BLD-ELEC05-04 · Lesson 5 · 28 clock hours · lab
Offsets: Calculation, Layout, and Hand Bending
Objective. Students calculate shrink and mark positions, then hand-bend accurate two-bend offsets in ½″ and ¾″ EMT at 22½°, 30°, and 45° to clear obstacles of specified heights without introducing twists or dog-legs.
What an Offset Does
An offset is a pair of bends in the same plane that shifts a conduit run sideways or vertically to clear an obstacle—a beam, pipe, duct, or the edge of a panel—then returns the run to its original direction. Because both bends must be equal in angle and perfectly aligned, offsets are one of the first real tests of a bender's accuracy. Get the math right before you touch the bender and the conduit will drop into place; skip the math and you waste material and time.
The Multiplier Method
Every bend angle has a fixed multiplier that converts obstacle height into the distance you must separate the two marks on the conduit.
| Bend Angle | Multiplier | Shrink per inch of height |
|-----------|------------|---------------------------|
| 22½° | 2.6 | 3/16″ (≈ 0.19″) |
| 30° | 2.0 | 1/4″ (0.25″) |
| 45° | 1.4 | 3/8″ (≈ 0.37″) |
Mark-to-mark distance = obstacle height × multiplier
Shrink = obstacle height × shrink constant
Shrink is the amount the overall run shortens after bending. You must add it back when you cut conduit to a finished length or your run will come up short at the box.
Layout Procedure
1. Measure the obstacle height from the finished surface (or top of the pipe to be cleared) to the centerline of the existing conduit run.
2. Calculate mark-to-mark distance and shrink using the table above.
3. Choose the first bend mark location based on where the offset must begin. Mark it with a pencil line all the way around the conduit—a partial mark causes twists.
4. Measure the mark-to-mark distance from the first mark and draw the second mark the same way.
5. Note in your bending log: obstacle height, angle chosen, mark-to-mark distance, calculated shrink, and cut length if applicable.
Making the Bends
Foot benders (hand benders) for EMT have an arrow, a star or teardrop, and degree markings on the hook. For offsets you use the arrow mark.
1. Slide the conduit into the bender hook so the arrow aligns with the first mark.
2. Orient the bender so the handle stands roughly vertical. Keep one foot firmly on the bender footrest.
3. Apply smooth, even pressure—no jerking—until the desired angle reads on the bender's degree indicator or the conduit aligns with a reference angle on the floor.
4. Without removing the conduit from the bender, roll it 180° (flip it over) so the second mark aligns with the arrow and the bend you just made faces down.
5. Apply the same angle at the second mark, bending toward the first bend.
6. Lay the finished offset on the floor. Both legs must be parallel; use a torpedo level on each leg to confirm they are within 2° of level (or of each other if the run is not horizontal). If the legs are not parallel you have a dog-leg; if one leg is rotated relative to the other you have a twist.
Correcting Common Errors
Dog-leg (legs not parallel): One bend angle is greater than the other. Slightly overbend the shallow side or use a bender with a more precise degree stop.
Twist: The conduit rotated between bends. Return to the start; use a full circumference pencil mark and hold the conduit against your body or a straight edge as you make the second bend.
Wrong height: Measure the actual offset with a tape or combination square. If it is high, the angle is too steep; if low, the angle is too shallow. Recalculate and rebend on a new piece.
Shrink not accounted for: The run is short at the box or fitting. Always add shrink to your cut length before cutting.
Safety in the Lab
- Cut ends are sharp. Ream every cut end with a pipe reamer immediately after cutting. Wear leather gloves when handling freshly cut conduit.
- Benders can pinch. Keep fingers away from the hook area during the bend stroke.
- No overhead bending. Always bend with the bender on the floor; losing control of a long stick overhead can cause impact injuries.
- Eye protection (safety glasses) required whenever cutting or reaming conduit; chips and burrs can be ejected unexpectedly.
- Inspect conduit before bending. Kinked, dented, or corroded EMT will crack at the bend point and must be discarded.
- Keep your bending area clear of tripping hazards; conduit sticks protrude and move unexpectedly during bending.
Key terms9
OffsetA two-bend configuration that displaces a conduit run a set distance to clear an obstacle and then returns it to the original direction.
