Objective. Students will apply OSHA electrical safety requirements and lockout/tagout (LOTO) procedures to PV-specific de-energization tasks, and will demonstrate adult CPR and first-aid response to electric shock and heat emergencies.
⚠ Pending professional review
This lesson, its worked examples and its practice questions has not yet been verified by a licensed professional engineer or master tradesperson or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.
VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.
Why Electrical Safety Is Non-Negotiable in PV Work
PV systems present hazards that differ from standard construction wiring in one critical way: solar panels generate voltage whenever light strikes them. Even after you open an AC breaker, the DC side of the array remains live during daylight. A fully charged residential string can exceed 300–600 V DC, and current as low as 100 milliamps can cause ventricular fibrillation. Respecting this dual-source hazard—grid AC and solar DC—is the foundation of every electrical safety practice you will use on the job.
OSHA's construction electrical safety rules are found in 29 CFR Part 1926, Subpart K. The general industry lockout/tagout standard, 29 CFR 1910.147, provides the engineering principles that the solar trade applies in the field. Know both references; NABCEP exam content draws from both.
Personal Protective Equipment (PPE) for Electrical Work
Before you touch any conductor, select PPE rated for the hazard:
- Insulated gloves: Rated for the voltage class you are working near. Check for cuts, punctures, and expiration before each use. Never use gloves with visible damage.
- Safety glasses or face shield: Arc flash and flying debris are real risks at disconnects.
- Arc-rated (AR) clothing: Required when there is an arc-flash hazard. Cotton and polyester blends can melt to skin; wear AR-rated shirts and pants or a flash suit when the task demands it.
- Non-conductive hard hat: Required on most construction sites by default.
- Insulated tools: All hand tools used on or near energized parts must be rated and labeled for the voltage involved.
- Voltage alert pen: Use it as a quick first check, but always confirm with a calibrated digital multimeter (DMM).
Inspect all PPE at the start of every shift. Damaged PPE goes out of service immediately.
Lockout/Tagout (LOTO) Principles for PV Systems
Lockout/tagout is the procedure that protects workers from the unexpected energization or release of stored energy while they service equipment. On a PV system you must address two independent energy sources simultaneously.
The six-step LOTO sequence:
1. Notify affected employees that equipment is being taken out of service.
2. Shut down the equipment using its normal stopping procedure (e.g., shut down the inverter via its control panel).
3. Isolate all energy sources: open the AC utility disconnect, open the DC array disconnect, and open any sub-array combiners.
4. Lockout/tagout each isolation point: apply your personal lock and a danger tag to every disconnect you opened. Each worker applies their own lock — never share a lock.
5. Release stored energy: wait for capacitors in the inverter to discharge (follow the manufacturer's wait time, often 5 minutes or more), and be aware that DC conductors between the array and the open DC disconnect remain energized by sunlight.
6. Verify zero energy state: use a DMM to measure voltage at every test point before touching any conductor. Measure AC line-to-line, AC line-to-ground, and DC positive-to-negative. A reading of zero on a calibrated meter confirms the circuit is de-energized.
Return to service: remove your lock only after all work is complete, all personnel are clear, and tools and materials are accounted for. Locks are removed in reverse order by the person who applied them.
Key PV-specific caution: The conductors between the solar array and the open DC disconnect are still energized whenever there is light. Covering or shading the panels reduces—but may not eliminate—voltage. Never assume the DC source side is safe based on the position of a switch alone.
Using a Digital Multimeter to Verify Zero Energy
A DMM is your confirmation tool after LOTO. Set the meter to the appropriate voltage range before probing:
- For AC: select AC voltage (VAC), range above the expected system voltage.
- For DC: select DC voltage (VDC), range above the expected string voltage.
- Insert the red probe in the VΩ port and the black probe in the COM port.
- Touch probes to the test points, read the display, and record your result.
- A reading at or near zero confirms de-energization at that point. Test every point listed on your LOTO form.
Never skip verification because you believe a switch was opened. Meters can fail; use a known-good meter, test the meter on a known source first, then test the circuit, then test the meter again (the "test-before-touch" habit).
First Aid for Electric Shock
Do not touch the victim if the source may still be energized. Call 911 immediately. De-energize the circuit using LOTO if you can do so safely. Once the area is confirmed safe, approach the victim.
- Check responsiveness and breathing.
- If unresponsive and not breathing normally, begin CPR and send someone for the AED.
- Electric shock can cause internal burns and cardiac arrhythmia even when the victim looks uninjured. All electric-shock victims must receive medical evaluation.
- If the victim is conscious and breathing, place them in the recovery position and monitor until EMS arrives.
First Aid for Heat Illness
Rooftop PV installation is physically demanding in direct sun. Recognize heat illness early:
- Heat exhaustion: heavy sweating, weakness, cool and moist skin, nausea. Move to shade, have the worker rest and drink cool water, apply cool wet cloths.
- Heat stroke: hot and dry or damp skin, confusion, loss of consciousness. This is a life-threatening emergency. Call 911, move the worker to a cool location, and use aggressive cooling (ice packs to neck, armpits, and groin if available) while waiting for EMS.
Prevent heat illness: schedule heavy work during cooler morning hours, encourage hydration before thirst develops, and use a buddy system so workers watch each other for early symptoms.
CPR and AED
CPR combines chest compressions and rescue breaths to maintain circulation until the heart can be restarted. For adult CPR: push hard and fast in the center of the chest, at least 2 inches deep, at a rate of 100–120 compressions per minute. Minimize interruptions. When an AED is available, power it on and follow its voice prompts exactly. AEDs are designed for untrained users; the device will tell you what to do step by step. Early defibrillation is the single most effective intervention for cardiac arrest from electric shock.
You must pass the hands-on CPR/first-aid skills check to receive your completion card. That card, along with a clean LOTO verification form, is your exit ticket for today's lab.
Key terms8
Lockout/Tagout (LOTO)A safety procedure requiring workers to isolate equipment from all energy sources, apply personal locks and warning tags to each isolation point, and verify zero energy before servicing — governed by OSHA 29 CFR 1910.147 principles.
Zero Energy StateThe confirmed condition in which all electrical, mechanical, and stored energy in a system has been isolated and dissipated so that no hazardous energy can be released; verified by instrument measurement, not assumption.
Dual-Source HazardThe PV-specific condition in which both the utility grid (AC) and the solar array (DC) can independently energize a system; both sources must be isolated before work begins.
Arc-Rated (AR) ClothingGarments tested and labeled with an arc thermal performance value (ATPV) that indicates how much incident arc energy they can withstand; required when an arc-flash hazard exists.
Digital Multimeter (DMM)A portable instrument used to measure voltage (AC and DC), current, and resistance; the primary tool for verifying zero energy state after LOTO on a PV system.
Voltage Alert Pen (Non-Contact Voltage Tester)A pen-shaped device that detects the presence of AC voltage without direct contact; used as a quick preliminary check but not as a substitute for DMM measurement to confirm zero energy.
Heat StrokeA life-threatening heat emergency characterized by a core body temperature above safe limits, altered mental status, and failure of the body's cooling system; requires immediate 911 call and aggressive cooling.
AED (Automated External Defibrillator)A portable device that analyzes heart rhythm and delivers an electric shock to restore normal rhythm in cardiac arrest; designed with voice prompts for use by trained and untrained rescuers.
Worked examples4
1. After completing LOTO on a training board, you set your DMM to DC voltage and measure a residential PV string test point. The meter reads 4.2 V DC. Is the circuit at zero energy state? What should you do?
- A reading of 4.2 V DC is not zero; it indicates some residual voltage is present at that test point.
- Do not proceed with the mock connector task. A small residual voltage could indicate that the DC disconnect is not fully open, a leakage path exists, or the meter is detecting a capacitor discharge that is not yet complete.
- Re-inspect every isolation point: confirm each DC disconnect handle is fully in the open (off) position and that your lock is securing it.
- Wait the full manufacturer-specified inverter discharge time (often 5 minutes or more), then re-measure at the same test point.
- Only when the DMM reads 0 V (or a value within the meter's stated accuracy of zero) at every required test point can you sign the LOTO verification form and proceed.
Answer: No, the circuit is not at zero energy state. Stop work, re-verify all isolation points, allow full capacitor discharge time, and re-measure before proceeding.
2. You need to set your DMM to measure the AC output voltage of a 240 V single-phase inverter before LOTO. The meter has the following AC voltage ranges: 600 V, 200 V, 20 V. Which range do you select and why?
- Identify the expected voltage: the inverter output is 240 V AC.
- Choose a range that is higher than the expected voltage to avoid over-ranging the meter and to ensure an accurate reading.
- The 200 V range is below 240 V — selecting it would cause the meter to display 'OL' (overload) and give no useful reading.
- The 20 V range is far below the voltage and would damage the meter or give no reading.
- The 600 V range is above 240 V and is the correct selection.
Answer: Select the 600 V AC range. It is the lowest range that exceeds the expected 240 V, giving the most accurate reading without over-ranging the instrument.
3. During a LOTO walkthrough, a student counts the isolation points on a simple residential training board: one AC utility disconnect, one inverter AC input breaker, and one DC array disconnect. How many personal locks must the student apply, and to which points?
- OSHA LOTO principles require that each energy isolation point be locked in the safe (open/off) position.
- Count the isolation points: (1) AC utility disconnect, (2) inverter AC input breaker, (3) DC array disconnect — a total of three isolation points.
- Each isolation point must receive its own lock (and tag). One personal lock per isolation point = three locks total.
- Verify that all three locks are applied and that no other energy sources (such as a battery storage system or a second array circuit) have been overlooked.
Answer: The student must apply three personal locks — one to each of the three isolation points: the AC utility disconnect, the inverter AC input breaker, and the DC array disconnect.
4. A co-worker collapses on a rooftop and is unresponsive. You are 10 feet away and the DC array is still live due to sunlight. What is the correct order of your first four actions?
- Step 1 — Do not rush to touch the co-worker: confirm the victim is not in contact with an energized conductor. If there is any possibility of ongoing electrical contact, do not touch the victim until the circuit is de-energized.
- Step 2 — Call or direct someone to call 911 immediately and to retrieve the AED from the job-site kit.
- Step 3 — If it is safe to do so without endangering yourself, quickly open the AC utility disconnect and the DC array disconnect to de-energize the system using LOTO (emergency LOTO if time permits), or direct a qualified person to do so.
- Step 4 — Once the area is confirmed safe, assess the victim: tap the shoulder, shout 'Are you okay?' Check for normal breathing. If unresponsive and not breathing normally, begin CPR immediately and use the AED as soon as it arrives.
Answer: Confirm safety (no ongoing electrical contact), call 911 and send for the AED, de-energize the system if safely possible, then begin CPR and use the AED.
In class: Demonstrate a complete LOTO sequence on a simulated PV training board (AC and DC disconnect switches, inverter, utility disconnect): students verbally narrate each step—notify, shut down, isolate, lockout/tagout, release stored energy, verify—while the instructor evaluates against a LOTO checklist drawn from OSHA 29 CFR 1910.147 principles as applied in the construction context. · Practice using a digital multimeter to verify absence of voltage on the training board after LOTO: students measure AC and DC test points, record readings, and sign off that the circuit is at zero energy state before proceeding with a mock connector task. · Complete a hands-on adult CPR and AED training session and basic first-aid for electric shock (do-not-touch protocol, emergency call, recovery position) and heat illness (shade, hydration, cooling) delivered by an instructor holding a current CPR/first-aid instructor credential; students must pass the skills check to earn a CPR/first-aid completion card.
Materials: PV electrical safety training board with AC and DC disconnects (deenergized training unit), personal locks and tags (one per student), digital multimeters (one per pair), test leads, voltage alert pen, AED trainer unit, CPR manikins (one per two students), first-aid kit for demonstration, OSHA 29 CFR 1910.147 reference excerpt, CPR/first-aid curriculum from an accredited provider
Check: LOTO skills check: student performs complete LOTO sequence on the training board with zero critical steps missed; instructor initials each step on the LOTO verification form. CPR/first-aid skills check: student passes the hands-on skills evaluation per the CPR provider's standard. Both checks must be passed; either may be retried once within the lesson block. Pass mark: 100% on LOTO critical steps; CPR provider pass standard for skills check.
Practice check8
Answer each question, then check it. Nothing is recorded; this is your own practice.