Insulation Installation: Blankets, Spray Foam, and Fire-Rated Systems

Objective. The student installs mineral wool blanket insulation and a fire-rated foam collar around a pipe penetration to manufacturer instructions and the applicable shipboard specification, with no visible gaps, correct compression, and collar fully seated and fastened.

Why Insulation Matters on a Ship

Shipboard insulation serves three distinct purposes: thermal control, condensation prevention, and fire containment. In a marine environment, steel hull plating conducts heat and cold rapidly, and uncontrolled condensation leads to corrosion and mold. Fire, however, is the greatest threat at sea—escape routes are limited and a fire that travels through a bulkhead penetration can overwhelm a vessel in minutes. Correctly installed insulation addresses all three concerns simultaneously. This lesson covers mineral wool blanket installation and fire-rated intumescent collar installation at pipe penetrations.

Mineral Wool Blanket Insulation

Mineral wool (also called rock wool or slag wool) is the dominant blanket insulation in commercial shipbuilding because it is non-combustible, dimensionally stable when wet, and resistant to vermin. It is sold in rolls or batts of varying density and thickness. The shipboard insulation specification—not a general construction guide—governs the required R-value, minimum installed thickness, and fastening spacing for each compartment type.

Cutting and Fitting

Always cut mineral wool with a sharp utility knife and straight edge on a stable work surface. Measure the bay width between frames, add nothing for compression allowance—the material should fill the bay snugly without being crushed. When fitting around pipes, brackets, or other obstructions, make relief cuts and fit pieces tightly together so no void larger than 1/4 inch remains. Butt seams should be staggered when double-layer installations are specified.

Compression Limits

Over-compressing mineral wool reduces its effective R-value and can crack the facing. Under-compressing leaves air gaps that defeat thermal and acoustic performance. Follow the manufacturer's published minimum installed thickness. If the spec calls for 2-inch blanket, the installed thickness measured at the clips must not fall below the manufacturer's stated minimum—typically stated as a percentage of nominal thickness. Check the product data sheet for the exact figure.

Fastening with Speed Clips

Speed clips (also called insulation pins and clips) are the standard fastener in shipbuilding. Weld pins to the steel structure at the spacing stated in the specification—commonly on a grid pattern. Press the blanket over the pins, then snap the speed clip over each pin to retain the blanket. Bend or cut any pin that protrudes more than 1/8 inch beyond the clip to eliminate a puncture hazard. Work from the bottom of the bay upward so each course supports the next.

Fire-Rated Penetration Collar Installation

Every time a combustible pipe or a pipe with a combustible liner passes through a fire-rated bulkhead or deck, the annular gap must be sealed with a listed intumescent fire collar. Intumescent material expands rapidly under heat, crushing and sealing the opening before fire and smoke can pass. The word listed means the product has been independently tested and approved by a recognized testing laboratory (such as UL) for a specific fire-resistance rating—typically expressed in hours (e.g., 2-hour rating).

Reading the Manufacturer's Instructions

Listed products may only be installed exactly as tested. The manufacturer's written instructions specify: pipe material and diameter range the collar is approved for, required clearance between pipe OD and sleeve ID, fastener type and torque or seating depth, minimum distance from collar face to combustible material, and whether the collar must be on one side or both sides of the bulkhead. Substituting fasteners or altering dimensions voids the listing.

Installation Sequence

1. Verify the pipe diameter and material match the collar listing.

2. Confirm the sleeve ID provides the clearance stated in the instructions.

3. Slide or clamp the collar onto the pipe at the bulkhead face as directed.

4. Align the collar with any orientation marks (some collars are directional).

5. Insert and tighten all fasteners to the manufacturer's specified condition.

6. Inspect that the collar face is fully seated flush against the bulkhead with no gap between collar and surface.

7. Document with a photograph showing the collar, pipe, and bulkhead—this photo enters the work package.

Safety: Mineral Wool Respiratory and Skin Hazards

Mineral wool fibers are a respiratory and skin irritant. NIOSH classifies refractory ceramic fibers as a potential occupational carcinogen; while mineral wool used in building and marine applications is a different fiber category, NIOSH still recommends respiratory protection during installation and cutting. Minimum required PPE:

For intumescent collar work, standard PPE (safety glasses, gloves) is sufficient during normal installation. If cutting a collar to length is required, a dust mask is still inadequate—use an N95.

