BUS-CONS57-07 · Lesson 6 · 14 clock hours · practice

RFI and Submittal Management in Procore

Objective. Students create, route, respond to, and close out both an RFI and a submittal in Procore, following a realistic review schedule and documenting the complete communication record.

⚠ Pending professional review

This lesson, its worked examples and its practice questions has not yet been verified by a credentialed professional in the field or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.

VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.

Why RFIs and Submittals Are the Backbone of Project Communication

Every construction project generates hundreds of decisions. When the drawings conflict, when a specification is unclear, or when a subcontractor needs design-team approval before ordering materials, two formal tools control that communication: the Request for Information (RFI) and the submittal. Managing both poorly is one of the most common causes of project delays, disputes, and cost overruns. Managing both well—with a full audit trail—is a core competency for any construction manager and is directly tested in the CMAA CMIT exam.

Procore centralizes both tools so that every party (owner, architect, general contractor, subcontractors) works from the same record. Nothing lives in someone's email inbox alone.

What Is an RFI?

An RFI is a formal written question sent from the contractor to the design team requesting clarification or direction. Common triggers include drawing conflicts discovered during coordination, specification ambiguities, field conditions that differ from what the drawings show, and substitution requests.

A well-drafted RFI contains:

In Procore, you create an RFI under the RFI module, assign it to the design manager or architect, set the due date, and save it. Procore timestamps the creation, sends automatic email notifications, and locks the original question so neither party can alter it later. That immutability is its legal value.

When the architect responds, you log the response directly in the RFI record—attaching any revised sketch or written direction—and then formally close the RFI. Closing does not mean deleting: the full thread stays in the system permanently as part of the project record.

What Is a Submittal?

A submittal is a document, sample, or product data package that a subcontractor or supplier sends to the contractor, who reviews it and forwards it to the design team for approval before the corresponding work or material is procured or installed. Common submittal types include shop drawings, product data sheets, mix designs, material samples, and manufacturer's certificates.

The specification divides submittals by CSI section. Your submittal log should mirror the specification index so nothing is missed. For each item you track:

In Procore's Submittals module you build this log once, assign reviewers at each step, and the system routes the package automatically when you advance the workflow. Reviewers receive email prompts; late items appear in dashboards with red flags.

Routing and Review Periods

The review period is not a suggestion—it is usually stated in Division 01 of the specifications. Never shrink a contractual review period without written agreement from the architect; doing so can transfer schedule risk to the contractor. Work backward from the required-on-site date: subtract installation lead time, shipping, fabrication, design-team review, your own review, and the sub's preparation time. If that chain puts the required submission in the past, you have a schedule problem that must be escalated immediately—not quietly ignored.

Status Reporting and Owner Communication

Open RFIs and unapproved submittals are risk. Owners and lenders want to see them quantified and managed. Procore's built-in reports let you filter RFIs by status (open, closed, overdue) and submittals by ball-in-court (contractor, design team, sub). Export the report as a PDF, then distill it into a one-page owner summary that answers three questions: What is open? Who holds the ball? What is the impact if it is not resolved by a specific date?

This proactive communication posture is a tested CMAA CMIT competency. An owner who learns about a problem from your report—before it causes a delay—trusts the project team. An owner who learns about it from a delay notice does not.

Safety Considerations in the RFI and Submittal Workflow

RFIs and submittals are paperwork tools, but their content directly affects field safety. When an RFI describes a coordination conflict in a confined space, an elevated work area, or around energized systems, flag the safety implication in the RFI body so the design team understands urgency. When reviewing submittals for equipment or systems, verify that the product data includes Safety Data Sheets (SDS) where required and that installation instructions match OSHA requirements for the work type (fall protection, lockout/tagout procedures for electrical equipment, etc.). Never approve a submittal that omits required safety documentation just to keep the log moving.

Key terms8

Request for Information (RFI)A formal written document used by the contractor to request clarification or direction from the design team, creating a timestamped, immutable record of the question and the answer received.
SubmittalA document, shop drawing, product data sheet, or sample that a subcontractor or supplier submits for review and approval by the contractor and design team before procurement or installation.
Submittal LogA master list of all required submittals on a project, organized by specification section, tracking responsible parties, submission dates, review periods, and approval status.
Ball-in-CourtThe party currently responsible for the next action on an RFI or submittal; Procore tracks this automatically and uses it in status reports to show who is holding up a decision.
Review PeriodThe contractually defined number of calendar days the design team is allowed to review and respond to a submittal; typically found in Division 01 of the project specifications.
Audit TrailThe complete, time-stamped history of every action taken on an RFI or submittal—who created it, who received it, who responded, and when—which serves as the official project record in disputes.
Required-On-Site DateThe date a material or piece of equipment must arrive at the jobsite to support the construction schedule; used as the anchor point when working backward to set submittal deadlines.
Specification Index (Division 01 / CSI)The table of contents of the project specifications organized by CSI MasterFormat sections; used to build the submittal log so that every required submittal is identified and tracked.
In class: RFI lifecycle exercise: using a scenario drawn from the sample project, students draft an RFI describing a coordination conflict (tied to the Bluebeam markup exercise), assign it to the design team with a due date, log a mock response from the architect, and formally close the RFI—capturing the full audit trail. · Submittal log setup and routing: students build a submittal log for five items (concrete mix design, structural steel shop drawings, window submittals, roofing system, and MEP equipment data) based on the project specification index provided, assign reviewers, and set required-on-site dates working backward from the schedule. · Status reporting drill: students run Procore's RFI and submittal reports, export them as PDFs, and prepare a one-page owner-report summary identifying any open items past due—connecting to the CMAA CMIT competency of proactive communication management.
Materials: Procore Training Sandbox, scenario packet (coordination conflict description and specification index), Procore RFI and Submittal help documentation, owner-report summary template
Check: Instructor evaluates RFI and submittal log against a checklist: correct fields completed, realistic dates, proper routing, and closed RFI with response attached; students must pass 9 of 11 checklist items.

Practice check8

Answer each question, then check it. Nothing is recorded; this is your own practice.

Project Communication and Documentation
1. When creating an RFI in Procore, which field most directly protects the project schedule?
Schedule and Procurement Management
2. A roofing submittal must arrive on site in 12 weeks. The fabricator needs 3 weeks after approval to manufacture and ship. The design team's contractual review period is 2 weeks. Your internal review takes 1 week. The subcontractor needs 1 week to prepare the package. How many weeks from today must the subcontractor deliver the package to you?
Project Communication and Documentation
3. Which Procore feature ensures that the original text of an RFI question cannot be altered after it is saved?
Safety and Compliance
4. A submittal for a rooftop HVAC unit arrives in Procore without the manufacturer's installation instructions or lockout/tagout procedure documentation. The correct action is to:
Project Communication and Documentation
5. The term 'ball-in-court' in Procore's submittal workflow refers to:
CMAA CMIT Core Competencies
6. When preparing a one-page owner-report summary from Procore's RFI and submittal reports, the CMAA CMIT competency being demonstrated is:
Schedule and Procurement Management
7. A student's submittal log shows the design team's review period for structural steel shop drawings is 14 calendar days, but the student schedules only 7 days. What is the most likely consequence?
Project Communication and Documentation
8. To formally close an RFI in Procore after receiving the architect's response, which action must be completed?