newSchoolWorks.com › VoTechWorks › Building & Construction › Elevator Mechanic (pre-apprentice) › Traction Elevator Systems › Lesson 7
BLD-ELEV10-03 · Lesson 7 · 12 clock hours · practice

Integrated Traction System Inspection and LOTO Field Practice

Objective. Students will perform a complete pre-operation inspection of the training traction elevator from machine room through pit, applying correct lockout/tagout at each step and completing all documentation without prompting.

⚠ Pending professional review

This lesson, its worked examples and its practice questions has not yet been verified by a licensed professional engineer or master tradesperson or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.

VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.

Why This Practice Session Matters

A traction elevator is a system of interconnected mechanical, electrical, and hydraulic components that must all function correctly before a car carries a single passenger. Pre-operation inspection and lockout/tagout (LOTO) are not formalities — they are the procedures that prevent crush injuries, electrocutions, and fatal falls. In this session you will walk the entire system from machine room to pit, apply LOTO correctly at each control point, and document everything as a licensed mechanic would on a real job site.

Lockout/Tagout: Principles and Procedure

LOTO is governed by OSHA's Control of Hazardous Energy standard (29 CFR 1910.147). The goal is to bring every energy source — electrical, gravitational, mechanical, and hydraulic — to zero before you work. For a traction elevator the critical energy sources are the main line electrical supply to the machine room, the control panel power, and the stored mechanical energy in the suspended car and counterweight.

The six-step LOTO sequence for this exercise:

1. Notify — inform everyone who uses or works near the elevator that it is being taken out of service.

2. Identify — locate every energy isolation point: the main line disconnect, the control power switch, and any secondary feeds.

3. Isolate — open the main line disconnect and the control power switch to interrupt all electrical energy.

4. Lock and tag — each individual mechanic applies their own personal lock and a completed tag to every isolation device. One lock per person, every time — never share a lock.

5. Release stored energy — allow the car to settle; confirm the brake is set. If the car is not at a landing, follow the instructor's direction before entering the hoistway.

6. Verify zero energy — attempt to start the car using the normal call button and the car operating panel. Confirm no movement and no power indicator lights are on. Use a calibrated voltage tester on the load side of every disconnect before touching any conductors.

Document every step on the LOTO log sheet as you complete it. A blank field on the log is treated the same as a missed step during scoring.

Machine Room Inspection

Begin at the machine room with the elevator still in normal service, then apply LOTO before touching any equipment. After verification:

Hoistway and Car Frame Inspection

Enter the hoistway only after LOTO is fully applied and verified. Work top-down from the car top:

Pit Inspection

Enter the pit only after confirming LOTO, activating the pit stop switch, and ensuring adequate lighting. Never enter a pit with a running elevator.

Defect Recognition and Reporting

When you find a defect — whether pre-staged by the instructor or discovered during a real inspection — record it immediately on the deficiency report form. Each entry must include: location of the defect, what you observed, the applicable ASME A17.1 requirement that is not being met, and the corrective action required. Vague entries such as "rope looks bad" are not acceptable. Write specifically: "Car hoist rope No. 3 exhibits broken wires exceeding allowable limits per ASME A17.1; rope must be replaced before return to service."

Conduct and Safety Rules for This Session

Key terms10

Lockout/Tagout (LOTO)An OSHA-required procedure for isolating all hazardous energy sources and securing them with personal locks and warning tags before maintenance or inspection work begins.
Zero energy stateThe condition in which every energy source (electrical, mechanical, gravitational) affecting the equipment has been isolated, released, and verified at zero before work proceeds.
Main line disconnectThe primary electrical shutoff switch in the machine room that disconnects all power to the elevator drive and control systems.
GovernorA mechanical overspeed detection device connected to the car safeties; it triggers the safety mechanism if the car exceeds a preset downward speed.
Progressive safetyA type of car safety device that grips the guide rails gradually to stop an overspeeding or free-falling car, limiting deceleration forces on passengers.
Sheave grooveThe machined channel in the drive sheave that seats and supports the hoist ropes; worn or improperly shaped grooves reduce traction and accelerate rope wear.
BufferAn energy-absorbing device at the bottom of the hoistway that cushions the car or counterweight in the event of an overtravel past the lowest landing.
Deficiency reportWritten documentation that identifies a specific inspection finding, cites the applicable code requirement, and states the corrective action required before the elevator returns to service.
Pit stop switchA mandatory safety switch located in the elevator pit that, when activated, removes the car from normal operation and prevents movement while personnel are working in the pit.
ASME A17.1The Safety Code for Elevators and Escalators published by the American Society of Mechanical Engineers; the primary US standard governing design, installation, inspection, and maintenance requirements.
In class: Full lockout/tagout exercise: each student individually isolates machine room power (main line disconnect and control power) using the program's LOTO station, applies personal lock and tag, verifies zero energy by attempting normal operation, and documents the procedure on a LOTO log sheet. · Systematic inspection run: working from a structured checklist, students inspect machine, brake, sheave grooves, rope condition, car frame, guide shoes, safeties, governor, pit equipment, and buffers, recording observations and flagging any pre-staged defects planted by the instructor. · Defect report and debrief: students write a brief deficiency report for each flagged item found, state the corrective action required, and participate in an instructor-led debrief reviewing any missed items and reinforcing code-based justification.
Materials: Training traction rig (full system), personal LOTO locks and tags, LOTO log sheets, comprehensive inspection checklist, deficiency report form, ASME A17.1 (current edition), NEIEP Traction module
Check: Instructor scores LOTO log and inspection checklist; student must correctly identify at least four of five planted defects, complete LOTO documentation with no missing fields, and commit zero unsafe acts — any unsafe act is an automatic fail requiring repeat.

Practice check8

Answer each question, then check it. Nothing is recorded; this is your own practice.

Safety and Hazardous Energy Control
1. Under OSHA's hazardous energy control standard, who must apply a personal lock to each isolation point during a LOTO procedure?
Safety and Hazardous Energy Control
2. After opening the main line disconnect and applying your personal lock and tag, what is the correct next action before touching any electrical conductors?
Inspection and Maintenance Documentation
3. A student finds that oil buffers in the pit show visible fluid seepage at the base seal. The correct entry on the deficiency report should:
Traction Elevator Components and Maintenance
4. Which condition during a sheave groove inspection would most directly require the hoist ropes to be evaluated for replacement?
Safety and Hazardous Energy Control
5. Before a mechanic may enter the elevator pit to perform an inspection, which action must be completed in addition to full LOTO?
Traction Elevator Components and Maintenance
6. During a car safety inspection, a student notices one safety jaw is stiff and does not move freely when manually exercised. This finding should be:
Safety and Hazardous Energy Control
7. A student removes a classmate's personal lock from the main disconnect to restore power quickly at the end of the session. According to the program's LOTO policy, this results in:
Traction Elevator Components and Maintenance
8. The governor on a traction elevator is most accurately described as a device that: