BLD-SOLA09-08 · Lesson 1 · 24 clock hours · lab
Site Assessment, Load Analysis, and System Design
Objective. Given an assigned project scenario, students will conduct a roof or ground-mount site assessment, perform a shading analysis with a solar pathfinder or app-based tool, calculate system size from load data, and produce a complete NEC 690-compliant single-line diagram and bill of materials.
⚠ Pending professional review
This lesson, its worked examples and its practice questions has not yet been verified by a licensed professional engineer or master tradesperson or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.
VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.
Site Assessment, Load Analysis, and System Design
This capstone lab brings together every skill you have built in the program. You will assess a real or mock site, calculate a system size, and produce the design documents a licensed contractor would submit for a permit. Work carefully — errors here cost money and can create safety hazards on an energized roof.
Site Assessment
Before you size a single module, you must understand the physical site. Arrive with your compass, inclinometer, tape measure, and shading tool.
Roof or ground-mount survey. Measure the available area and record roof pitch (or proposed tilt angle for a ground mount) and the compass azimuth of each candidate array location. True south (180° azimuth) is the reference for maximum annual production in the continental United States. Deviations east or west reduce yield; quantify this for your written justification.
Shading analysis. Use a Solar Pathfinder, Solmetric SunEye, or an equivalent app-based tool (such as SunSurveyor or the shade analysis feature built into Aurora Solar) to map obstructions at each candidate location. The tool projects the sun's annual path onto your measurement. Record the percentage of annual solar access (or equivalent metric) at each of your three locations. Select the location with the highest unshaded solar access and document your choice with the tool output and a written explanation of how shading would affect annual energy production. Even partial shading on one cell in a series string can reduce output of the entire string — this is why location selection matters.
Safety during site assessment. Follow all fall-protection requirements whenever you are on a roof: wear a hard hat, non-slip footwear, and a properly anchored personal fall arrest system if you are at or above six feet. On a cooperating building, follow the site owner's safety plan. Never walk on a roof surface you have not confirmed can bear your weight. Keep tools tethered to prevent dropped-object hazards.
Load Analysis and System Sizing
System size is driven by what the customer actually uses, not by how much roof space is available.
Step 1 — Annual consumption. Read the utility bill provided by your instructor. Sum twelve months of kWh usage to get annual consumption. If only one month is shown, use the annualization factor on your worksheet.
Step 2 — DC system size using peak sun hours. The standard method divides the daily kWh target by the peak sun hours (PSH) available at the site, then applies a system derate factor to account for real-world losses (wiring, inverter efficiency, soiling, temperature, and mismatch). A commonly used overall derate factor is around 0.80, though you should calculate or use the value provided on your worksheet.
```
Daily kWh target = Annual kWh ÷ 365
Required DC kW = Daily kWh target ÷ (PSH × derate factor)
```
Step 3 — Module and inverter selection. Choose modules from the manufacturer specification sheets provided. Calculate the number of modules needed: divide the required DC wattage by the module's STC-rated power (Watts). Round up to a whole number. Select a string inverter or microinverter that accepts the resulting DC input range.
String Sizing and NEC 690 Principles
String sizing keeps the system within the voltage and current limits set by both the NEC and the equipment manufacturer.
Voltage. NEC Article 690.7 requires that the maximum system voltage be calculated using the module's open-circuit voltage (Voc) corrected for the lowest expected ambient temperature at the site using the temperature coefficient provided in the module spec sheet. The corrected Voc per module multiplied by the number of modules in series must not exceed the inverter's maximum input voltage and must not exceed the system's maximum voltage rating (commonly 600 V for residential, 1000 V or 1500 V for commercial systems).
Current. NEC Article 690.8 principles require that conductor and overcurrent device ampacity be based on the module's short-circuit current (Isc) multiplied by 1.25 (to establish the continuous-duty baseline), and then further multiplied by 1.25 for overcurrent protection sizing where required, unless the equipment is rated for continuous operation under these conditions.
Safety during electrical design. A design error that results in a string voltage above inverter or NEC limits creates an arc-flash and fire hazard. Check every voltage calculation twice before submitting. During any physical work with energized conductors, apply lockout/tagout (LOTO) procedures and wear appropriate arc-rated PPE.
Single-Line Diagram and Bill of Materials
A single-line diagram (SLD) is the electrical schematic that AHJs (Authorities Having Jurisdiction) and inspectors review for permit approval. Every component and disconnect must appear and be labeled.
Required elements for a residential grid-tied SLD:
- PV array (show number of strings and modules per string)
- DC disconnect (rapid shutdown and array disconnect)
- Inverter
- AC disconnect
- Main service panel (show point of interconnection)
- Utility meter
- Grounding electrode conductor and equipment grounding conductors
- All conductor sizes and conduit types on each segment
- System voltage and current ratings at each segment
Draft by hand first on graph paper, then reproduce in your design software. The hand draft forces you to think through every connection before the software automates anything.
Your bill of materials (BOM) must list every component in the SLD with manufacturer, model number, quantity, and the rated specification that governs its selection (e.g., inverter max input voltage, conductor ampacity).
Completing Your Written Narrative
A short written narrative (one to two pages) accompanies the SLD and BOM. Explain why you chose each major piece of equipment, how your string sizing keeps the system within NEC 690.7 and 690.8 limits, and why you selected the final array location over the alternatives. This narrative is your professional justification — write it as if you are presenting to a building department.
Key terms10
Peak Sun Hours (PSH)The number of hours per day at a given location during which solar irradiance averages 1,000 W/m², used as the basis for estimating daily PV energy production.
