BLD-LINE69-03 · Lesson 3 · 7 clock hours · lab

Outrigger Setup, Work-Zone Establishment, and Traffic Control

Objective. Students set up outriggers on a level and a simulated off-level surface, calculate safe working radius, and configure a MUTCD-compliant work zone with cones, signage, and flagging before any aerial operation begins.

⚠ Pending professional review

This lesson, its worked examples and its practice questions has not yet been verified by a licensed professional engineer or master tradesperson or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.

VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.

Why Outrigger Setup and Work-Zone Control Come First

No aerial lift operation begins until two things are complete: the machine is stable and the surrounding area is protected. Skipping or rushing either step is among the leading causes of bucket-truck fatalities and near-misses. This lesson covers both tasks in the order you will perform them on every job.

Outrigger Fundamentals

Outriggers are extendable steel legs that spread the machine's footprint and transfer load to the ground, preventing the truck from tipping when the boom is elevated. Most utility bucket trucks carry four outriggers—one at each corner—and each rests on an outrigger pad to distribute weight across soft or uneven ground.

Deployment sequence. Always follow the manufacturer's operator manual. The general sequence is: (1) Engage the parking brake and place the transmission in park or neutral as required. (2) Activate the power take-off (PTO) if the outriggers are hydraulically driven. (3) Extend outriggers fully to the width specified in the load chart. (4) Lower the outrigger feet until they contact the pad and the tires are either just off the ground or lightly loaded, per the manufacturer's specification. (5) Verify level using the bubble level indicator on the chassis.

Level tolerance. Manufacturers publish a maximum allowable out-of-level angle—commonly one to three degrees, but always check your specific machine. Exceeding this limit reduces the rated safe working load and increases tip risk. If the ground slopes beyond the allowed angle, you must find a better position, use cribbing as approved by your employer and the manufacturer, or call a supervisor.

Off-level surfaces. On a simulated angled pad, lower the uphill outrigger first to pull that side of the truck down, then bring the downhill side up to match. Re-check the bubble after each adjustment. Never operate with the bubble outside the marked ring.

Outrigger pad placement. Pads must sit on firm, stable ground—never over a trench, utility cover, or soft soil without adequate cribbing. Inspect pads for cracks before each use.

Safe Working Radius

The load chart posted inside the cab (or on the boom) shows the maximum allowable load at each combination of boom angle and radius. Radius is the horizontal distance from the center of rotation to the load. As the boom swings out or the angle decreases, radius increases and capacity decreases.

To calculate radius when you know boom length (L) and boom angle above horizontal (θ):

> Radius = L × cos(θ)

For example, a 40-foot boom at 45 degrees has a radius of 40 × cos(45°) ≈ 40 × 0.707 ≈ 28.3 feet. Always compare your calculated radius to the load chart before placing personnel or tools in the bucket.

MUTCD Work-Zone Requirements

The Manual on Uniform Traffic Control Devices (MUTCD), published by the Federal Highway Administration, sets the national standard for all temporary traffic control. Chapter 6 covers work zones. As a lineworker, you are responsible for understanding and applying these requirements any time you work on or near a public roadway.

The four components of a temporary traffic control zone:

1. Advance-warning area – Signs alert drivers that a work zone is ahead. Place the first sign well in advance of the activity area; the MUTCD provides a table of minimum distances based on posted speed.

2. Transition area – Tapers move traffic away from the work space using cones or other channelizing devices.

3. Activity area – The space where work actually occurs, including the work space and the traffic space.

4. Termination area – Returns traffic to its normal path downstream of the work.

Taper length formula. For low-speed roads (posted speed 45 mph or below), the MUTCD provides a formula based on lane width and speed. A widely used field approximation is:

> Taper length (feet) = Speed (mph) × Lane width (feet) / 60

For a 25 mph road with a 12-foot lane: 25 × 12 / 60 = 5 feet per cone spacing is not taper length—read the formula carefully. The full taper length = (Speed²/ 60) × lane width where speed ≤ 45 mph, giving 25² / 60 × 12 = 625/60 × 12 ≈ 125 feet of taper on a 25 mph, 12-foot lane.

Cone spacing within a taper is generally the posted speed in feet (e.g., 25 mph → cones every 25 feet along the taper).

Flaggers. When signal control or signs alone are not sufficient, a flagger must be used. Flaggers must be trained, wear high-visibility apparel meeting ANSI/ISEA 107 requirements, and use a STOP/SLOW paddle.

PPE Requirements for This Operation

Before stepping near the unit: hard hat (Class E for electrical work), safety glasses, high-visibility vest (Class 2 minimum on most roadways), and steel-toed boots rated for electrical hazard (EH). Gloves appropriate for the task should be within reach. If work involves energized lines, additional rubber insulating PPE applies—but outrigger setup and work-zone layout are conducted with the unit de-energized and no overhead contact.

Safety Rules—Non-Negotiable

Key terms10

OutriggerAn extendable steel leg on a bucket truck that increases the machine's footprint and transfers load to the ground to prevent tipping during elevated operations.
Outrigger padA thick plate placed under each outrigger foot to distribute the machine's weight over a larger ground area and prevent the foot from sinking into soft surfaces.
Safe working radiusThe horizontal distance from the center of the machine's rotation to the load; as radius increases, rated lifting or working capacity decreases per the load chart.
MUTCDManual on Uniform Traffic Control Devices; the Federal Highway Administration publication that sets national standards for signs, signals, and markings including temporary traffic control in work zones.
Taper lengthThe distance along a roadway over which cones or channelizing devices shift traffic from its normal lane into the adjusted path; calculated using speed and lane width.
Advance-warning areaThe section of a work zone where signs alert approaching drivers to the upcoming work activity before they reach the transition or activity area.
Bubble level indicatorA spirit level mounted on the truck chassis that shows whether the machine is within the manufacturer's allowable out-of-level tolerance before boom operation.
Power take-off (PTO)A mechanism that transfers power from the truck's engine to auxiliary equipment such as the hydraulic system that drives the outriggers and boom.
FlaggerA trained worker who uses a STOP/SLOW paddle and high-visibility apparel to manually direct traffic through or around a work zone when signs alone are insufficient.
Load chartA table posted in the cab or on the boom that specifies the maximum allowable load at each combination of boom angle and working radius for a specific machine.

