Gas Pressure Testing and Leak Detection

Objective. The student will perform an air pressure test on a gas piping rough-in assembly, detect and locate leaks using approved methods, and document results on a standard inspection form.

Why Pressure Testing Matters

Before any gas piping is concealed behind walls, ceilings, or underground, it must be tested to prove it holds pressure without leaking. This step protects lives. Natural gas and LP (liquefied petroleum) gas are both flammable and, in sufficient concentration, explosive. A single undetected leak left inside a wall cavity can accumulate to dangerous levels over days or weeks. Pressure testing and leak detection are the last line of defense before the system is hidden from view, and no authority having jurisdiction (AHJ) will approve covering work that has not passed a documented pressure test.

This lab follows the testing procedures outlined in the International Fuel Gas Code (IFGC), which most US states adopt (sometimes with local amendments). Always confirm the exact requirements with your local AHJ and the adopted edition of the code in your jurisdiction.

Test Medium: Why Air, Not Gas

During rough-in testing, air — not gas — is always used as the test medium. Air is non-flammable. Using actual gas to pressure-test new piping before the system is verified leak-free would create a serious explosion and fire hazard. An air compressor with a regulated low-pressure output supplies the test pressure. Do not use oxygen or any other industrial gas; use only clean, dry air or an inert gas such as nitrogen.

Test Pressure and Hold Time

The IFGC specifies minimum test pressure and hold time requirements for gas piping. Requirements vary based on pipe size, operating pressure of the system, and whether the piping is new or being extended. For typical residential and light-commercial gas piping (systems operating at pressures of one-half pound per square inch or less), the IFGC requires a minimum test pressure and a minimum hold time — consult your current IFGC reference for the exact values that apply to the pipe size and system type you are testing. Always record the specific code edition and section on your test record form.

The pressure gauge you use must be calibrated and appropriate for the test pressure range. A gauge with too large a range may not show a small pressure drop clearly. Read and record the gauge at the beginning and end of the hold period. If the final reading equals the initial reading (within the tolerance of the gauge), the system passes.

Equipment Setup

1. Cap all open ends of the piping assembly.

2. Install the pressure gauge at a convenient access point (often a capped tee or test port).

3. Connect the regulated air supply and slowly bring pressure up to the required test pressure. Do not overpressure the assembly.

4. Isolate the air supply (close the supply valve) before beginning the timed hold period. The gauge reading should remain stable.

5. Start the timer. Watch the gauge throughout the hold period.

Leak Detection with Detection Solution

Gas leak detection solution (sometimes called bubble solution) is a liquid applied to joints, fittings, and connections with a brush or applicator. If air is escaping from a joint, it will cause the solution to bubble. Apply solution generously to every joint — threaded connections, union fittings, valves, and any other assembly points. Watch each joint for 15–30 seconds before moving on.

A slow leak may produce very small, slow bubbles; do not rush. If you find a leak:

Electronic combustible gas detectors are used to detect gas leaks on live systems, but during an air pressure test, the detection solution method is the standard approach because the test medium is air, not combustible gas.

Safety Rules for This Lab

Completing the Test Record

Documentation is as important as the test itself. An inspector must be able to read your record and confirm every required parameter was met. Your form must include:

Incomplete forms will not be accepted. In the field, an incomplete or missing test record can result in a failed inspection and required re-inspection fees. Treat every form as a legal document.

Connection to Your Credentials

NCCER Plumbing Levels 3 and 4 include gas piping installation and testing. Journeyman licensing exams in most states include questions on gas system testing procedures and code requirements. Accurate test documentation is also a professional and legal obligation once you are licensed.

Key terms8

Pressure testA procedure in which a piping system is pressurized with a test medium (air or inert gas) to a specified pressure and held for a specified time to verify it holds pressure without leaking before concealment or commissioning.
Test mediumThe substance used to pressurize a piping system during testing. For gas piping rough-in, clean dry air (or an inert gas such as nitrogen) is used — never actual gas or oxygen.
Hold timeThe minimum duration the pressurized system must maintain the test pressure without pressure drop, as required by the applicable code (IFGC). The timer does not start until the supply is isolated.
Gas leak detection solutionA liquid applied to joints and fittings during an air pressure test; escaping air causes it to bubble, revealing the exact location of a leak.
Calibrated pressure gaugeA gauge that has been verified against a known standard for accuracy; required for pressure testing so that readings are reliable and defensible on inspection records.
Authority having jurisdiction (AHJ)The governmental body or official responsible for enforcing codes in a given area — typically the local building or gas inspection department. Always confirm local code requirements with the AHJ.
International Fuel Gas Code (IFGC)A model code developed by the International Code Council that establishes requirements for the installation and testing of fuel gas piping systems; adopted with or without amendments by most US states.
Lockout/tagout (LOTO)An OSHA-required safety procedure for de-energizing and physically locking equipment (such as a compressor) so it cannot be restarted while a worker is performing repairs or maintenance.

