MFG-SHIP13-04 · Lesson 8 · 18 clock hours · lab
Bulkhead and Longitudinal Fit-Up
Objective. Students will position and tack a transverse bulkhead and at least two longitudinal stiffeners in a simulated hull-section jig, achieving plumb, fair, and spacing within tolerances and completing the required fit-up inspection checklist.
Bulkhead and Longitudinal Fit-Up
A ship's hull is a system of interlocking parts that must line up precisely before a single permanent weld is laid. Transverse bulkheads divide the hull into watertight compartments and carry lateral loads. Longitudinal stiffeners run fore-and-aft along the shell plating and bottom, resisting bending along the ship's length. Getting both elements plumb, fair, and correctly spaced during fit-up is the shipfitter's core responsibility — errors allowed to pass at this stage are amplified by every weld and plate that follows.
The Fit-Up Sequence
Shipyards follow a consistent sequence for a reason: each step creates the reference that the next step depends on.
1. Set the keel baseline. The keel bar is the ship's centerline reference. Every measurement of height, spacing, and plumb originates here. Confirm the jig's keel bar is level before touching anything else.
2. Establish frame stations. Frame station lines are marked on the keel bar and on the jig rails at the correct spacing shown on the construction drawing. Check that your tape reads from the correct baseline end — a reversed start causes every station to be wrong.
3. Plumb each frame. A frame must stand perpendicular to the keel plane. Use a plumb bob dropped from the frame's centerline mark, or a calibrated digital level placed on the frame web. The standard tolerance used in this program is ±1/8 inch per 10 feet of height. Tack the frame only after plumb is confirmed.
4. Fair the longitudinals. A longitudinal stiffener must lie in a smooth, continuous curve (or straight line) from frame to frame — no kinks, no hollows. Hold a flexible straight-edge batten along the stiffener's face to check fairness. A shadow gap between batten and stiffener indicates a hard spot or hollow that must be corrected before tacking.
5. Fit the bulkhead. Once frames and longitudinals are secured, drop the bulkhead plate into position. The bulkhead must be plumb athwartship (side-to-side) and stand at the correct frame station fore-and-aft. Clamp it with strong-backs so it cannot move while you verify dimensions.
Plumb, Fair, and Square — What Each Means
- Plumb means truly vertical. A plumb bob hangs on gravity's line; a digital level measures deviation from vertical in degrees and converts to linear offset.
- Fair means a smooth, continuous curve with no sudden changes in direction. Fairness is checked with a batten — a thin, flexible strip that conforms to an intended curve and reveals discontinuities.
- Square means 90° between two reference surfaces. Check square with a framing square or by measuring diagonals: if both diagonals of a rectangle are equal, the rectangle is square.
Tack Welds
Tack welds are small, temporary welds that hold parts in position until full welding is complete. In marine fabrication, tacks must be treated like real welds: wrong placement or poor fusion can crack under the stress of subsequent welding and leave unfused areas in the final joint.
- Space tacks as specified on the WPS (Welding Procedure Specification) or as directed by the supervisor — typically every 12 to 18 inches for structural fit-up, but always follow the project document.
- Tacks must be free of cracks, porosity visible to the eye, and undercut.
- Tacks at the start and end of a joint must be placed far enough back from the joint end to allow the welder to strike an arc without burning the edge.
- Use the designated MIG (GMAW) procedure for tacking; do not free-style with an unapproved process.
Strong-Backs and Clamps
A strong-back is a bar or beam temporarily welded or clamped across a joint to hold parts in alignment and resist distortion. Use C-clamps and locking pliers to apply clamping force before tacking. Never rely on the tack weld alone to pull misaligned parts together — force the parts to the correct position with clamps, then tack.
Fit-Up Inspection Checklist
Before any permanent welding begins, every critical dimension must be verified and documented. The checklist used in this lab covers:
- Plumb of bulkhead (±1/8 inch per 10 ft)
- Station location of bulkhead (fore-aft position per drawing)
- Spacing of longitudinals (±1/8 inch from marked position)
- Fairness of longitudinals (batten check — no visible gap)
- Tack-weld spacing (per specification)
- Tack-weld quality (no visible cracks or porosity)
All items must receive instructor sign-off before the team moves on. This mirrors shipyard practice, where a fit-up inspector (often a Quality Control inspector or lead fitter) must approve fit-up before the welder is authorized to begin.
Safety for This Lab
- Eye and face protection: Wear safety glasses at all times in the lab. Add a welding helmet (auto-darkening, appropriate shade) whenever tacking.
- Hand protection: Leather welding gloves when tacking or handling freshly tacked steel.
- Foot protection: Steel-toed boots — no exceptions around plate and bar stock.
- Housekeeping: Coiled tape measures, dropped battens, and loose clamps on the floor are trip hazards. Return tools to the bench when not in use.
- MIG welder setup: Inspect the gun cable, contact tip, and gas supply before use. Confirm shielding gas flow. Do not weld without ventilation.
- Lockout/Tagout awareness: If the MIG welder must be serviced (contact tip change, wire jam), follow your facility's LOTO procedure — de-energize and lock out before opening the wire-feed compartment.
- Lifting: Bulkhead plates and flat bars have sharp edges and significant weight. Use gloves, keep your back straight, and ask your partner to assist.
Key terms9
Transverse bulkheadA structural partition running athwartship (side to side) that divides the hull into separate compartments and resists lateral loads.
Longitudinal stiffenerA structural member running fore-and-aft along the hull that resists bending along the ship's length; commonly flat bar, angle, or T-bar.
