BLD-SOLA09-07 · Lesson 1 · 10 clock hours · theory

NEC Structure, Article 690 Overview, and PV System Classifications

Objective. Students will navigate the NEC codebook efficiently and correctly classify a described PV system by type (stand-alone, grid-tied, multimode) and identify which Article 690 parts apply.

⚠ Pending professional review

This lesson, its worked examples and its practice questions has not yet been verified by a licensed professional engineer or master tradesperson or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.

VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.

Why the NEC Matters for PV Installers

Every electrical installation in the United States, including solar photovoltaic (PV) systems, must comply with the National Electrical Code (NEC), formally known as NFPA 70. The NEC is published by the National Fire Protection Association and is adopted into law by most states and local jurisdictions. When an authority having jurisdiction (AHJ) — typically a building or electrical inspector — approves your permit and signs off on your inspection, they are confirming that your work meets the NEC. Failing inspection costs time, money, and reputation. More importantly, a non-compliant installation can cause fires, electric shock, or electrocution. The NEC is a safety document first.

How the NEC Is Organized

Understanding the structure of the NEC lets you find answers quickly rather than guessing.

Article 690 at a Glance

Article 690 is titled Solar Photovoltaic (PV) Systems. It covers the installation of PV systems, including the source circuits, output circuits, disconnecting means, ground-fault and arc-fault protection, system grounding, and marking requirements. The article is divided into numbered parts, each addressing a specific area of the system:

When you are working on a job, always start with the definitions in 690.2 to confirm you are using terms the same way the code does.

PV System Classifications

Not all PV systems are the same, and Article 690 applies differently depending on system type. The definitions in 690.2 are authoritative.

Stand-Alone (Off-Grid) Systems supply loads that are not connected to an electric utility. Power comes only from PV modules and, usually, battery storage. There is no grid connection. A remote cabin is a classic example. Stand-alone systems must still meet Article 690 requirements, but Article 705 (interconnection) does not apply.

Interactive (Grid-Tied) Systems are connected to the electric utility in parallel. Excess power can flow back to the grid. These systems require inverters that meet anti-islanding requirements — meaning they automatically shut down if the grid loses power so that utility workers are not endangered by a back-fed line they think is de-energized. Article 705 governs the interconnection. Residential rooftop solar is almost always an interactive system.

Multimode Systems can operate both in parallel with the utility and as stand-alone systems when the grid is unavailable. They use a special multimode inverter or inverter-charger. When grid-tied, Article 705 applies; when operating off-grid, the stand-alone provisions govern. Article 706 applies if battery storage is included.

Direct-Coupled Systems connect a PV source directly to a load (such as a PV water pump) with no battery or inverter. These are simple systems but must still meet applicable sections of Article 690.

Safety Considerations

Before you open the codebook on a real job, remember that PV systems present two serious electrical hazards:

1. PV source circuits are energized by sunlight and cannot be turned off by a switch alone. Always follow lockout/tagout (LOTO) procedures and use appropriate PPE, including arc-rated clothing and insulated gloves rated for the system voltage, before working on any circuit.

2. Back-fed utility voltage is present at the utility-side terminals of an interactive inverter even when the inverter is off. Treat those terminals as always live.

The NEC's marking requirements in Part VI of Article 690 exist precisely so that anyone working on or near the system — including firefighters — can identify energized conductors and disconnecting means quickly. Correct labeling is not optional; it is a life-safety requirement.

Navigating the Codebook Efficiently

Practice a simple three-step routine: (1) Identify the topic — is this a wiring method question, a disconnect question, or a definitions question? (2) Go to the Table of Contents or Index to find the article and part. (3) Read the section and any referenced sections it points to. Many sections cross-reference other articles; follow those references before reaching a conclusion. Speed comes with repetition, which is why locating sections quickly is a skill tested on the NABCEP PV Associate exam.

Key terms10

Authority Having Jurisdiction (AHJ)The organization, office, or individual responsible for enforcing the requirements of the NEC, or their designated representative — typically the local electrical inspector.
Article 690The section of NEC Chapter 6 that establishes installation requirements specifically for solar photovoltaic systems, including circuits, disconnecting means, grounding, marking, and energy storage.
Stand-Alone SystemA PV system that supplies power to loads independently of the electric utility grid, with no utility interconnection.
Interactive (Grid-Tied) SystemA PV system that operates in parallel with the electric utility and can deliver power to the grid; governed in part by Article 705.
Multimode SystemA PV system capable of operating both in parallel with the utility and as a stand-alone system when the grid is unavailable, often using a multimode inverter and battery storage.
Anti-IslandingA required protection function that causes a grid-tied inverter to cease energizing the utility line automatically when utility power is lost, protecting utility workers from back-fed voltage.
690.2 DefinitionsThe section within Part I of Article 690 that provides official NEC definitions for terms used throughout the article; the starting point for classifying any PV system.
Direct-Coupled SystemA PV system in which the source directly powers a load without a battery or inverter, such as a PV-powered pump operating only when sunlight is available.
Article 705The NEC article governing interconnected electric power production sources, including the requirements for connecting interactive PV systems to the utility grid.
Article 706The NEC article governing energy storage systems, including battery installations that are part of or associated with a PV system.
In class: Instructor-led walk-through of NEC layout: chapters, articles, parts, sections, and the index; students race to locate five assigned sections and record the path taken. · Tabletop card-sort exercise: students match twelve system descriptions (stand-alone, interactive, direct-coupled, etc.) to the correct Article 690 classification using the definitions in 690.2. · Small-group discussion comparing three one-line diagrams (residential grid-tied, off-grid cabin, and grid-tied with storage) to identify which Article 690 parts and which supporting articles (705, 706) govern each system.
Materials: Current edition NFPA 70 National Electrical Code (one copy per student or tablet access), Article 690 outline handout, three sample one-line diagrams, whiteboard, sticky-note card sets
Check: Five-question open-codebook quiz: students locate the correct code section and write the section number plus a one-sentence plain-language summary for each; passing score 80 percent.

Practice check8

Answer each question, then check it. Nothing is recorded; this is your own practice.

NEC Article 690 / PV System Fundamentals
1. A homeowner's PV system is connected to the utility grid and automatically shuts off when the utility loses power. Which Article 690 system classification best describes this installation?
NEC Article 690 / Code Navigation
2. A remote hunting cabin has a PV array charging a battery bank that powers lights and a water pump. There is no utility connection. Which supporting NEC article governs the battery storage portion of this installation?
NEC Article 690 / Code Navigation
3. Where in Article 690 would you find the official NEC definition of the term 'photovoltaic system'?
Safety / Electrical Hazard Control
4. A PV system inverter is turned off at its disconnect. A technician is about to work on the utility-side terminals of the inverter. What is the FIRST safety action required?
NEC Article 690 / Code Navigation
5. Which NEC chapter contains Article 690?
NEC Article 690 / PV System Fundamentals
6. A PV system can run a home normally when the utility is available and also power critical loads during a grid outage using a battery bank and a special inverter. This system is BEST classified as which type?
NEC Article 690 / Safety and Marking
7. Which Part of Article 690 contains requirements for labeling conductors and disconnects so that first responders can quickly identify energized circuits?
NEC Article 690 / Code Navigation
8. A student is told to find the requirements for the maximum system voltage of a PV source circuit. After checking Section 690.2 for definitions, which Part of Article 690 should the student consult next?