Quality Verification

The inspector checks two things before signing off:

1. Blanket installation: No visible gap greater than 1/4 inch at any seam, joint, or obstruction cutout. Installed thickness at all clip locations must meet the manufacturer's minimum. Clips are properly closed and no pins protrude unsafely.

2. Collar installation: Every step in the manufacturer's instructions is completed in the correct sequence. The collar is fully seated and fastened. The photograph is legible, dated, and filed in the work package.

A failed insulation installation is not a minor defect—it is a fire and moisture risk that must be corrected before the space is closed out.

Key terms9

Mineral woolNon-combustible inorganic fiber insulation made from rock or slag, used in shipbuilding for thermal, acoustic, and fire control; irritating to skin, eyes, and lungs during handling.
Speed clip (insulation pin and clip)A two-part fastener system used in shipbuilding: a welded steel pin penetrates the insulation blanket and a spring-steel clip snaps over the pin to hold the blanket against the hull structure.
Intumescent materialA substance that expands significantly in volume when exposed to heat, used in fire collars and seals to close openings and prevent fire and smoke spread through penetrations.
Listed productA product that has been tested and approved by an independent, nationally recognized testing laboratory for a specific application and rating; must be installed exactly as tested to maintain the listing.
Fire-rated penetration collarA listed intumescent device clamped or fastened around a pipe at a fire-rated bulkhead or deck opening to maintain the fire-resistance rating of that assembly.
Compression limitThe manufacturer-specified minimum installed thickness of insulation blanket; over-compressing below this limit reduces thermal performance and can damage the product.
Annular gapThe ring-shaped open space between the outside diameter of a pipe and the inside diameter of the sleeve or opening through which it passes; must be sealed at fire-rated assemblies.
N95 respiratorA NIOSH-approved filtering facepiece respirator that filters at least 95% of airborne particles; the minimum respiratory protection required when cutting or handling mineral wool insulation.
Work packageThe collection of documentation—drawings, specifications, inspection records, and photographs—that accompanies a shipbuilding task and provides evidence that work was completed correctly.

Worked examples4

1. A hull bay has an irregular frame spacing of 22 inches on one side and 24 inches on the other. The mineral wool blanket roll is 48 inches wide. What width should you cut the piece, and how do you handle the taper?
  1. Measure both edges of the bay: 22 inches at one frame and 24 inches at the other frame.
  2. Cut the blanket as a trapezoid: mark 22 inches at one end and 24 inches at the other end along the same edge, connect with a diagonal line, and cut along that line with a utility knife and straight edge.
  3. Test-fit the piece; it should fill the bay snugly at both edges with no gap greater than 1/4 inch.
  4. If a small gap remains at the narrow end, cut a thin filler strip from scrap blanket and tuck it in to close the gap before clipping.
Answer: Cut a tapered piece 22 inches wide at one end and 24 inches wide at the other to match the bay geometry; use a filler strip if any gap exceeds 1/4 inch.
2. The specification requires speed clips on a 12-inch by 12-inch grid across a bay that measures 24 inches wide by 36 inches tall. How many pins must be welded to cover that bay?
  1. Determine the number of columns: 24 inches ÷ 12 inches = 2 spaces, so pins at 0 in, 12 in, and 24 in = 3 columns. However, pins at the very frame edge are impractical; in practice the grid starts 6 inches from each frame (half-spacing at edges). Recalculate: starting at 6 inches, next at 18 inches = 2 columns interior. Add edge pins if the spec requires them—use the spec as written.
  2. For this problem, assume the spec means a full 12-inch grid starting at 6 inches from each edge (common practice): columns at 6 in and 18 in = 2 columns.
  3. Determine the number of rows: 36 inches tall, starting at 6 inches from bottom, then 18 in, then 30 in = 3 rows.
  4. Total pins = 2 columns × 3 rows = 6 pins.
Answer: 6 pins arranged in 2 columns and 3 rows at a 12-inch grid with a 6-inch edge offset.
3. A mineral wool blanket is nominally 2 inches thick. The manufacturer states the minimum installed thickness is 90% of nominal thickness. What is the minimum acceptable installed thickness in inches?
  1. Convert 90% to a decimal: 90 ÷ 100 = 0.90.
  2. Multiply nominal thickness by the decimal: 2.00 inches × 0.90 = 1.80 inches.
  3. The installed thickness must be at least 1.80 inches at every clip point.
Answer: The minimum installed thickness is 1.80 inches (1 and 13/16 inches rounded to the nearest 1/16 inch).
4. You need to cut a rectangular piece of mineral wool to fit around a 4-inch diameter pipe that passes through the center of an 18-inch wide by 24-inch tall bay section. What size hole do you cut, and where is its center located?
  1. Locate the pipe center: 18 ÷ 2 = 9 inches from either side edge; 24 ÷ 2 = 12 inches from top and bottom edge.
  2. The pipe OD is 4 inches, so the hole radius is 2 inches. Cut a circular hole of 4-inch diameter centered at (9 in, 12 in) on the blanket.
  3. After fitting, any gap between the hole edge and the pipe surface that exceeds 1/4 inch must be packed with a cut strip of mineral wool to eliminate the void.
  4. Confirm no gap at the pipe perimeter exceeds 1/4 inch before clipping the blanket in place.
Answer: Cut a 4-inch diameter circular hole centered 9 inches from the side edges and 12 inches from top and bottom; fill any perimeter gap greater than 1/4 inch with a mineral wool strip.

