Bulkhead and Longitudinal Fit-Up

Objective. Students will position and tack a transverse bulkhead and at least two longitudinal stiffeners in a simulated hull-section jig, achieving plumb, fair, and spacing within tolerances and completing the required fit-up inspection checklist.

Bulkhead and Longitudinal Fit-Up

A ship's hull is a system of interlocking parts that must line up precisely before a single permanent weld is laid. Transverse bulkheads divide the hull into watertight compartments and carry lateral loads. Longitudinal stiffeners run fore-and-aft along the shell plating and bottom, resisting bending along the ship's length. Getting both elements plumb, fair, and correctly spaced during fit-up is the shipfitter's core responsibility — errors allowed to pass at this stage are amplified by every weld and plate that follows.

The Fit-Up Sequence

Shipyards follow a consistent sequence for a reason: each step creates the reference that the next step depends on.

1. Set the keel baseline. The keel bar is the ship's centerline reference. Every measurement of height, spacing, and plumb originates here. Confirm the jig's keel bar is level before touching anything else.

2. Establish frame stations. Frame station lines are marked on the keel bar and on the jig rails at the correct spacing shown on the construction drawing. Check that your tape reads from the correct baseline end — a reversed start causes every station to be wrong.

3. Plumb each frame. A frame must stand perpendicular to the keel plane. Use a plumb bob dropped from the frame's centerline mark, or a calibrated digital level placed on the frame web. The standard tolerance used in this program is ±1/8 inch per 10 feet of height. Tack the frame only after plumb is confirmed.

4. Fair the longitudinals. A longitudinal stiffener must lie in a smooth, continuous curve (or straight line) from frame to frame — no kinks, no hollows. Hold a flexible straight-edge batten along the stiffener's face to check fairness. A shadow gap between batten and stiffener indicates a hard spot or hollow that must be corrected before tacking.

5. Fit the bulkhead. Once frames and longitudinals are secured, drop the bulkhead plate into position. The bulkhead must be plumb athwartship (side-to-side) and stand at the correct frame station fore-and-aft. Clamp it with strong-backs so it cannot move while you verify dimensions.

Plumb, Fair, and Square — What Each Means

Tack Welds

Tack welds are small, temporary welds that hold parts in position until full welding is complete. In marine fabrication, tacks must be treated like real welds: wrong placement or poor fusion can crack under the stress of subsequent welding and leave unfused areas in the final joint.

Strong-Backs and Clamps

A strong-back is a bar or beam temporarily welded or clamped across a joint to hold parts in alignment and resist distortion. Use C-clamps and locking pliers to apply clamping force before tacking. Never rely on the tack weld alone to pull misaligned parts together — force the parts to the correct position with clamps, then tack.

Fit-Up Inspection Checklist

Before any permanent welding begins, every critical dimension must be verified and documented. The checklist used in this lab covers:

All items must receive instructor sign-off before the team moves on. This mirrors shipyard practice, where a fit-up inspector (often a Quality Control inspector or lead fitter) must approve fit-up before the welder is authorized to begin.

Safety for This Lab

Key terms9

Transverse bulkheadA structural partition running athwartship (side to side) that divides the hull into separate compartments and resists lateral loads.
Longitudinal stiffenerA structural member running fore-and-aft along the hull that resists bending along the ship's length; commonly flat bar, angle, or T-bar.
PlumbPerfectly vertical, as confirmed by a plumb bob or digital level; a bulkhead out of plumb creates misalignment that compounds through subsequent assembly.
FairSmooth and continuous with no abrupt changes in curvature or direction; checked with a flexible batten laid against the member.
Strong-backA temporary bar or beam clamped or tacked across a joint to hold parts in correct alignment and limit distortion during fit-up and welding.
Tack weldA short, temporary weld used to hold parts in position before full welding; must meet the same quality standards (no cracks, no porosity) as production welds.
BattenA thin, flexible strip used to check the fairness of a curved or straight member by revealing hollows, kinks, or hard spots.
Frame stationA designated athwartship location along the hull's length, marked on the baseline; frames, bulkheads, and floors are fitted at these stations according to the construction drawing.
Fit-up inspection checklistA documented form verifying that all critical dimensions — plumb, spacing, fairness, and tack quality — meet specification before permanent welding begins.