MultiplierA fixed constant for a given bend angle used to convert obstacle height into the required mark-to-mark distance on the conduit.
ShrinkThe amount by which a conduit run becomes shorter in overall developed length after an offset is bent; it must be added to the cut length to maintain a correct run dimension.
Mark-to-mark distanceThe measured distance between the two layout marks on the conduit where each bend of an offset will be made.
Dog-legA defect in which the two legs of an offset are not parallel, caused by the two bend angles being unequal.
TwistA defect in which the two bends of an offset are not in the same plane, causing the conduit to rotate along its axis between the two bends.
EMT (Electrical Metallic Tubing)A thin-wall steel conduit type commonly used in commercial and residential wiring that is bent with a hand or mechanical bender; it requires connectors rather than threads.
Torpedo levelA short, pocket-sized spirit level used in the field to check that conduit legs are level, plumb, or parallel to one another within an acceptable tolerance.
Developed lengthThe total length of conduit stock consumed in a run including the straight sections and the arcs of all bends.
Worked examples4
1. Calculate the mark-to-mark distance and shrink for a 4″ offset at 30°.
- Identify the multiplier for 30°: 2.0
- Mark-to-mark distance = obstacle height × multiplier = 4″ × 2.0 = 8.0″
- Identify the shrink constant for 30°: 0.25″ per inch of height
- Shrink = 4″ × 0.25 = 1.0″
Answer: Mark-to-mark distance = 8.0″; Shrink = 1.0″
2. Calculate the mark-to-mark distance and shrink for a 6″ offset at 45°.
- Identify the multiplier for 45°: 1.4
- Mark-to-mark distance = 6″ × 1.4 = 8.4″
- Identify the shrink constant for 45°: 0.375″ per inch of height
- Shrink = 6″ × 0.375 = 2.25″
Answer: Mark-to-mark distance = 8.4″; Shrink = 2.25″
3. Calculate the mark-to-mark distance and shrink for a 2″ offset at 22½°.
- Identify the multiplier for 22½°: 2.6
- Mark-to-mark distance = 2″ × 2.6 = 5.2″
- Identify the shrink constant for 22½°: 0.19″ per inch of height
- Shrink = 2″ × 0.19 = 0.38″, which rounds to approximately 3/8″
Answer: Mark-to-mark distance = 5.2″; Shrink ≈ 0.38″ (3/8″)
4. A conduit run must be exactly 48″ from box to box after the offset is bent. The offset is 4″ high at 45°. How long should the conduit be cut before bending?
- Shrink for a 4″ offset at 45° = 4 × 0.375 = 1.5″
- The bending process will shorten the stick by 1.5″, so the cut length must be longer than the finished run length.
- Cut length = finished run length + shrink = 48″ + 1.5″ = 49.5″
Answer: Cut the conduit to 49.5″ before bending.
The math in this lesson2
Learners compute offset mark-to-mark distance with cosecant multipliers, shrink per inch, and pre-bend cut length.
A-SSE.1G-SRT.8
In class: Using the multiplier method, students calculate and record in their bending logs the mark-to-mark distance and shrink for three obstacle heights (2″, 4″, and 6″) at each of the three bend angles before touching the bender. · Students bend a 4″ offset at 30° in ¾″ EMT, measure both the offset height and the parallelism of the two legs with a torpedo level, and compare measured shrink to calculated shrink; discrepancies are discussed as a group. · Students assemble a short conduit run through a plywood panel with two pre-drilled holes at different heights; the conduit must pass cleanly through both holes using a calculated offset, demonstrating real-world application.
Materials: Hand benders, ½″ and ¾″ EMT, tape measures, torpedo levels, combination squares, pre-drilled plywood offset-practice panel, multiplier reference cards, bending logs, pipe cutters, reamers
Check: Offset height within ±¼″, legs parallel within 2° per torpedo level, no visible twist; instructor measures all three dimensions; must pass two of three offset sizes to advance.
Practice check8
Answer each question, then check it. Nothing is recorded; this is your own practice.
Record this lesson on my transcript. Sign in with your key and enrollment email to record lessons (enroll free if you have no key). This page stays open to read and practise.