The math in this lesson2

Learners count speed-clip pins on a 12-inch grid across a 24 by 36 inch bay.
6.RP.37.RP.3
Brush up in the math halls at newSchoolWorks.com:
In class: Instructor demo and safety briefing: respiratory hazards of mineral wool (NIOSH reference), required PPE (N95 or better respirator, gloves, long sleeves), handling and cutting technique, compression limits, fastening with speed clips, and fitting blankets around obstructions without voids. · Hands-on installation practice: each student cuts mineral wool blankets to fit a mock hull bay (irregular frame spacing), installs with speed clips at specified spacing, and achieves full coverage with no visible gap greater than 1/4 inch, verified by instructor walk-around. · Fire-rated penetration collar installation: students fit a listed intumescent pipe collar around a sleeve penetration in a mock bulkhead following manufacturer's written instructions, fasten per instructions, and photograph the finished installation for their work package.
Materials: Mineral wool blanket insulation rolls, intumescent pipe collars (listed product), speed clips and pins, utility knife, straight edge, tape measure, mock hull bay fixture, mock bulkhead with installed pipe sleeves, N95 respirators, safety glasses, nitrile gloves, long-sleeve coveralls, manufacturer installation instructions, shipboard insulation specification excerpt
Check: Instructor inspects blanket installation for gaps (none greater than 1/4 inch) and compression (not over-compressed below manufacturer minimum thickness); collar installation checked against manufacturer instructions step-by-step; both must pass; photograph must be in work package.

Practice check8

Answer each question, then check it. Nothing is recorded; this is your own practice.

Safety and Health
1. When cutting mineral wool blanket insulation in an enclosed compartment, what is the minimum NIOSH-recognized respiratory protection required?
Marine Systems Installation
2. What does the term 'listed' mean when applied to an intumescent fire collar?
Fire Protection Systems
3. Which of the following actions would void the fire-resistance listing of an intumescent pipe collar?
Quality Assurance and Inspection
4. The shipboard insulation specification allows a maximum gap of 1/4 inch between mineral wool blanket sections. After installing a blanket around a pipe bracket, the inspector finds a 3/8-inch gap on one side. What is the correct action?
Marine Systems Installation
5. Why is over-compressing a mineral wool blanket below the manufacturer's minimum installed thickness a problem?
Safety and Health
6. When installing insulation speed clips, what is the correct action if a welded pin protrudes more than 1/8 inch beyond the closed clip?
Blueprint Reading and Specifications
7. What document governs the required R-value, minimum installed thickness, and fastening spacing for insulation in a specific shipboard compartment?
Fire Protection Systems
8. An intumescent pipe collar is installed at a bulkhead penetration but the collar face has a visible gap between it and the bulkhead surface. Why is this a deficiency that must be corrected before close-out?