Objective. Using a builder's level, rod, and field notes, students will calculate instrument height, rod readings, and cut or fill values at five designated points on a flat or gently sloping surface, with each result within 0.05 ft of the instructor's verified answer.
This lesson, its worked examples and its practice questions has not yet been verified by a licensed professional engineer or master tradesperson or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.
VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.
Every cut you make with a dozer or grader and every fill you place with a scraper must match the engineer's plan grade. If your machine runs too high, concrete or asphalt crews have to make up the difference. If you go too low, you waste fill material and compact time. The builder's level and Philadelphia rod are the field tools that tell you, in feet and hundredths, exactly where the ground stands relative to where it needs to be.
An automatic (self-leveling) builder's level contains a compensator that keeps the line of sight perfectly horizontal once the instrument is roughly leveled with its leveling screws. Set the tripod on firm ground, attach the level, center the circular bubble, and the instrument does the fine leveling automatically. Never leave a level on an active job pad where equipment is running — a vibration or strike can damage the compensator. Set up at a safe distance from machine travel lanes, and always use the lens cap when not reading.
Benchmark (BM): A point of known elevation, often marked with a brass disk or a survey nail in concrete. All your calculations start here.
Backsight (BS): The first rod reading you take — always on the benchmark or a turning point of known elevation. Adding the backsight to the benchmark elevation gives you the Height of Instrument (HI).
> HI = Benchmark Elevation + Backsight Reading
Height of Instrument (HI): The elevation of the line of sight through the level. This number stays constant for every reading taken from that instrument setup.
Foresight (FS): A rod reading taken at any point whose elevation you want to find. Subtracting the foresight from the HI gives you the ground elevation at that point.
> Ground Elevation = HI − Foresight Reading
Once you know the existing ground elevation at a stake, compare it to the plan grade elevation shown on the data sheet.
> Cut = Existing Elevation − Plan Grade Elevation
> Fill = Plan Grade Elevation − Existing Elevation
Note that plan grade is often the top of subbase or subgrade, not the finished surface. If the data sheet specifies a subgrade depth (for example, 0.50 ft below plan grade for gravel base), subtract that depth from the plan grade before calculating cut or fill.
Soil changes volume when it is disturbed. Shrinkage means compacted fill occupies less volume than the loose material you hauled. Swell means excavated material expands when loosened. Your instructor will supply the specific factors for today's exercise. The general rule is:
Always use the factors given on the problem sheet — never guess soil behavior on a real job.
A standard differential-leveling field-notes form has columns for: Station, Backsight (BS), HI, Foresight (FS), Elevation, Plan Grade, and Cut/Fill. Fill every column before moving to the next station. Incomplete notes are useless notes — and on a real project, they can lead to costly grade errors.
Label the benchmark at the top of the page with its known elevation. After your last foresight, check your arithmetic: the last elevation should close back to within an acceptable tolerance of the starting benchmark if you run a loop.
1. PPE: Hard hat, safety glasses, and steel-toed boots are required on the pad at all times.
2. Striking stakes: Wear gloves when swinging the sledgehammer. Check that no one is within the swing arc before striking.
3. Equipment traffic: The outdoor pad may be used by other classes. Stay in your designated work zone and maintain awareness of any moving machinery. If a machine approaches, stop work and step back until it clears.
4. Carrying the rod: Carry the Philadelphia rod horizontally, below shoulder height, to avoid striking overhead utilities or other people. Call out "rod coming through" when moving in a group.
5. Tripod stability: Firmly press tripod legs into the ground. A tipping level can be damaged beyond repair and can injure bystanders.
After you read all five stakes, return your rod to the benchmark and take a final backsight. If your computed elevation of the benchmark from this check reading differs from the known elevation by more than the acceptable closure tolerance for the exercise, re-run your notes to find the error. A systematic error (same direction every time) usually means a rod-reading mistake or a math error in HI. A random error often means the rod was not held plumb — use a rod level or gently rock the rod and take the lowest reading, which corresponds to the plumb position.
Answer each question, then check it. Nothing is recorded; this is your own practice.
A free tech program — complimentary, as our commitment to get America working. Help us build VoTechWorks. Tell us what works, what doesn’t, and what you want to learn.
Does the school offer financial aid?
No. We don’t offer financial aid because we’re free. No, really: completely free.
Do you offer industry certification?
No. We are not certified yet, so we can’t offer that to students. What we do offer is knowledge and understanding of a trade.
Enroll first in the trade you’re interested in. You get your key, your program opens, and you begin studying.
Enroll free →