Worked examples3

1. A pressure gauge reads 15 psig at the start of the hold period. At the end of the required hold time, it reads 14 psig. The gauge has a manufacturer-stated accuracy of ±0.5 psig. Has the system passed the pressure test?
  1. Determine the pressure drop: 15 psig − 14 psig = 1 psig drop.
  2. Determine the gauge's total allowable error band: ±0.5 psig on each reading means two readings could together carry up to 1.0 psig of combined error.
  3. Compare: the observed drop (1 psig) equals the maximum combined gauge uncertainty (1.0 psig), meaning the result is right at the edge — but a 1 psig drop is still a pressure drop that must be investigated.
  4. Conclusion: A measurable drop of 1 psig should not be accepted as a pass. The correct action is to apply detection solution to all joints and identify whether any leak is present before accepting or rejecting the result.
Answer: The system does not cleanly pass. A 1 psig drop requires leak investigation with detection solution before the test can be accepted. Retest after confirming or correcting any leak.
2. You must convert a test pressure stated in the code as inches of water column (in. W.C.) to psig for your pressure gauge, which reads in psig. The required test pressure is 10 in. W.C. What is that in psig?
  1. Use the conversion factor: 1 psig = 27.68 in. W.C. (standard value).
  2. Divide the required pressure by the conversion factor: 10 ÷ 27.68 = 0.361 psig.
  3. Round appropriately for field use: approximately 0.36 psig.
Answer: 10 in. W.C. equals approximately 0.36 psig. A standard dial gauge scaled in psig would show very little deflection at this pressure; consider using a manometer or a low-range gauge for accurate reading at this test pressure.
3. A gas piping rough-in test requires a hold time of 10 minutes. The technician starts the timer at 9:07 a.m. and records an initial gauge reading of 6 psig. At what clock time should the final gauge reading be taken, and what must the final reading be for the system to pass?
  1. Calculate end time: 9:07 a.m. + 10 minutes = 9:17 a.m.
  2. The final reading must be taken at or after 9:17 a.m. — not before.
  3. For the system to pass, the final gauge reading must equal the initial reading (6 psig) within the accuracy tolerance of the calibrated gauge, indicating no pressure loss.
Answer: The final reading is taken at 9:17 a.m. The gauge must still read 6 psig (no measurable pressure drop) for the test to pass.

The math in this lesson2

Learners convert test pressure from inches of water column to psig.
N-Q.1N-Q.3
Brush up in the math halls at newSchoolWorks.com:
In class: Instructor demonstrates pressure gauge installation, pressurization to the test pressure required by the IFGC for the pipe size and system type, and the hold-time procedure; students record the test parameters in their lab log. · Each student applies gas detector solution to every joint of their assembled steel pipe system, monitors the gauge for the required hold period, and identifies an instructor-planted intentional leak (loose fitting); students record location and corrective action taken. · Students complete a test record form documenting pipe size, test medium (air), test pressure, hold time, initial gauge reading, final gauge reading, leak findings, and disposition — mimicking real inspection documentation required before concealment.
Materials: Air compressor (regulated low-pressure supply), calibrated pressure gauges, gas leak detection solution, timer, intentional-leak assembly prepared by instructor, pressure test record forms, IFGC reference for test pressure requirements, lab log
Check: Completed test record reviewed by instructor: correct test pressure recorded, hold time met, leak correctly identified and location documented, corrective action stated. All fields complete and accurate to pass; incomplete forms require resubmission before the next lab.

Practice check8

Answer each question, then check it. Nothing is recorded; this is your own practice.

Gas Piping Systems / Safety
1. Why is air used as the test medium for gas piping rough-in pressure tests rather than actual gas?
Gas Piping Systems / Testing Procedures
2. During a pressure test, a technician notices the gauge drops slightly after the supply valve is closed. What is the FIRST corrective action?
Workplace Safety / OSHA
3. Which safety standard governs the de-energizing of an air compressor before a plumber repairs a leaking fitting on a pressurized test assembly?
Documentation / Inspection Requirements
4. A pressure test record form is missing the final gauge reading. What should happen next?
Gas Piping Systems / Testing and Measurement
5. A calibrated pressure gauge is described as having an accuracy of ±0.5 psig. A technician records an initial reading of 12 psig and a final reading of 11 psig — a drop of 1 psig. Which statement best describes this result?
Gas Piping Systems / Leak Detection
6. When applying gas leak detection solution during an air pressure test, how long should each joint be observed before moving to the next one?
Workplace Safety / PPE
7. Which of the following pieces of personal protective equipment is MANDATORY while the gas piping test assembly is pressurized?
Gas Piping Systems / Testing Procedures and Safety
8. A student finds an intentional leak at a loose union fitting during the lab exercise. What is the correct sequence of steps?
Record this lesson on my transcript. Sign in with your key and enrollment email to record lessons (enroll free if you have no key). This page stays open to read and practise.