🚧 Under construction — VoTechWorks is being built. A free tech program — complimentary, as our commitment to get America working.
voTechWorksGrade 13 · a vocational technology learning center, by urbanicity
newSchoolWorks.com › VoTechWorks › Building & Construction › Electrical Lineworker › Rigging for Electrical Linework › Lesson 4
BLD-LINE69-04 · Lesson 4 · 6 clock hours · demo

Hand Signals, Tag Lines, and Communication During Lifts

Objective. Students will correctly perform and interpret all standard ASME B30.3 crane hand signals and demonstrate proper two-person tag-line control of a suspended load during a simulated lift on a training apparatus or boom truck.

⚠ Pending professional review

This lesson, its worked examples and its practice questions has not yet been verified by a licensed professional engineer or master tradesperson or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.

VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.

Why Signals and Tag Lines Matter

Every rigging accident investigation in electrical linework points to the same root causes: a load that moved when no one expected it, a signal that was misread, or a tag line that went slack at the wrong moment. When you add the hazard of nearby energized conductors, a swinging load is not just a struck-by risk — it can create an arc flash or ground fault that kills everyone in the work zone. Clear, standardized hand signals and disciplined tag-line technique are the front-line controls that keep suspended loads predictable and workers safe.

The Signal Person's Role

ASME B30.3 — the standard that governs construction-type cranes — designates the signal person as the single authorized voice between the work crew and the equipment operator. Only one signal person gives signals to the operator at any time. The operator obeys only that person's signals, except for an emergency stop, which anyone on the site may give.

Before the lift begins, the crew must agree on who the signal person is and confirm the communication method (hand signals, radio, or both). If radio is used, hand signals remain the backup. The signal person must maintain a clear line of sight to the operator and the load throughout the lift. If line of sight is lost for any reason, the signal person immediately gives the Dog Everything signal — all motion stops until communication is re-established.

Standard ASME B30.3 Hand Signals

Learn every signal so it becomes automatic. Each description below matches the poster you will use in class.

Practice each signal until you can produce it without thinking. In the role-play exercise, an ambiguous or incomplete signal means the lift stops — exactly as it would on a job site.

Communicating During a Lift

Good communication is continuous, not just at the start. The signal person watches the load, the rigging, and the clearance zones simultaneously. Key habits:

1. Pre-lift brief: Every lift gets a brief that covers the load weight, rigging plan, travel path, and designated clearance zones (especially any energized conductor buffers).

2. Positive confirmation: Before giving the first hoist signal, the signal person confirms that all crew members are clear of the load's travel path.

3. Slow and deliberate: Signal one motion at a time. Never combine two motions into a single gesture — the operator may interpret only one of them.

4. Hold on ambiguity: If anything is uncertain, signal Dog Everything and talk it through before continuing.

Tag-Line Fundamentals

A tag line is a rope attached to a suspended load to control its rotation and lateral position. Tag lines do not lift the load — the rigging does that. Tag lines prevent the load from spinning, swinging into obstacles, or drifting into clearance zones.

Attachment: Attach tag lines to a secure point on the load, low enough to give good lateral leverage. Never attach a tag line to the rigging hardware or the hook.

Length: Tag lines should be long enough that handlers stay well clear of the load and never directly under it. A minimum of 20 feet is the standard starting point; longer is often better.

Two-person control: Two tag-line handlers work as a team, one on each side of the load's travel path. Each handler maintains slight tension — the line is never slack, but neither handler pulls hard enough to fight the other or the rigging. Communicate verbally: call out "tension" when you take up slack, "easing" when you let line out, and "stop" if the load moves toward a hazard.

Gloves and grip: Always wear leather lineman's gloves when handling tag lines. Never wrap a tag line around your hand, wrist, or body — a sudden load shift can drag you off your feet or into the load.

Clearance zones: In electrical linework, flag or cone off the minimum approach distance to any energized conductor before the lift begins. Tag-line handlers must position themselves so their bodies stay outside those zones, and they must never allow the load or the tag line itself to enter the zone.

