conduit benders (hand and mechanical), fish tape, wire-pulling lubricant, EMT and rigid conduit, wire and cable per site spec, voltage tester, digital multimeter, site drawings, NEC code book, field-log booklet | Journeyman initials each daily log entry confirming task completion and acceptable quality; at least 90% of entries completed without omissions. Any work rejected by inspection must be documented, corrected, and re-verified. Pass = journeyman sign-off on every logged workday with no more than two corrective re-dos per 30-hour block. |
| 3 | Supervised Field Work — Phase 2: Trim-Out, Device Installation, and Testing | 250 | field | Students will install devices, luminaires, panels, and service equipment; perform continuity and voltage testing; and support the electrician of record through inspection readiness, demonstrating safe and code-compliant work habits throughout. |
| Torque screwdriver/driver, non-contact voltage tester, digital multimeter, AFCI/GFCI testers, luminaire mounting hardware, panel schedules and site drawings, NEC code book, LOTO kit, field-log booklet | Journeyman evaluates trim-out quality using the program employer evaluation rubric at the midpoint (approximately hour 125 of this phase) and again at the end; student must score Satisfactory or above on workmanship, safety compliance, and professional conduct at both checks. Pass = Satisfactory or above on all rubric dimensions at the final employer mid-point evaluation. |
| 4 | Final Employer Evaluation, Faculty Site Visit, and Externship Closeout | 40 | field | Students will complete the externship with a documented final employer performance evaluation, a faculty-conducted site visit or structured debrief, and a compiled and submitted field-log portfolio that verifies all required hours and competencies. |
| Employer evaluation form (final), faculty site-visit or debrief protocol, complete field-log booklet, self-reflection template, program hour-verification form | Final employer evaluation form completed and signed; all 486 hours verified by employer signature and daily log totals; faculty debrief or site-visit protocol completed; self-reflection submitted. Pass = final employer evaluation rating of Satisfactory or above on all dimensions AND verified total hours of 486 or more. |
| Assessment | Type | Weight | Pass standard | Method & rubric |
|---|---|---|---|---|
| Final Employer Skills Demonstration Evaluation | Skills demonstration | 70% | Satisfactory or above on every rated dimension of the employer evaluation rubric (safety compliance, technical workmanship, use of tools and instruments, code awareness, communication, and professional conduct); no dimension rated Unsatisfactory. | The supervising journeyman or master electrician completes the program's standardized employer evaluation form at the conclusion of the externship, rating the student across all competency dimensions based on direct observation across the full placement. A copy is signed by both parties and submitted to the program coordinator as a required credential for course completion. Competency · Safety · Attendance · Conduct · Initiative |
| Field Log Portfolio | Log | 30% | 486 or more verified hours documented with daily entries; journeyman or supervisor initials on each entry; all required sections complete (tasks, tools, code references, safety observations); self-reflection submitted; no more than three entries missing any single required field. | The student submits the complete bound or digital field-log portfolio containing every daily log entry, both employer evaluation forms (midpoint and final), the faculty debrief record, and a one-page self-reflection. The portfolio is reviewed by the faculty coordinator against the program's log checklist; it serves as the primary hour-verification document for both NCCER registry submissions and state journeyman licensure applications that require documented field experience. Complete · Verified |
This course systematically reviews every major content domain tested on the NCCER Electrical Level 1–4 assessments, the OSHA 10-Hour Outreach card requirements, and the state journeyman electrician licensing examination, using spaced repetition, timed practice questions, and full-length mock exams. Learners identify personal knowledge gaps from prior coursework, drill targeted remediation on weak domains, and demonstrate exam-ready competence under realistic timed and proctored conditions. The course also covers exam registration logistics, fee structures, acceptable identification, and retake policies for each credential so learners are administratively prepared on test day.
OutcomesThis course systematically reviews every major content domain tested on the NCCER Electrical Level 1–4 assessments, the OSHA 10-Hour Outreach card requirements, and the state journeyman electrician licensing examination, using spaced repetition, timed practice questions, and full-length mock exams. Learners identify personal knowledge gaps from prior coursework, drill targeted remediation on weak domains, and demonstrate exam-ready competence under realistic timed and proctored conditions. The course also covers exam registration logistics, fee structures, acceptable identification, and retake policies for each credential so learners are administratively prepared on test day.
How the course runs. 4 blocks: Diagnostic Assessment and Personalized Study Planning; Domain-by-Domain Content Review: NCCER Levels 1–4 and OSHA 10; Targeted Calculation Lab: NEC Load Calculations, Conductor Sizing, and Motor Branch Circuits; Full-Length Proctored Mock Certification Exams and Final Debrief.