PlumbPerfectly vertical, as confirmed by a plumb bob or digital level; a bulkhead out of plumb creates misalignment that compounds through subsequent assembly.
FairSmooth and continuous with no abrupt changes in curvature or direction; checked with a flexible batten laid against the member.
Strong-backA temporary bar or beam clamped or tacked across a joint to hold parts in correct alignment and limit distortion during fit-up and welding.
Tack weldA short, temporary weld used to hold parts in position before full welding; must meet the same quality standards (no cracks, no porosity) as production welds.
BattenA thin, flexible strip used to check the fairness of a curved or straight member by revealing hollows, kinks, or hard spots.
Frame stationA designated athwartship location along the hull's length, marked on the baseline; frames, bulkheads, and floors are fitted at these stations according to the construction drawing.
Fit-up inspection checklistA documented form verifying that all critical dimensions — plumb, spacing, fairness, and tack quality — meet specification before permanent welding begins.
Worked examples4
1. The bulkhead stands 7 feet 6 inches (90 inches) tall. The maximum allowable out-of-plumb is ±1/8 inch per 10 feet. What is the maximum total offset allowed at the top of this bulkhead?
- Convert bulkhead height to feet: 90 inches ÷ 12 = 7.5 feet.
- Find how many 10-foot increments fit in 7.5 feet: 7.5 ÷ 10 = 0.75.
- Multiply the rate by the height ratio: 0.75 × 1/8 inch = 0.75 × 0.125 inch = 0.09375 inch.
- Round to the nearest practical fraction: 0.09375 inch ≈ 3/32 inch.
Answer: The maximum allowable total out-of-plumb offset at the top of a 7-foot-6-inch bulkhead is approximately 3/32 inch (≈ 0.094 inch).
2. Your construction drawing shows Longitudinal A located 18 inches from the keel centerline and Longitudinal B located 34 inches from the keel centerline. After fit-up, you measure Longitudinal A at 17 7/8 inches and Longitudinal B at 34 1/4 inches. Do either longitudinal pass the ±1/8-inch tolerance?
- Check Longitudinal A: Required = 18 inches, Measured = 17 7/8 inches. Difference = 18 − 17.875 = 0.125 inch = 1/8 inch. This is exactly at the tolerance limit, which is acceptable (tolerance is ±1/8 inch).
- Check Longitudinal B: Required = 34 inches, Measured = 34 1/4 inches = 34.25 inches. Difference = 34.25 − 34 = 0.25 inch = 1/4 inch. This exceeds ±1/8 inch.
- Longitudinal A passes. Longitudinal B must be repositioned before tacking.
Answer: Longitudinal A passes (offset = 1/8 inch, exactly at limit). Longitudinal B fails (offset = 1/4 inch, exceeds the ±1/8-inch tolerance) and must be adjusted.
3. You need to verify that the bulkhead plate is square by checking diagonals. You measure one diagonal at 62 1/4 inches and the other at 62 9/16 inches. What is the difference, and is the plate square within 1/8-inch allowance?
- Convert both measurements to sixteenths for easy subtraction: 62 1/4 inch = 62 4/16 inch; 62 9/16 inch = 62 9/16 inch.
- Subtract: 62 9/16 − 62 4/16 = 5/16 inch.
- Compare to allowance: 5/16 inch = 0.3125 inch, which exceeds 1/8 inch (0.125 inch).
- Conclusion: the diagonals are not equal within tolerance; the plate is out of square and must be adjusted.
Answer: The diagonal difference is 5/16 inch, which exceeds the 1/8-inch allowance. The bulkhead is out of square and must be repositioned.
4. The fit-up drawing specifies tack welds spaced every 12 inches along the bulkhead-to-keel joint, which measures 48 inches long. How many tack welds are required, and at what positions?
- Divide the joint length by the spacing interval: 48 ÷ 12 = 4 intervals.
- Number of tacks = number of intervals + 1 = 4 + 1 = 5 tacks (one at each end and one at each intermediate point).
- Positions from the start of the joint: 0 inches, 12 inches, 24 inches, 36 inches, and 48 inches.
Answer: Five tack welds are required, placed at 0, 12, 24, 36, and 48 inches from the start of the joint.
The math in this lesson2
Learners scale a 1/8 inch per 10 feet plumb tolerance to a 90-inch bulkhead.
6.RP.37.NS.3
In class: Instructor walks students through a shipyard fit-up procedure, emphasizing the sequence: set keel baseline, establish frame stations, plumb each frame, fair longitudinals, then fit the bulkhead. · Students work in teams of two in a mock hull jig to position a pre-cut bulkhead plate, establish plumb using a plumb bob and digital level, tack it in place, then measure and set two longitudinal flat bars to their marked positions. · Teams complete a fit-up inspection checklist—checking spacing, plumb, fairness (using a batten), and tack-weld spacing—and have the instructor sign off each item before proceeding to the next.
Materials: Mock hull jig with keel bar and frame brackets, pre-cut mild-steel plate bulkhead, flat-bar longitudinals, clamps, strong-backs, MIG welder for tacking, plumb bob, digital level, 25-ft tape, straight-edge batten, fit-up inspection checklist
Check: Completed and signed fit-up inspection checklist: all critical dimensions (plumb ±1/8 inch per 10 ft, spacing ±1/8 inch, tack spacing within specification) must pass before sign-off; all items must be green to pass the lesson.
Practice check8
Answer each question, then check it. Nothing is recorded; this is your own practice.
Record this lesson on my transcript. Sign in with your key and enrollment email to record lessons (enroll free if you have no key). This page stays open to read and practise.