BUS-CONS57-05 · Lesson 7 · 15.5 clock hours · practice
Purchase Orders, Subcontracts, and Change Order Administration
Objective. Students will issue a purchase order for a structural steel package, process one change order to that PO, and log both transactions in a procurement tracking log consistent with project record-keeping requirements.
⚠ Pending professional review
This lesson, its worked examples and its practice questions has not yet been verified by a credentialed professional in the field or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.
VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.
Purchase Orders, Subcontracts, and Change Order Administration
Procurement documents are the legal foundation of every construction project. A purchase order (PO) and a subcontract define what is being bought, at what price, under what conditions, and when delivery is expected. Managing these documents accurately protects the project budget, the schedule, and every party involved.
The Purchase Order
A purchase order is a written commercial document issued by the buyer (the general contractor or owner) to a vendor or supplier, authorizing the purchase of specific goods or services at an agreed price and on agreed terms. Once the vendor signs or formally acknowledges it, the PO becomes a binding contract.
Every PO must include the following fields—leaving any one blank creates risk:
- Vendor name and address — identifies the legal party being engaged
- PO number — unique identifier used in the procurement log and in accounting
- Scope reference — cites the applicable specification section, drawing set, or bid package (e.g., "Structural Steel Package per Drawing Set S-100 through S-210")
- Unit prices and total price — itemized where possible so change orders can reference agreed unit rates
- Delivery date and location — states where material must arrive and by what date; ties to the project schedule
- Payment terms — for example, net 30 days after receipt of invoice and approved delivery ticket
- Insurance requirements — minimum coverage types and limits the vendor must carry (general liability, workers' compensation, automobile); certificates must be on file before work begins
- Submittal requirements — shop drawings, product data, or mill certifications that must be approved before fabrication starts
For a structural steel package, submittal requirements are especially important. Shop drawings must typically be approved by the structural engineer of record before the fabricator cuts any steel. Issuing the PO before that approval chain is in place is a common source of costly rework.
Subcontracts vs. Purchase Orders
A subcontract covers labor and materials together—a trade contractor who both supplies materials and performs installation on site. A PO typically covers a supplier who delivers goods only. Subcontracts are longer documents and include additional provisions: schedule adherence, site safety compliance, indemnification, and dispute resolution. Both documents must reflect the same scope, price, and insurance requirements written into the prime contract, so review the prime contract before finalizing either document.
Change Order Administration
A change order (CO) is a formal written amendment to an existing PO or subcontract. Changes happen on every project—material prices shift, scope is added or deleted, delivery dates move. The key discipline is that no change is valid until it is documented and signed by both parties.
When a vendor submits a change-order request, evaluate it in three steps:
1. Verify entitlement — does the contract actually allow this change? A material price escalation clause in the PO permits cost adjustments within defined limits; without such a clause, the vendor assumed that risk.
2. Check the numbers — compare the requested price change to the unit prices in the original PO. If the PO includes a unit rate for steel (dollars per ton), apply that rate to the revised quantity before accepting a lump-sum claim.
3. Assess schedule impact — a revised delivery date must be evaluated against the project schedule's critical path. If the new date pushes a milestone, document the impact and notify the owner or project manager immediately.
Your written rationale for approving or rejecting a CO becomes part of the project record. Be specific: cite the contract clause, the unit price, or the schedule float. Vague rationale creates disputes.
If you approve the CO, issue a revised PO or a numbered change order document that references the original PO number and clearly states the change in price, delivery date, and scope. The vendor must acknowledge it in writing.
Procurement Tracking Log
Every PO and CO must be entered into the project's procurement tracking log—typically a spreadsheet maintained by the project engineer or estimator. The log is the single source of truth for committed costs and delivery commitments. Key columns include:
- PO number and vendor
- Original committed cost
- Approved change order amounts (cumulative)
- Revised total committed cost
- Original and revised delivery dates
- Status (pending, approved, delivered, invoiced, paid)
The sum of all revised committed costs in the log must reconcile to the project budget line for that scope. If the log total and the budget line disagree by even one dollar, there is an error somewhere—find it before submitting a cost report to the owner or lender.
Safety and Record-Keeping Requirements
Procurement documents have a direct connection to site safety. Insurance certificates from vendors must be verified before any vendor personnel arrive on site—this is not optional. Workers' compensation coverage protects against liability if a delivery driver or fabricator employee is injured during unloading. Confirm that the vendor's safety plan, if required by the subcontract, is on file.
For steel erection specifically, OSHA standards govern the activities of the erection crew on site. While the PO covers supply, the erection subcontract must address fall protection, connecting work, and the steel erector's safety plan. Always ensure procurement documents align with site safety responsibilities so no gap exists between the supplier's obligations and the erector's obligations.
All signed POs, COs, insurance certificates, and acknowledgments must be filed in the project's document control system and retained for the period required by the contract and applicable law. Losing a signed document is the same as losing your legal protection.
Key terms10
Purchase Order (PO)A written commercial document issued by a buyer to a vendor that authorizes the purchase of specified goods or services at agreed prices and terms; it becomes a binding contract upon vendor acknowledgment.
Change Order (CO)A formal written amendment to an existing PO or subcontract that documents an agreed change in scope, price, delivery date, or any combination of these; it must be signed by both parties to be valid.
Committed CostThe dollar amount the project has contractually obligated to a vendor or subcontractor through executed POs and subcontracts, including approved change orders; appears in the procurement log and cost reports.