What competent looks like. Correctly answer at least 75 percent of NCCER Electrical Level 1–4 knowledge-check questions across all four module groups on a timed practice exam. Demonstrate understanding of all OSHA 10 core topic areas—including hazard recognition, fall protection, electrical safety, and PPE selection—sufficient to earn the OSHA 10 completion card through an authorized trainer. Apply NEC code lookup and calculation skills (load calculations, wire sizing, overcurrent protection, grounding) at the speed and accuracy required by the state journeyman licensing examination. Develop and execute a personalized remediation plan that targets individually diagnosed weak domains across all three credential areas. Complete two full-length timed mock licensing exams under proctored conditions, scoring at or above the passing threshold established by the state licensing board. Explain the registration process, required documentation, testing-center rules, and retake policies for the NCCER registry, OSHA 10 outreach, and state journeyman license.
| # | Lesson | Hr | Type | Objective | Activities | Materials | Check |
|---|---|---|---|---|---|---|---|
| 1 | Diagnostic Assessment and Personalized Study Planning | 15 | theory | Learners will complete a scored diagnostic covering all NCCER Electrical Level 1–4 content domains, OSHA 10 topic areas, and journeyman exam calculation types, then produce a written remediation plan that ranks their three weakest domains and schedules targeted study sessions. |
| Diagnostic exam packet (instructor-compiled from released NCCER sample questions and journeyman practice banks), NCCER Electrical Trainee Guides Levels 1–4, current edition NEC codebook, gap-analysis worksheet, pencils, calculator (non-programmable, per exam rules) | Learner submits a complete gap-analysis worksheet with domain error rates calculated and a written study plan; competence is confirmed when the instructor verifies that all diagnostic errors are mapped to a specific reference and a realistic study schedule is documented — pass requires submission of both documents with no unmapped domains. |
| 2 | Domain-by-Domain Content Review: NCCER Levels 1–4 and OSHA 10 | 45 | theory | Learners will review all four NCCER Electrical craft-knowledge domain groups (electrical theory, wiring methods and materials, motors and controls, and systems and equipment) plus all OSHA 10 required topic areas, answering targeted practice question sets after each domain to confirm retention at or above 75 percent. |
| NCCER Electrical Trainee Guides Levels 1–4, current edition NEC codebook with index tabs, OSHA 10 outreach topic outline, domain quiz packets, non-programmable scientific calculator, whiteboard, projector for worked examples | Score on each 25-question domain quiz is recorded; learners must achieve at least 75 percent on every domain quiz before the course advances to mock exams — any learner below threshold completes instructor-directed remediation on that domain and takes an alternate 25-question quiz, with both scores logged. |
| 3 | Targeted Calculation Lab: NEC Load Calculations, Conductor Sizing, and Motor Branch Circuits | 35 | lab | Learners will solve a set of twenty-five multi-step calculation problems representative of those appearing on state journeyman licensing exams — including service load calculations, branch-circuit sizing, voltage-drop calculations, motor branch-circuit and overload protection sizing, and conduit fill — achieving a minimum accuracy of 75 percent under timed exam conditions. |
| Current edition NEC codebook, Ugly's Electrical Reference (current edition) for quick-lookup cross-check, non-programmable scientific calculator, timed calculation problem packets (instructor-compiled), answer key with NEC citations, pencils, scratch paper | Each calculation packet is scored by the instructor; learners must reach 75 percent or higher on at least one of the two timed packets — scoring and error categories are logged on the gap-analysis tracking sheet to inform the final mock exam review. |
| 4 | Full-Length Proctored Mock Certification Exams and Final Debrief | 40 | practice | Learners will complete two separate full-length proctored mock exams — one modeled on the NCCER Electrical Level 1–4 summative assessment format and one modeled on a state journeyman licensing exam — under conditions that replicate actual testing environments, then participate in a scored debrief that confirms readiness and finalizes exam registration plans. |
| Mock Exam 1 packet (NCCER-format, instructor-compiled from NCCER sample question pools), Mock Exam 2 packet (journeyman-format, instructor-compiled from state practice exam banks), current edition NEC codebook, non-programmable scientific calculator, individual domain score report forms, exam registration handout listing NCCER accredited sponsor contact, state licensing board website, and local OSHA 10 authorized trainers | Each learner must score at or above 75 percent on at least one of the two mock exams to receive a course completion certificate — scores on both exams and all prior domain quizzes are compiled into a readiness report that the instructor reviews with each learner individually before signing off. |
| Assessment | Type | Weight | Pass standard | Method & rubric |
|---|---|---|---|---|
| Full-Length Proctored Mock Certification Exam Suite | Mock certification exam | 100% | A score of 75 percent or higher on at least one of the two full-length proctored mock exams (NCCER-format or journeyman licensing-format), combined with documented completion of domain quizzes and the calculation lab at or above 75 percent in each area, is required to pass the course and receive the completion certificate. | This mock_cert assessment consists of two separate full-length, timed, proctored exams administered under conditions that replicate actual NCCER and state journeyman licensing testing environments, including approved materials only and strict time limits. Results are analyzed by domain and compiled into an individual readiness report that documents the learner's preparedness for each of the three target credentials — NCCER Electrical Level 1–4, OSHA 10, and State Journeyman Electrician — and guides final registration decisions. Score · Time management |
Students sit the NCCER Electrical Level 1–4 craft assessments administered through an NCCER Accredited Training Sponsor, the OSHA 10-Hour Construction Industry Outreach course delivered by an OSHA-authorized trainer, and their state journeyman electrician licensing examination administered by the applicable state electrical licensing board. Pass standard: Credential issued by the body.
Back to Electrical · How the school gets authority to award these credentials
A free tech program — complimentary, as our commitment to get America working. Help us build VoTechWorks. Tell us what works, what doesn’t, and what you want to learn.