Worked examples4

1. The bulkhead stands 7 feet 6 inches (90 inches) tall. The maximum allowable out-of-plumb is ±1/8 inch per 10 feet. What is the maximum total offset allowed at the top of this bulkhead?
  1. Convert bulkhead height to feet: 90 inches ÷ 12 = 7.5 feet.
  2. Find how many 10-foot increments fit in 7.5 feet: 7.5 ÷ 10 = 0.75.
  3. Multiply the rate by the height ratio: 0.75 × 1/8 inch = 0.75 × 0.125 inch = 0.09375 inch.
  4. Round to the nearest practical fraction: 0.09375 inch ≈ 3/32 inch.
Answer: The maximum allowable total out-of-plumb offset at the top of a 7-foot-6-inch bulkhead is approximately 3/32 inch (≈ 0.094 inch).
2. Your construction drawing shows Longitudinal A located 18 inches from the keel centerline and Longitudinal B located 34 inches from the keel centerline. After fit-up, you measure Longitudinal A at 17 7/8 inches and Longitudinal B at 34 1/4 inches. Do either longitudinal pass the ±1/8-inch tolerance?
  1. Check Longitudinal A: Required = 18 inches, Measured = 17 7/8 inches. Difference = 18 − 17.875 = 0.125 inch = 1/8 inch. This is exactly at the tolerance limit, which is acceptable (tolerance is ±1/8 inch).
  2. Check Longitudinal B: Required = 34 inches, Measured = 34 1/4 inches = 34.25 inches. Difference = 34.25 − 34 = 0.25 inch = 1/4 inch. This exceeds ±1/8 inch.
  3. Longitudinal A passes. Longitudinal B must be repositioned before tacking.
Answer: Longitudinal A passes (offset = 1/8 inch, exactly at limit). Longitudinal B fails (offset = 1/4 inch, exceeds the ±1/8-inch tolerance) and must be adjusted.
3. You need to verify that the bulkhead plate is square by checking diagonals. You measure one diagonal at 62 1/4 inches and the other at 62 9/16 inches. What is the difference, and is the plate square within 1/8-inch allowance?
  1. Convert both measurements to sixteenths for easy subtraction: 62 1/4 inch = 62 4/16 inch; 62 9/16 inch = 62 9/16 inch.
  2. Subtract: 62 9/16 − 62 4/16 = 5/16 inch.
  3. Compare to allowance: 5/16 inch = 0.3125 inch, which exceeds 1/8 inch (0.125 inch).
  4. Conclusion: the diagonals are not equal within tolerance; the plate is out of square and must be adjusted.
Answer: The diagonal difference is 5/16 inch, which exceeds the 1/8-inch allowance. The bulkhead is out of square and must be repositioned.
4. The fit-up drawing specifies tack welds spaced every 12 inches along the bulkhead-to-keel joint, which measures 48 inches long. How many tack welds are required, and at what positions?
  1. Divide the joint length by the spacing interval: 48 ÷ 12 = 4 intervals.
  2. Number of tacks = number of intervals + 1 = 4 + 1 = 5 tacks (one at each end and one at each intermediate point).
  3. Positions from the start of the joint: 0 inches, 12 inches, 24 inches, 36 inches, and 48 inches.
Answer: Five tack welds are required, placed at 0, 12, 24, 36, and 48 inches from the start of the joint.

The math in this lesson2

Learners scale a 1/8 inch per 10 feet plumb tolerance to a 90-inch bulkhead.
6.RP.37.NS.3
In class: Instructor walks students through a shipyard fit-up procedure, emphasizing the sequence: set keel baseline, establish frame stations, plumb each frame, fair longitudinals, then fit the bulkhead. · Students work in teams of two in a mock hull jig to position a pre-cut bulkhead plate, establish plumb using a plumb bob and digital level, tack it in place, then measure and set two longitudinal flat bars to their marked positions. · Teams complete a fit-up inspection checklist—checking spacing, plumb, fairness (using a batten), and tack-weld spacing—and have the instructor sign off each item before proceeding to the next.
Materials: Mock hull jig with keel bar and frame brackets, pre-cut mild-steel plate bulkhead, flat-bar longitudinals, clamps, strong-backs, MIG welder for tacking, plumb bob, digital level, 25-ft tape, straight-edge batten, fit-up inspection checklist
Check: Completed and signed fit-up inspection checklist: all critical dimensions (plumb ±1/8 inch per 10 ft, spacing ±1/8 inch, tack spacing within specification) must pass before sign-off; all items must be green to pass the lesson.

Practice check8

Answer each question, then check it. Nothing is recorded; this is your own practice.

NCCER Shipfitting — Layout and Assembly
1. What is the FIRST step in the shipyard fit-up sequence before establishing frame stations or fitting a bulkhead?
NCCER Shipfitting — Measurement and Tolerances
2. A shipfitter checks a 10-foot-tall bulkhead with a plumb bob and finds the top is offset 3/16 inch from plumb. What action is required?
NCCER Shipfitting — Layout and Assembly
3. Which tool is BEST suited for checking the fairness of a longitudinal stiffener?
Safety — Lockout/Tagout (OSHA General Industry / Shipyard)
4. Before changing a contact tip on a MIG welder during a tacking operation, a student should FIRST:
NCCER Shipfitting — Measurement and Tolerances
5. After fit-up, a team measures their longitudinal stiffener at 24 3/16 inches from the keel centerline against a required dimension of 24 inches. The tolerance is ±1/8 inch. What is the correct conclusion?
NCCER Shipfitting — Layout and Assembly
6. What is the purpose of a strong-back during bulkhead fit-up?
AWS D1.1 / NCCER Maritime Welding — Weld Quality
7. A quality-control inspector rejects a series of tack welds because they contain visible cracks. Why is this a disqualifying defect rather than a cosmetic concern?
NCCER Shipfitting / NCCER Maritime Welding — Fit-Up Practice
8. A 48-inch bulkhead-to-keel joint requires tack welds every 12 inches, starting from each end. A fitter places tacks at 0, 12, 24, 36, and 48 inches. How many tack welds did the fitter place, and is this correct?
Record this lesson on my transcript. Sign in with your key and enrollment email to record lessons (enroll free if you have no key). This page stays open to read and practise.