Safety Priorities for Every Lift

Key terms8

ASME B30.3The American Society of Mechanical Engineers standard governing construction-type cranes; it defines, among other things, the standardized hand signals all signal persons and operators must use.
Signal personThe one designated crew member authorized to give motion signals to the crane or equipment operator during a lift; the operator follows only this person's signals except for an emergency stop.
Dog EverythingThe ASME B30.3 hand signal — hands clasped in front of the body — that commands all crane or hoist motion to stop and remain stopped until further notice.
Tag lineA rope attached to a suspended load to control its rotation and lateral movement without lifting it; used in pairs to keep the load on a precise travel path.
Fall zoneThe area beneath and around a suspended load where workers could be struck if the load drops or the rigging fails; all non-essential personnel must stay out of this zone.
Emergency stop signalBoth arms extended laterally with palms down, waved rapidly; the only signal that any person on the work site — not just the designated signal person — is authorized to give.
Minimum approach distanceThe closest distance a worker or any conductive object may come to an energized conductor; established by OSHA and applicable utility safety rules, and marked with cones or flags before overhead lifts begin.
Pre-lift briefA short meeting held by the crew before every lift to confirm load weight, rigging plan, travel path, hazards, clearance zones, and the identity of the designated signal person.
In class: Instructor demonstration of all ASME B30.3 standard hand signals (hoist, lower, stop, emergency stop, travel, swing, extend/retract boom, dog everything) using a poster and live demonstration; students practice each signal in unison, then quiz each other in pairs using signal flashcards. · Role-play exercise: students rotate through the roles of signal person and equipment operator (simulated with a training boom truck or a block-and-tackle apparatus) for a series of scripted lift scenarios; the 'operator' may only respond to correct signals—an incorrect or ambiguous signal triggers an immediate stop, and the pair must restart. · Tag-line lab: a weighted mock load (sandbag, approximately 50 lb) is suspended from a boom or overhead frame; two students apply tag lines at appropriate anchor points, then direct the load through a simulated travel path past a mock obstacle (a flag on a post representing an energized conductor clearance zone) without the load contacting the obstacle or either tag line going slack.
Materials: ASME B30.3 hand signal poster and flashcard set, training boom truck or overhead block-and-tackle apparatus, 50 lb sandbag mock load, two tag lines (minimum 20 ft each), hard hats, safety glasses, hi-vis vests, cones to mark clearance zones.
Check: Instructor observes each student performing the complete ASME B30.3 signal set; student must produce all signals correctly without a prompt—one re-try permitted per signal; plus tag-line lab scored on load control (no contact with obstacle) and proper communication—both tasks must be completed successfully to pass.

Practice check8

Answer each question, then check it. Nothing is recorded; this is your own practice.

NCCER Power Line Worker — Rigging and Hoisting Safety
1. Under ASME B30.3, who is authorized to give the Emergency Stop signal during a crane lift?
NCCER Power Line Worker — Rigging and Hoisting Safety
2. A signal person loses sight of the suspended load as it moves behind a utility pole. What is the correct immediate action?
NCCER Power Line Worker — Rigging and Hoisting Safety
3. Which ASME B30.3 hand signal is made by holding the forearm vertical with the forefinger pointing up while making small horizontal circles with the wrist?
OSHA 10 — Struck-By and Rigging Hazards
4. During the tag-line lab, a student wraps the tag line twice around her hand for a better grip. Why must the instructor stop this practice immediately?
NCCER Power Line Worker — Electrical Hazard Awareness
5. Two tag-line handlers are guiding a mock load past a flagged clearance zone representing an energized conductor. The load begins to drift toward the flag. What is the correct team response?
NCCER Power Line Worker — Rigging and Hoisting Safety
6. According to standard rigging practice, where should tag lines be attached on a suspended load?
NCCER Power Line Worker — Rigging and Hoisting Safety
7. In the role-play exercise, the student acting as 'operator' receives a signal that combines a Hoist gesture and a Swing gesture at the same moment. What is the correct operator response?
OSHA 10 — Hazard Communication and Job Hazard Analysis
8. What is the primary purpose of a pre-lift brief before an overhead rigging operation near electrical conductors?
Record this lesson on my transcript. Sign in with your key and enrollment email to record lessons (enroll free if you have no key). This page stays open to read and practise.