BUS-CONS57-07 · Lesson 2 · 12 clock hours · lab

Procore Project Setup and Directory Management

Objective. Students configure a complete Procore project shell—including company directory, user permissions, project stages, and custom folder structure—from a provided project brief.

⚠ Pending professional review

This lesson, its worked examples and its practice questions has not yet been verified by a credentialed professional in the field or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.

VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.

Why Project Setup Is the Foundation of Every Procore Project

Procore is a cloud-based construction management platform used on commercial, civil, and institutional projects across the United States. Before a single RFI is logged or a drawing is issued, someone must configure the project environment correctly. A poorly set up project creates permission gaps, misfiled documents, and audit failures—all of which cost time and money. As a construction manager or estimator, you will either build this shell yourself or be responsible for verifying that it was built correctly.

The Project Shell: What It Contains

A Procore project shell is the complete configuration that lives behind every active project. It includes:

Getting these elements right at the start prevents rework and protects the integrity of the project record, which may become a legal document during a dispute.

Configuring the Company and User Directory

In Procore, the Directory tool holds two layers: companies and people. You first add each firm, then add individual users under that firm. Every person on a Procore project must have a unique email address; Procore's Registry links credentials and activity to that identity.

When you add a user, you assign a permission template or configure permissions tool by tool. Procore uses four access levels for most tools: None, Read Only, Standard, and Admin. Choosing the wrong level is a security and liability risk. For example:

Documenting your rationale in a permission matrix is standard practice and is often required by owner contracts. It creates an auditable record that proves access was intentional and appropriate.

Building a WBS-Aligned Folder Structure

The Work Breakdown Structure (WBS) is a hierarchical decomposition of the total project scope into manageable components. When your Procore folder structure mirrors your WBS, team members can find documents quickly, and automated reports pull from the right locations.

A typical commercial office building folder structure might look like:

```

01 - General Requirements

02 - Site Work

03 - Concrete

04 - Masonry

05 - Structural Steel

06 - Wood & Plastics

07 - Thermal & Moisture Protection

08 - Openings

09 - Finishes

10 - Specialties

...

Admin / Contracts

Admin / Correspondence

Admin / Submittals

Admin / RFIs

Admin / Meeting Minutes

```

Division numbers above follow the MasterFormat numbering system, a widely used standard for organizing construction documents. Using a recognized standard means any experienced trade partner can navigate your folders without training.

Data Accuracy and Quality Control

Inaccurate metadata—wrong contract value, wrong start date, missing square footage—corrupts cost-per-square-foot benchmarks and report filters. Always verify entries against the signed contract or owner-provided project brief before saving.

The peer audit process mirrors real Quality Assurance practices used on major projects. A second set of eyes catches errors the original configurator missed. When you audit a partner's sandbox project, use the checklist systematically: do not skip items because something looks correct at a glance.

Safety Considerations in a Digital Platform Context

While configuring Procore does not involve physical hazards, the platform manages safety records including Incidents, Observations, and Inspections. Incorrect permission settings can allow unauthorized users to edit or delete safety records—a serious compliance risk under OSHA recordkeeping requirements. Always ensure that safety tool permissions are set so records can be created and viewed by field supervisors but can only be edited or deleted by authorized safety personnel or the CM. Never grant blanket Admin access to all tools to save setup time.

Connecting to Your Credentials

NCCER Project Management competencies include document control and project information management—skills you practice every time you configure a project directory. CMAA's CM-in-Training body of knowledge covers project information management and stakeholder communication, both of which depend on a correctly structured Procore environment. OSHA 30 trains you to recognize recordkeeping obligations; proper Procore permission settings support that compliance.

Key terms8

Project ShellThe complete initial configuration of a Procore project, including metadata, directory, permissions, and folder structure, set up before active project use begins.
Directory ToolThe Procore module that stores all companies and individual users associated with a project, along with their contact information and permission assignments.
Permission TemplateA saved set of tool-level access levels (None, Read Only, Standard, Admin) in Procore that can be applied to multiple users who share the same role.
Work Breakdown Structure (WBS)A hierarchical decomposition of a project's total scope into smaller, manageable components; used to organize cost codes, schedules, and document folders.
MasterFormatA standard published by the Construction Specifications Institute (CSI) that organizes construction documents and specifications into numbered divisions, widely used to structure project folders.
Permission MatrixA document that maps each project role to specific tool access levels and records the business rationale for each access decision, creating an auditable record.
Procore Training SandboxA controlled Procore environment provided for practice and learning that mirrors production functionality without affecting live project data.
Project MetadataDescriptive data entered when creating a Procore project—such as project type, address, square footage, contract value, and key dates—that drives reports and integrations.
In class: Step-by-step lab: using a fictional commercial project brief, students create a new project in the Procore training sandbox, enter all required metadata (project type, address, square footage, value, dates), and configure the WBS-aligned folder structure for drawings and documents. · Permission-role exercise: students assign at least five user roles (owner, CM, GC superintendent, structural sub, architect) with appropriate tool permissions and document the rationale for each restriction in a one-page permission matrix. · Peer audit: partners swap sandbox projects and use a provided checklist to verify correct setup, then write one corrective action note for any missing item, mirroring real QA practices.
Materials: Procore Training Sandbox, project brief handout (fictional commercial office building), Procore Help Center documentation, permission matrix template, peer audit checklist
Check: Instructor reviews completed sandbox project against a 15-point setup rubric; students must score 12 of 15 points, with zero deficiencies in permission settings.

Practice check8

Answer each question, then check it. Nothing is recorded; this is your own practice.

NCCER Project Management – Document Control and Project Information Management
1. When configuring a Procore project, what is the correct sequence for adding a new subcontractor user to the directory?
CMAA CMIT – Project Information Management
2. A structural subcontractor needs to upload shop drawings and respond to submittal review comments in Procore. Which permission level on the Submittals tool is most appropriate?
NCCER Project Management – Document Control
3. Which numbering system is most commonly used to organize a Procore document folder structure on commercial construction projects?
CMAA CMIT – Stakeholder Management and Project Information
4. During a peer audit of a sandbox project, a student finds that the GC Superintendent has Admin access to the Budget tool. What is the most appropriate corrective action note to write?
NCCER Project Management – Project Planning and Control
5. Why is accurate project metadata—such as contract value, square footage, and start date—critical when setting up a Procore project shell?
OSHA 30 – Recordkeeping and Reporting
6. From an OSHA recordkeeping compliance standpoint, which permission setting represents the greatest risk on the Procore Incidents tool?
CMAA CMIT – Project Information Management
7. A permission matrix in Procore project setup serves which primary purpose?
NCCER Project Management – Quality Management
8. On the 15-point setup rubric used to assess student sandbox projects, the passing score is 12 points with zero deficiencies in permission settings. A student scores 13 points but has one permission error allowing an architect Read Only access to the Budget tool. What is the correct outcome?