System Derate FactorA multiplier less than 1.0 applied during system sizing to account for real-world losses including inverter efficiency, wiring resistance, soiling, shading, and temperature effects on modules.
Open-Circuit Voltage (Voc)The maximum voltage a PV module produces when no current is flowing; used under NEC Article 690.7 principles to calculate maximum string voltage corrected for cold-temperature conditions.
Short-Circuit Current (Isc)The maximum current a PV module produces when its output terminals are shorted; the basis for conductor and overcurrent device sizing under NEC Article 690.8 principles.
Solar PathfinderA non-electronic optical instrument that uses a convex reflective surface and printed sun-path charts to map shading obstructions throughout the entire year at a proposed array location.
Single-Line Diagram (SLD)A simplified electrical schematic showing all system components, interconnections, conductor sizes, and ratings on a single drawing; required for permit submittal and inspection.
AzimuthThe compass direction a solar array faces, measured in degrees from true north; 180° (true south) maximizes annual energy production in the continental United States.
Bill of Materials (BOM)An itemized list of every component in a PV system, including manufacturer, model number, quantity, and the rated specification relevant to its selection.
Authority Having Jurisdiction (AHJ)The organization, office, or individual responsible for enforcing code requirements at the installation site, typically the local building or electrical department.
Temperature Coefficient of VocA module specification, expressed as a percentage or voltage change per degree Celsius, used to correct Voc for the coldest expected ambient temperature when calculating maximum string voltage.
Worked examples4
1. A household uses 10,950 kWh per year. The site has 5.0 peak sun hours per day. Use a system derate factor of 0.80. What DC system size in kW is required?
- Calculate daily kWh target: 10,950 kWh ÷ 365 days = 30 kWh/day
- Apply the sizing formula: Required DC kW = Daily kWh ÷ (PSH × derate factor)
- Substitute values: Required DC kW = 30 ÷ (5.0 × 0.80) = 30 ÷ 4.0 = 7.5 kW
Answer: The required DC system size is 7.5 kW.
2. You have selected a module with a rated power of 400 W (STC). How many modules are needed to build the 7.5 kW system from the previous example?
- Convert system size to watts: 7.5 kW × 1,000 = 7,500 W
- Divide by module rated power: 7,500 W ÷ 400 W/module = 18.75 modules
- Round up to the nearest whole module: 19 modules
Answer: 19 modules are required (rounding up from 18.75 to ensure the system meets the target).
3. A module has a Voc of 42.0 V at STC and a temperature coefficient of Voc of −0.29 %/°C. The lowest expected ambient temperature at the site is −10 °C. STC test temperature is 25 °C. What is the temperature-corrected Voc for one module, and what is the maximum number of modules you can wire in series to stay within a 600 V system limit?
- Calculate the temperature difference: 25 °C − (−10 °C) = 35 °C below STC
- Calculate the percentage increase in Voc: 35 °C × 0.29 %/°C = 10.15% increase (Voc rises as temperature drops)
- Calculate corrected Voc per module: 42.0 V × (1 + 0.1015) = 42.0 V × 1.1015 = 46.26 V
- Divide system voltage limit by corrected Voc: 600 V ÷ 46.26 V = 12.97 modules
- Round down to the nearest whole number: 12 modules maximum per string
Answer: The temperature-corrected Voc is approximately 46.26 V per module. A maximum of 12 modules may be wired in series to stay within the 600 V system limit.
4. A module has an Isc of 10.0 A. What minimum continuous current rating must a conductor carry for a single string of these modules, applying the NEC Article 690.8 continuous-duty multiplier?
- Identify the base current: Isc = 10.0 A for one string
- Apply the NEC 690.8 continuous-duty factor of 1.25: 10.0 A × 1.25 = 12.5 A
- This 12.5 A is the minimum ampacity the conductor must be rated to carry continuously before applying any additional correction factors for conduit fill or ambient temperature
Answer: The conductor must be rated for at least 12.5 A of continuous current before additional correction factors are applied.
The math in this lesson2
Learners apply temperature coefficients and the 125% NEC factor to Voc and Isc.
7.RP.3A-CED.4
In class: Teams of two visit the program's mock-site or a cooperating building, use a Solar Pathfinder or Solmetric SunEye (or equivalent app) to map shading obstructions at three potential array locations, record tilt and azimuth, and select the optimal location with a written justification citing annual production impact. · Using the customer's utility bill provided by the instructor, each student calculates annual kWh consumption, determines DC system size using a standard peak-sun-hour method, selects modules and inverter from a real equipment catalog, calculates string sizing and voltage/current limits per NEC 690.7 and 690.8 principles, and records all calculations on a structured worksheet. · Each student drafts a single-line diagram by hand and then reproduces it in a free CAD or design tool (such as Aurora Solar free tier, Helioscope student access, or SketchUp with a solar plugin), labels all required components and disconnects, and submits the diagram with an itemized bill of materials and a short written narrative explaining equipment choices.
Materials: Solar Pathfinder or app-based shading tool, compass, inclinometer, tape measure, utility bill sample handouts, module and inverter specification sheets from at least two manufacturers, NEC Article 690 reference copy, string-sizing worksheet template, laptop with CAD or PV design software, graph paper, ruler
Check: Instructor reviews the single-line diagram against a rubric: all required disconnects present, string voltage within inverter and NEC limits, grounding and bonding shown, labels complete, and BOM matches diagram. Pass = 80% rubric score with zero uncorrected code violations.
Practice check8
Answer each question, then check it. Nothing is recorded; this is your own practice.
Record this lesson on my transcript. Sign in with your key and enrollment email to record lessons (enroll free if you have no key). This page stays open to read and practise.