SubcontractA contract between a general contractor and a trade contractor who provides both labor and materials on site; more comprehensive than a PO and includes schedule, safety, and indemnification provisions.
SubmittalDocuments submitted by a vendor or subcontractor—such as shop drawings, product data sheets, or mill certifications—that must be reviewed and approved before fabrication or installation may begin.
EntitlementThe contractual right of a vendor or subcontractor to receive additional compensation or time; evaluating entitlement means confirming that the contract language actually authorizes the requested change before approving it.
Unit PriceAn agreed cost per measurable unit of work or material (e.g., dollars per ton of steel) established in the PO; used to price scope changes without renegotiating the entire contract.
Procurement Tracking LogA project-level spreadsheet or database that records every PO and CO, tracking original committed cost, approved changes, revised totals, and delivery status; the single source of truth for procurement activity.
Insurance CertificateA document issued by a vendor's insurer that evidences required coverage types and limits; must be on file and verified before the vendor's personnel begin work on or deliver to the project site.
Payment TermsThe contractual conditions governing when and how a vendor will be paid, such as 'net 30 days after receipt of an approved invoice and signed delivery ticket.'
Worked examples4
1. The original PO for structural steel is $284,000. The fabricator submits a change-order request for a $12,500 material price increase. Your PO contains a unit price of $1,250 per ton for W-shape beams and the fabricator claims the increase covers 10 additional tons of W-shapes added to the scope by the engineer. Is the claimed amount consistent with the unit price, and what is the revised PO total?
- Step 1 — Check entitlement: The scope change (10 additional tons) was directed by the engineer of record, so the vendor has entitlement to a price adjustment.
- Step 2 — Apply the unit price from the PO: 10 tons × $1,250 per ton = $12,500.
- Step 3 — Compare to the requested amount: $12,500 requested = $12,500 per unit price calculation. The amounts match; the CO is supported.
- Step 4 — Calculate the revised PO total: $284,000 (original) + $12,500 (approved CO) = $296,500.
Answer: The change-order request of $12,500 is consistent with the contract unit price. The revised PO total is $296,500.
2. Your procurement tracking log shows three steel-related POs: PO-001 at $284,000, PO-002 at $47,500, and PO-003 at $18,200. One approved change order of $12,500 applies to PO-001 and a credit change order of –$3,000 applies to PO-003. The project budget line for structural steel is $359,200. Does the log reconcile?
- Step 1 — Calculate the revised total for PO-001: $284,000 + $12,500 = $296,500.
- Step 2 — PO-002 has no change orders: revised total = $47,500.
- Step 3 — Calculate the revised total for PO-003: $18,200 + (–$3,000) = $15,200.
- Step 4 — Sum all revised PO totals: $296,500 + $47,500 + $15,200 = $359,200.
- Step 5 — Compare to budget line: $359,200 = $359,200.
Answer: The procurement log reconciles to the project budget line of $359,200. No discrepancy exists.
3. A fabricator's change-order request claims 15 tons of additional plate steel at $980 per ton, plus a delivery delay of 14 calendar days. Your PO has a unit price of $980 per ton for plate steel. Calculate the cost of the approved CO and state what scheduling action you must take.
- Step 1 — Verify unit price matches: PO states $980 per ton for plate steel; the fabricator's rate is $980 per ton. Consistent.
- Step 2 — Calculate the CO cost: 15 tons × $980 per ton = $14,700.
- Step 3 — Issue CO document for $14,700 and update the revised PO total accordingly.
- Step 4 — Assess the schedule impact: the 14-day delivery delay must be compared to the activity float in the project schedule. Notify the project manager or scheduler immediately so they can evaluate whether the critical path is affected and whether a time extension or acceleration is required.
Answer: The approved CO amount is $14,700. The 14-day delivery delay requires immediate notification to the project manager for schedule impact analysis; it must be reflected in the procurement log as a revised delivery date.
4. After entering all transactions, your log shows total original committed cost of $349,200 and total approved change orders of +$12,500 and –$3,000. Your budget line for the scope is $358,500. Identify whether the log reconciles and, if not, by how much it is off.
- Step 1 — Calculate net change orders: $12,500 + (–$3,000) = $9,500.
- Step 2 — Calculate revised committed cost: $349,200 + $9,500 = $358,700.
- Step 3 — Compare to budget: $358,700 vs. $358,500.
- Step 4 — Determine discrepancy: $358,700 – $358,500 = $200 over budget.
Answer: The log does not reconcile. The revised committed cost of $358,700 exceeds the budget line of $358,500 by $200. The source of the $200 difference must be identified and corrected before a cost report is issued.
In class: Using a provided PO template and the steel scope from earlier lessons, complete a purchase order—filling in all fields: vendor, scope reference, price, delivery date, payment terms, insurance requirements, and submittal requirements · Receive a fictional change-order request from the steel fabricator (material price increase and revised delivery date); evaluate it against the contract unit prices and schedule, approve or reject with written rationale, and issue a revised PO or change order document · Enter the original PO and the change order into a procurement tracking log spreadsheet, updating committed cost, approved changes, and revised delivery date columns; verify that the log reconciles to the project budget line
Materials: PO template (Word/Excel), subcontract change order form, procurement tracking log spreadsheet template, project budget extract, sample steel fabricator change-order request
Check: PO and change order documents complete and all fields populated; log arithmetic reconciles to budget within $0; instructor signs off on document accuracy to pass
Practice check9