Worked examples4

1. A bucket truck boom is 40 feet long and is positioned at a 45-degree angle above horizontal. What is the working radius?
  1. Write the formula: Radius = Boom length × cos(boom angle)
  2. Substitute values: Radius = 40 ft × cos(45°)
  3. cos(45°) = 0.707 (standard value)
  4. Radius = 40 × 0.707 = 28.28 ft
Answer: The working radius is approximately 28.3 feet. Compare this value to the load chart before operating.
2. You are setting up a work zone on a 25 mph residential road with a 12-foot lane width. Calculate the required taper length using the MUTCD low-speed formula: Taper length = (Speed² ÷ 60) × lane width.
  1. Identify variables: Speed = 25 mph, Lane width = 12 ft
  2. Square the speed: 25² = 625
  3. Divide by 60: 625 ÷ 60 ≈ 10.42
  4. Multiply by lane width: 10.42 × 12 ≈ 125 ft
Answer: The required taper length is approximately 125 feet.
3. Using the taper length from the previous example (125 feet on a 25 mph road), how many cones are needed for the taper if cones are spaced at the posted speed in feet (25-foot intervals), and what is the spacing between cones?
  1. Cone spacing = posted speed in mph expressed as feet = 25 ft apart
  2. Number of spaces = Taper length ÷ cone spacing = 125 ÷ 25 = 5 spaces
  3. Number of cones = number of spaces + 1 = 5 + 1 = 6 cones for the taper line
  4. Add cones for the longitudinal buffer and activity area as required by site conditions
Answer: Six cones placed 25 feet apart cover the 125-foot taper. Additional cones are required for the activity-area boundary.
4. A bucket truck boom is 50 feet long. The load chart shows that at a 30-foot radius the capacity is 500 lb, and at a 35-foot radius the capacity is 350 lb. The operator plans to use the boom at a 55-degree angle. Will the planned setup stay within the 500 lb capacity zone?
  1. Calculate radius: Radius = 50 × cos(55°)
  2. cos(55°) ≈ 0.574
  3. Radius = 50 × 0.574 = 28.7 ft
  4. 28.7 ft is less than 30 ft, so the setup falls within the 500 lb capacity zone on the load chart
Answer: Yes. At 55 degrees the radius is approximately 28.7 feet, which is within the 30-foot boundary for the 500 lb rating. The operator may proceed at loads up to 500 lb.

The math in this lesson1

Learners compute boom working radius 40 ft × cos 45° ≈ 28.3 ft to check the load chart.
G-SRT.8
Brush up in the math halls at newSchoolWorks.com:
In class: Hands-on outrigger deployment exercise: students level the unit on designated flat and angled pads, verify bubble level indicators, and record measurements; instructor checks each setup before signing off. · Work-zone layout drill using traffic cones, advance-warning signs, and taper spacing formula (speed limit × cone interval factor) for a simulated 25 mph road: students measure, place, and sketch the completed layout on a field diagram. · Tabletop scenario review: students receive three different site sketches (intersection work, highway shoulder, residential driveway) and must produce a compliant work-zone diagram for each, citing the applicable MUTCD section by general topic.
Materials: Aerial lift unit, outrigger pads, bubble level, 100 ft tape measure, traffic cones (minimum 10), advance-warning sign set, MUTCD Chapter 6 excerpts, site-sketch worksheets, pen, PPE (hard hat, safety glasses, high-vis vest, steel-toed boots)
Check: Outrigger setup is checked by instructor for level within manufacturer tolerance; work-zone layout is measured against MUTCD spacing requirements; students must pass both the flat and angled outrigger setups and correctly lay out at least two of three site scenarios.

Practice check8

Answer each question, then check it. Nothing is recorded; this is your own practice.

NCCER Power Line Worker – Aerial Lift Safety
1. What is the FIRST action a lineworker must take after parking a bucket truck and before deploying outriggers?
NCCER Power Line Worker – Aerial Lift Safety
2. A manufacturer specifies a maximum out-of-level tolerance of 2 degrees. During setup on a sloped surface the bubble indicator shows the truck is 3 degrees out of level. What should the operator do?
MUTCD Work-Zone Traffic Control
3. Using the MUTCD low-speed taper-length formula [Taper length = (Speed² ÷ 60) × lane width], what is the correct taper length for a 25 mph road with a 12-foot lane?
MUTCD Work-Zone Traffic Control
4. Which MUTCD chapter governs temporary traffic control in work zones?
NCCER Power Line Worker – Aerial Lift Operations
5. A boom is 35 feet long and positioned at 60 degrees above horizontal. What is the approximate working radius? (cos 60° = 0.500)
OSHA 10 – Construction Safety / Work-Zone Safety
6. What minimum ANSI/ISEA apparel class is generally required for a flagger directing traffic in a work zone on a public road?
MUTCD Work-Zone Traffic Control
7. On a 25 mph road, if cones in the taper are spaced at the posted speed in feet, how far apart should each cone be placed?
NCCER Power Line Worker – Aerial Lift Safety / OSHA 10
8. Before setting an outrigger pad near a curb on a city street, a lineworker should FIRST: