BLD-SOLA09-04 · Lesson 2 · 12 clock hours · demo

Roof Assessment, Structural Evaluation, and Load Basics

Objective. Students will conduct a roof condition inspection and locate rafter positions on a mock roof section, recording all findings on a site assessment form that meets a defined completeness standard.

⚠ Pending professional review

This lesson, its worked examples and its practice questions has not yet been verified by a licensed professional engineer or master tradesperson or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.

VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.

Why Roof Assessment Comes First

Before a single bracket is bolted down, you must know whether the roof can safely carry the added weight and forces of a PV array. A rooftop solar installation imposes new loads on a structure that was designed years or decades ago for other purposes. Skipping a thorough roof assessment is one of the most common causes of failed inspections, callbacks, and — in worst cases — structural damage. This lesson teaches you to gather the information that drives every attachment decision.

Personal Protective Equipment and Jobsite Safety

Even on a mock roof section at floor level, build the habit now. On an actual job, roof work requires a hard hat, non-slip footwear, and gloves as a minimum. Working at height adds fall-protection requirements (harness, anchor, lanyard) and compliance with OSHA standards for residential roofing. Never walk on a roof section without confirming it can hold your weight. Identify all skylights and fragile surfaces before stepping anywhere. Keep tools tethered or in a bag — a dropped tool from a roof is a falling-object hazard for anyone below.

Locating Rafters

Rafters (or roof trusses) are the structural members that carry the roof deck and everything placed on it. Lag bolts for racking must land in rafters, not just in the sheathing. Sheathing alone — typically OSB or plywood — cannot carry the tensile pullout load that wind uplift creates.

Use a stud finder set to the deepest scan mode and run it along the underside of the sheathing (from inside the attic if accessible) or across the top surface. Mark each hit with chalk or tape. Confirm with a probe or a small-diameter finish nail: the nail should meet solid resistance at the rafter center. Measure and record the on-center (OC) spacing — most residential roofs use 16-inch or 24-inch OC framing, but older or custom homes can vary. Measure at least three consecutive spaces and average them; do not assume uniform spacing.

Assessing Sheathing Condition

Once rafters are located, examine the sheathing between them. Good sheathing feels firm and does not deflect noticeably underfoot. Soft spots, dark staining, crumbling edges, or visible rot indicate moisture damage. Damaged sheathing must be repaired before any racking is attached; a lag bolt in rotted OSB will not hold design loads. Probe the sheathing at suspect areas and record your findings on the site assessment form. Note the estimated thickness (typically ½ inch to ¾ inch for residential OSB or plywood).

Identifying Roofing Material

The roofing material determines which attachment hardware and flashing method you use. The most common residential types are:

Record the material, its apparent age and condition, and any visible cracking, curling, or granule loss. An aging roof nearing end of life should be flagged for the customer — it is far better to reroof before the array goes up than to remove and reinstall panels later.

Measuring Roof Pitch

Pitch describes slope as rise over run — how many inches the roof rises for every 12 inches of horizontal distance. A 6:12 pitch rises 6 inches per foot. Use a pitch gauge (a tool with a swinging indicator) placed flat against the roof surface for a direct reading. Pitch affects drainage, worker safety, and snow-load calculations. Record pitch as a ratio (e.g., 6:12).

Understanding Structural Loads

Four load types matter for PV attachment:

Manufacturers publish load tables that combine these factors. Given a roof pitch, design wind speed, and rafter span, the table tells you the maximum allowed spacing between attachment points (lag bolts into rafters). You do not need to perform structural engineering calculations yourself — that is the engineer of record's job — but you must be able to read the table correctly and apply its requirements in the field.

Using the Manufacturer's Load Table

Load tables are organized by variables such as wind speed (mph), roof pitch range, and rafter or purlin span. Find the row matching your wind speed and pitch, then read across to your rafter span column. The intersection gives you maximum attachment spacing in inches or feet. If your calculated spacing exceeds the table maximum, you must add more attachment points. Always use the most conservative (smallest) value when your conditions fall between table entries. Record the table version, page number, and all inputs on the site assessment form so the Authority Having Jurisdiction (AHJ) can verify your work.

Completing the Site Assessment Form

A complete form is a legal and professional document. Every field must be filled in: rafter OC spacing (measured, not assumed), pitch, sheathing thickness and condition, roofing material and age estimate, and the load table attachment spacing calculation with inputs shown. Incomplete forms delay permits and inspections. Get it right the first time.

Key terms10

RafterA sloped structural framing member that supports the roof deck and transfers loads to the wall top plate and ridge; the target for lag-bolt attachments in most residential PV installations.
On-center (OC) spacingThe distance measured from the center of one framing member to the center of the next; standard residential rafters are commonly 16 or 24 inches OC.
Dead loadThe permanent, constant weight of building materials and installed equipment — including the PV modules, racking, and wiring — that the structure must support continuously.
Live loadA temporary, variable load applied to a structure, such as the weight of workers and tools during installation or maintenance activities.
Wind upliftThe upward (negative) pressure created by wind passing over a roof surface that can pull racking attachments out of the structure; often the governing load for attachment design.
Snow loadThe force exerted on a roof by accumulated snow; varies by geographic location, roof pitch, and local building codes or standard references.
Roof pitchThe slope of a roof expressed as rise over run — the number of inches of vertical rise for every 12 inches of horizontal distance (e.g., 6:12).
SheathingThe structural panel material (typically OSB or plywood) fastened to the top of the rafters to form the roof deck; it supports the roofing material but cannot alone carry lag-bolt pullout loads.
Attachment spacingThe maximum allowable distance between lag-bolt anchor points into rafters, as determined by the racking manufacturer's load table based on wind speed, pitch, and rafter span.
Authority Having Jurisdiction (AHJ)The governmental body — typically a local building department — responsible for reviewing plans, issuing permits, and conducting inspections for solar installations.

