BUS-CONS57-03 · Lesson 6 · 12 clock hours · theory
Pricing Materials and Equipment
Objective. Students will determine material unit prices using at least two sources (published cost data and a vendor quote) and calculate equipment cost for a task using ownership/operating cost or rental rate methods.
⚠ Pending professional review
This lesson, its worked examples and its practice questions has not yet been verified by a credentialed professional in the field or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.
VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.
Why Pricing Accuracy Matters
A quantity takeoff tells you how much of something you need. Pricing tells you what it costs. Errors at this stage ripple through the entire estimate: an understated material price can erase your profit margin before a single shovel hits the ground. Accurate pricing requires at least two independent sources—a published cost database and a current vendor or rental quote—so you can cross-check data and apply local market conditions.
Published Cost Data: RSMeans
RSMeans (published by Gordian) is the most widely used published cost reference in US commercial construction. It lists material, labor, and equipment costs organized by CSI MasterFormat division. Each line item shows:
- Material unit cost – the bare cost of the material per unit (e.g., per LF, SF, CY, EA)
- Labor unit cost – the cost to install one unit, based on standard crew productivity
- Equipment unit cost – the cost of equipment allocated to one unit of production
- Total bare cost – the sum of those three components
- O&P (overhead and profit) – typically shown as a percentage added to arrive at a contractor's price
RSMeans data is national average pricing. It includes a City Cost Index (CCI) that lets you adjust national figures to a specific metro area. To apply it, multiply the national bare cost by the local CCI factor (expressed as a decimal, e.g., 0.94 for a lower-cost market, 1.18 for a high-cost city). Always note the RSMeans edition year, because material prices change annually.
Vendor Quotes
A vendor or supplier quote is a written price offer from a material supplier for a defined quantity and specification. Quotes reflect actual current local market prices, including freight, fuel surcharges, and regional shortages or surpluses. Key rules for working with vendor quotes:
1. Match the specification exactly. A quote for 8-inch standard concrete masonry units (CMU) is not interchangeable with a quote for 8-inch lightweight CMU.
2. Record the unit. Lumber prices may be quoted per board foot, per linear foot, or per piece. Concrete block is typically quoted per unit. Confusion about units is a leading cause of pricing errors.
3. Note the validity period. Quotes often expire in 30 days or less. Flag the date on your pricing worksheet.
4. Confirm delivery terms. A price that does not include delivery ("ex-works" or "pickup only") must have freight added before it enters your estimate.
When your vendor quote and RSMeans diverge by more than roughly 10–15%, investigate why. Local market conditions, specification differences, or a minimum-order premium are common reasons.
Reconciling Two Sources
Document both prices side by side. If you use the vendor quote as your primary price (because it is current and local), show the RSMeans figure as a check. If the quote seems unusually low, do not use it without confirming the supplier understands the full specification—a price that is too good is often wrong.
Equipment Cost: Two Methods
Rental Rate Method
The simplest approach: obtain a daily, weekly, or monthly rental rate from a local rental company or a published rental rate guide. Add operating costs—fuel, lubricants, operator labor (if not already in crew labor), and minor consumables. Divide or multiply to match the duration needed for the task.
Daily equipment cost = Rental rate + Fuel/day + Consumables/day
This method works well for short-duration tasks and equipment you would not own.
Ownership-Plus-Operating (O+O) Cost Method
When a contractor owns equipment, the cost per unit of time includes:
- Ownership costs: depreciation, interest on investment, insurance, taxes, and storage. These accrue whether the machine works or sits idle.
- Operating costs: fuel, lubricants, tires or undercarriage wear, filters, and routine maintenance. These accrue only when the machine runs.
Simplified formula often used in estimating:
Hourly ownership cost ≈ (Purchase price − Salvage value) ÷ Useful life in hours
Total hourly equipment cost = Hourly ownership cost + Hourly operating cost
For estimating purposes, many published guides (including RSMeans equipment cost tables) provide an all-in hourly or daily rate for common machines that blends both components. Use those published rates when you do not have the contractor's actual ownership data.
Extending Quantities to Cost
Once you have a unit price from your chosen source, extension is straightforward:
Extended cost = Quantity × Unit price
Carry your units through every step. If your takeoff shows 48 CY of concrete and your price is per CY, the extension is direct. If your takeoff is in SF of formwork and your price is per SF, again direct. Mismatched units are the most common arithmetic error in cost summaries.
Build a pricing worksheet with columns for: item description, CSI code, quantity, unit, source (RSMeans or vendor), unit price, and extended cost. Subtotal by CSI division before rolling up to the project total.
Safety Considerations
Pricing work often involves site visits to verify quantities or meet with suppliers. On any active construction site, wear the minimum required PPE: hard hat, safety-toed boots, and high-visibility vest. Follow all site-specific safety orientation requirements. If you are near equipment operating areas, maintain the distances posted on barricades and never stand in an equipment swing radius. Estimators who visit sites with excavation must be aware of OSHA excavation hazard rules—stay back from open trench edges and observe any shoring or sloping in place. Never enter a confined space for any estimating purpose without proper confined-space entry procedures in place.
Key terms8
RSMeansA widely used published construction cost database organized by CSI division that provides national average material, labor, and equipment unit costs, adjustable to local markets using a City Cost Index.
City Cost Index (CCI)A location adjustment factor published by RSMeans that converts national average costs to local market costs by multiplying the national figure by the index value for a specific city or region.
Vendor QuoteA written price offer from a material supplier for a defined quantity and specification, reflecting current local market prices including any applicable freight or surcharges.
