Objective. Given a project brief and set of marine drawings, the student will produce a complete fabrication plan—bill of materials, weld symbol interpretation map, fit-up sequence, hazard identification, and pre-task safety checklist—that an evaluator judges complete and accurate.
In professional shipbuilding shops, no welder or fitter picks up a tool until a complete fabrication plan exists and a supervisor has signed off on it. Rushing into cutting and welding without a plan produces distorted panels, mislocated parts, weld defects, and—most seriously—injuries. This lesson teaches you how to build that plan from scratch using your drawing set, reference standards, and a systematic hazard-identification process.
Your assigned assembly arrives as two types of drawings: isometric views, which show the part in a three-dimensional perspective so you can visualize overall shape and orientation, and orthographic (plan/elevation/section) views, which give you precise dimensions in each of the three principal planes. Neither view alone is enough; use them together.
Work through the drawing set systematically:
1. Read the title block first. Record the drawing number, revision level, scale, material specification (for example, ASTM A131 Grade A mild steel or 5083-H116 aluminum), and the applicable welding code (usually AWS D1.1 for steel or AWS D1.2 for aluminum in marine work).
2. List every part. Transfer each part number, quantity, material grade, and cut dimension to your Bill of Materials (BOM) template. Double-check quantities—missing a duplicate part causes a stoppage mid-build.
3. Map every weld symbol. Using the AWS A2.4 reference chart, decode each weld symbol: identify the joint type (butt, fillet, groove), weld size or throat, process if called out, and any finishing requirements. Record each symbol on the weld map template, noting which drawing view it appears on so you can locate it physically on the assembly.
4. Flag joint designations. Marine drawings frequently label structural joints T1, T2, B1, and so on. These correspond to ABS or classification-society joint categories that set minimum weld size and inspection requirements. Write these designations on your weld map next to the symbol.
After completing the weld map independently, compare it with a partner. Discrepancies nearly always trace to misreading a weld symbol tail note or overlooking a section view. Resolve every discrepancy by returning to the drawing notes and the A2.4 chart—never by guessing.
Distortion is the enemy of precision marine fabrication. Steel shrinks as weld metal cools; if you weld one side of a panel completely before the other, the assembly will bow. NCCER Shipfitting distortion-control principles give you four main tools:
Document each step on the sequencing worksheet: step number, parts being joined, method (tack, root pass, fill, cap), and the distortion-control technique applied. Write a brief written rationale for each major decision; your evaluator will read this to confirm you understand why, not just what.
A JHA breaks the entire build into task steps, then lists the hazards and controls for each step. For a marine fabrication capstone, the major hazard categories are:
Hot-work hazards: Welding, grinding, and cutting generate sparks and UV radiation. Before any hot work begins, a hot-work permit must be issued, the area must be cleared of flammable materials within the required radius, a fire watch must be posted, and a fire extinguisher must be immediately available. Confirm permit requirements with your instructor; in real shipyards these are mandatory under both OSHA regulations and facility procedures.
Lockout/Tagout (LOTO): Before performing any maintenance, adjustments, or work near powered equipment—including welding machines, grinders, plasma cutters, overhead cranes, or ventilation systems—stored energy must be isolated and locked out per your facility's LOTO procedure (OSHA 29 CFR 1910.147 is the controlling standard). Each authorized worker places their own lock. On your JHA, identify every LOTO point by equipment name and location.
PPE by phase:
Fall hazards: Any work above four feet on scaffolding or elevated structures requires fall protection planning. Note anchor points and harness inspection on the JHA.
Confined-space hazards: Interior tank or void work may require a permit-required confined-space entry procedure, atmospheric testing, and a trained attendant stationed outside.
Present the completed JHA to your instructor for a line-by-line review. No fabrication begins until the instructor signs off. This mirrors real industry practice and is a hard requirement for your 20-point rubric: any safety item left blank or incorrect stops your progress regardless of how well the rest of the plan scores.
Your deliverables—BOM, weld map, sequence document, and JHA—form a single integrated fabrication plan. Think of them as linked: the BOM tells you what material to order, the weld map tells you where every joint goes and what code applies, the sequence tells you the order of operations, and the JHA tells you how to do all of it without injuring yourself or others. Experienced marine fabricators develop this planning habit on every job, large or small.