Worked examples4

1. You measure three consecutive rafter spaces on a mock roof section and record 16.25 in, 15.75 in, and 16.00 in. What is the average on-center rafter spacing to report on the site assessment form?
  1. Add the three measurements: 16.25 + 15.75 + 16.00 = 48.00 inches.
  2. Divide by the number of spaces measured: 48.00 ÷ 3 = 16.00 inches.
  3. Report 16.00 inches OC on the form.
Answer: 16.00 inches on-center.
2. A manufacturer's load table shows that for a design wind speed of 110 mph, a roof pitch of 6:12, and a rafter span of 24 inches OC, the maximum attachment spacing is 48 inches. The array row is 16 feet long. How many attachment points (lag bolts into rafters) are required for that row at minimum?
  1. Convert the row length to inches: 16 ft × 12 in/ft = 192 inches.
  2. Divide by maximum attachment spacing: 192 ÷ 48 = 4.00 spaces.
  3. Number of attachment points = number of spaces + 1 = 4 + 1 = 5 points.
  4. Confirm: 5 points create 4 spans of 48 inches each, covering 192 inches exactly — acceptable.
Answer: 5 attachment points (lag bolts) minimum for that row.
3. You are reading a pitch gauge held flat against a roof surface. The indicator reads 4:12. A co-worker suggests rounding up to 6:12 on the site form to get a more favorable (wider) attachment spacing from the load table. Why is this incorrect, and what should you record?
  1. Record the actual measured pitch: 4:12. The site assessment form must reflect real, measured conditions — not estimated or adjusted values.
  2. Using a pitch higher than actual to get a more permissive table value is unsafe and potentially fraudulent; it can result in under-attached arrays that fail under wind or snow loads.
  3. If the actual pitch falls in a less favorable table zone, you must use that zone's attachment spacing, even if it requires more attachment points.
Answer: Record 4:12 as measured. Use the load table row corresponding to 4:12; do not adjust upward to get a wider spacing.
4. A manufacturer's load table shows a maximum attachment spacing of 64 inches for a given set of conditions. The rafters are spaced 24 inches OC. The installer plans to attach at every third rafter (spacing = 72 inches). Is this acceptable?
  1. The proposed spacing is 72 inches (every third rafter at 24 in OC: 24 × 3 = 72 in).
  2. The table maximum for these conditions is 64 inches.
  3. 72 inches exceeds 64 inches, so the proposed layout does NOT meet the table requirement.
  4. The installer must attach at every other rafter (24 × 2 = 48 inches), which is within the 64-inch limit.
Answer: Not acceptable. Attaching at every third rafter gives 72-inch spacing, which exceeds the 64-inch table maximum. Attach at every second rafter for 48-inch spacing.

The math in this lesson2

Learners convert maximum attachment spacing into a whole number of rafter bays.
6.RP.3S-ID.2
Brush up in the math halls at newSchoolWorks.com:
In class: Instructor-led demonstration on a mock roof section: how to use a stud finder and probe to locate rafters, measure rafter spacing, assess sheathing condition, and identify roofing material type; students shadow and then repeat the steps independently. · Guided introduction to dead load, live load, wind uplift, and snow load concepts using the manufacturer's load table; students calculate required attachment spacing for a given roof pitch, wind speed, and rafter span using the table lookup method. · Pairs complete a roof assessment form on the mock section, recording rafter spacing, pitch (using a pitch gauge), sheathing thickness estimate, and roofing material; instructor reviews each form for accuracy and completeness.
Materials: Mock roof section with rafters and OSB sheathing, stud finder, probe, tape measure, pitch gauge, load tables from manufacturer manual, site assessment forms, PPE (hard hat, non-slip footwear, gloves)
Check: Completed site assessment form reviewed by instructor; all required fields populated, rafter locations within ±1 inch of actual, load table calculation verified correct. Incomplete or inaccurate forms require one re-attempt before progressing.

Practice check8

Answer each question, then check it. Nothing is recorded; this is your own practice.

PV System Design and Installation
1. When using a stud finder to locate rafters for lag-bolt attachment, what is the correct follow-up step before marking a rafter location as confirmed?
Safety and Environment
2. A rooftop inspection reveals soft spots, dark staining, and crumbling edges on the OSB sheathing between rafters. What is the correct course of action before installing PV racking?
PV System Design and Installation
3. Which load type represents the upward-pulling force that wind exerts on a PV array and is most commonly the governing design load for rooftop attachment spacing?
PV System Design and Installation
4. A pitch gauge placed flat on a roof surface reads 5:12. What does this measurement mean?
PV System Design and Installation
5. You are reading a manufacturer's load table. For a 110 mph design wind speed, 5:12 pitch, and 16-inch OC rafter spacing, the table shows a maximum attachment spacing of 72 inches. The array has a continuous run of 10 feet (120 inches). What is the minimum number of attachment points required for this run?
PV System Design and Installation
6. Why must lag bolts for rooftop PV racking be fastened into rafters rather than into the sheathing alone?
PV System Design and Installation
7. Which roofing material type typically allows PV racking clamps to be attached without making any penetrations through the roof membrane?
Safety and Environment
8. An installer notices the existing asphalt shingle roof is showing significant granule loss and curling edges. What is the most appropriate action to take and document on the site assessment form?