Unit PriceThe cost of one unit of a material or piece of equipment time (e.g., cost per CY, per SF, per hour), used as the multiplier in cost extension calculations.
ExtensionThe arithmetic product of quantity multiplied by unit price, yielding the total cost for a single line item in an estimate.
Rental Rate MethodAn equipment costing approach that uses the quoted daily, weekly, or monthly rental rate from a supplier, plus fuel and consumables, to determine the total equipment cost for a task.
Ownership-Plus-Operating (O+O) CostAn equipment costing method that separates ownership costs (depreciation, insurance, interest) from operating costs (fuel, maintenance) to calculate a total hourly or daily cost for contractor-owned equipment.
Bare CostThe direct cost of materials, labor, and equipment before adding contractor overhead and profit, as shown in RSMeans line items.
Worked examples4
1. A takeoff shows 120 CY of ready-mix concrete (4,000 psi). RSMeans lists the national bare material cost at $142.00/CY, and the local CCI for materials is 0.96. A vendor quote comes in at $138.50/CY delivered. Which price should you use, and what is the extended material cost for the concrete using the lower (vendor) price?
- Step 1 – Adjust RSMeans for location: $142.00 × 0.96 = $136.32/CY (RSMeans local adjusted).
- Step 2 – Compare to vendor quote: RSMeans adjusted = $136.32/CY; vendor quote = $138.50/CY. The difference is $2.18/CY (about 1.6%), which is within a reasonable range. The vendor quote is current and local, so use it as the primary price and note RSMeans as the check source.
- Step 3 – Extend the cost: 120 CY × $138.50/CY = $16,620.00.
- Step 4 – Document the pricing worksheet entry: Item = Ready-mix concrete 4,000 psi; Quantity = 120 CY; Source = Vendor quote (date); Unit price = $138.50; Extended = $16,620.00; RSMeans check = $136.32/CY.
Answer: Extended material cost = $16,620.00, using the vendor quote of $138.50/CY as the primary source.
2. A small excavator is needed for 3 days to dig footings. The local rental company quotes $475/day. Estimated fuel consumption is 8 gallons/day at $4.10/gallon. There are no other operating consumables. What is the total equipment cost for this task?
- Step 1 – Calculate daily fuel cost: 8 gal × $4.10 = $32.80/day.
- Step 2 – Calculate total daily cost: $475.00 (rental) + $32.80 (fuel) = $507.80/day.
- Step 3 – Multiply by task duration: $507.80/day × 3 days = $1,523.40.
- Step 4 – Document: Equipment = Small excavator; Method = Rental rate; Rate = $475/day + $32.80 fuel/day; Duration = 3 days; Total = $1,523.40.
Answer: Total equipment cost for the excavator = $1,523.40.
3. Using the simplified O+O method, a contractor owns a concrete pump purchased for $180,000 with an estimated salvage value of $18,000 after 10,000 hours of useful life. Operating costs (fuel, oil, wear parts) average $28.00/hour. The pump will be used for 6 hours on a job. What is the total equipment cost to charge to this job?
- Step 1 – Calculate hourly ownership cost: ($180,000 − $18,000) ÷ 10,000 hours = $162,000 ÷ 10,000 = $16.20/hour.
- Step 2 – Calculate total hourly cost: $16.20 (ownership) + $28.00 (operating) = $44.20/hour.
- Step 3 – Multiply by hours on task: $44.20/hour × 6 hours = $265.20.
- Step 4 – Document: Equipment = Concrete pump; Method = O+O; Ownership = $16.20/hr; Operating = $28.00/hr; Total hourly = $44.20; Hours = 6; Job cost = $265.20.
Answer: Total equipment cost charged to this job = $265.20.
4. A Division 03 scope includes 850 SF of 4-inch concrete slab on grade. RSMeans lists the bare material cost at $1.85/SF (adjusted locally). A vendor quote for the same mix and thickness comes in at $1.92/SF. You decide to use the RSMeans local price as the more conservative check. What is the extended material cost, and by how much does it differ from the vendor-quote-based extension?
- Step 1 – Extend using RSMeans local price: 850 SF × $1.85/SF = $1,572.50.
- Step 2 – Extend using vendor quote: 850 SF × $1.92/SF = $1,632.00.
- Step 3 – Calculate the difference: $1,632.00 − $1,572.50 = $59.50.
- Step 4 – Percentage difference: $59.50 ÷ $1,572.50 × 100 ≈ 3.8%. This is within a normal range; note both figures and the reason for choosing RSMeans (conservative pricing or scope-bid decision).
Answer: RSMeans-based extension = $1,572.50; vendor-quote-based extension = $1,632.00; difference = $59.50 (≈ 3.8%).
The math in this lesson1
Learners apply a 0.96 location factor, compare quotes by percent difference and extend material cost.
7.RP.3
In class: Students obtain a mock vendor quote for lumber and concrete block (instructor-prepared quote sheet simulating a supplier response) and compare prices to RSMeans material costs; they document price source, unit, and any local adjustment. · Instructor demonstrates equipment cost calculation using both a daily rental rate and a simplified ownership-plus-operating cost approach for a small excavator; students replicate the calculation for a concrete pump. · Students build a material and equipment cost summary for the Division 03 concrete scope from Lesson 3 takeoff, combining their quantities with the pricing sources discussed.
Materials: RSMeans cost database, mock vendor quote sheets, equipment rental rate sheet (instructor-prepared), Excel pricing template, calculators
Check: Material and equipment cost summary reviewed by instructor; pass = correct unit prices sourced from at least two references, quantities correctly extended, and totals within 5% of key.