🚧 Under construction — VoTechWorks is being built. A free tech program — complimentary, as our commitment to get America working.
voTechWorksGrade 13 · a vocational technology learning center, by urbanicity
newSchoolWorks.com › VoTechWorks › Building & Construction › Plumbing & Pipefitting › Capstone Project: Full-System Plumbing Installation › Lesson 2
BLD-PLUM06-09 · Lesson 2 · 96 clock hours · lab

Rough-In: DWV, Water Supply, and Gas Piping Installation

Objective. Following their approved plan set, students will rough-in a complete DWV system, a potable water supply system, and a gas piping branch in the full-scale mock-up bay, achieving correct slope, support spacing, and fitting orientation at every point, verified by a witnessed hydrostatic or air pressure test that holds target pressure for the full required duration with zero leaks.

Overview

The rough-in phase is the foundation of every plumbing installation. Before a single fixture is set, the drain-waste-vent (DWV) system, the potable water supply system, and the gas piping branch must all be installed, supported, tested, and documented inside the wall and floor cavities. In this capstone lab you will do exactly that — working from your approved plan set in the full-scale mock-up bay until every pipe, fitting, and valve is in its correct location and every pressure test passes.

DWV Installation

DWV systems carry wastewater away from fixtures and vent sewer gases safely to the atmosphere. Every horizontal drain line must slope continuously toward the building drain. The standard minimum slope for pipes 3 inches and smaller is 1/4 inch of fall per foot of run; pipes 4 inches and larger may use 1/8 inch per foot, though 1/4 inch is preferred and often required. Use a digital level to confirm slope at each hanger location — do not rely on visual judgment alone.

Fittings must be oriented to guide flow in the direction of drainage. Use sanitary tees (not standard tees) for branch connections on horizontal-to-vertical transitions, and long-sweep 90s or 45-degree elbows where horizontal direction changes are necessary. When working with ABS or PVC pipe, apply the manufacturer-approved primer before solvent cement on every joint. Allow adequate cure time before pressurizing the system. Cast-iron no-hub pipe and fittings are joined with stainless-steel shield couplings torqued to the manufacturer's specification with an inch-pound torque wrench.

Hangers and supports must be installed at intervals specified in the applicable plumbing code for each pipe material. Generally, plastic DWV pipe requires support at closer intervals than cast iron. Every vent pipe must be supported at the top of the stack and at intermediate intervals, and must terminate above the roofline at the height required by code and at a safe horizontal distance from any window, door, or air-intake opening.

Once assembly is complete, plug all openings and perform a low-pressure air test witnessed by your instructor. Record the gauge pressure, the start time, the end time, and the result (hold or fail) on the pressure-test log. Zero pressure drop for the full required duration is a passing result.

Potable Water Supply Installation

Water supply piping must be installed to prevent contamination, water hammer, and cross-connections. Begin at the simulated meter location. Run the cold-water main first, then branch off for the hot-water distribution lines.

Install an RPZ (reduced-pressure zone) backflow preventer on the cold-water main as specified in the scenario. An RPZ is a mechanical assembly containing two independently acting check valves and a differential pressure relief valve. It protects the potable supply against both back-siphonage and back-pressure — the highest level of mechanical backflow protection. After installation, complete the ASSE-format backflow test report, documenting each check valve's differential pressure and the relief valve opening point.

Shutoff valves must be installed at locations required by code (typically at each branch serving a fixture group, at each appliance, and at the main). Where a pressure-reducing valve (PRV) is required by the scenario, install it on the cold-water main downstream of the backflow preventer, and set the outlet pressure to the value shown on the plan set.

For copper pipe, use a pipe cutter — not a saw — to produce a square, burr-free cut. Ream and deburr every cut end before assembly. For PEX, use the manufacturer-specified crimp or clamp tool and the correct ring size for the pipe diameter. After all joints and connections are complete, fill the system with water, purge air, and apply the hydrostatic test pressure specified by the applicable code. Hold for the full required duration with zero leaks visible at any joint, valve, or fitting.

Gas Piping Installation

Gas piping demands the highest level of care. You will install a branch of either CSST (corrugated stainless steel tubing) or black-iron pipe from the simulated meter stub to two appliance locations.

For black-iron pipe, use a pipe threader and apply an approved, gas-rated pipe joint compound or PTFE tape rated for gas service to the male threads only. For CSST, follow the manufacturer's fitting instructions precisely — improper CSST fittings are a leading cause of gas leaks.

Before connecting or disconnecting any gas piping, apply lockout/tagout (LOTO) to the simulated gas-meter ball valve: close the valve, attach a hasp, apply your personal lock, and tag the hasp with your name and the date. No one may re-energize the valve until the person who placed the lock removes it.

After assembly, pressure-test with a manometer at the pressure and for the duration required by the applicable fuel-gas code. A manometer measures low pressures in inches of water column, which is the appropriate unit for gas distribution pressure testing. After the pressure hold, inspect every joint with a listed liquid leak-detection solution — bubbling indicates a leak that must be corrected and re-tested. Document gauge readings, start and end times, and results on the gas pressure-test log.

Safety Throughout the Lab

Key terms10

DWV (Drain-Waste-Vent)The piping system that carries wastewater and solid waste away from fixtures to the building drain and simultaneously vents sewer gases to the outside atmosphere to maintain atmospheric pressure in the drain lines.
Slope (Grade)The continuous downward pitch of a horizontal drain pipe, measured in inches of fall per foot of horizontal run, required to keep wastewater moving and prevent solids from settling in the pipe.
RPZ Backflow Preventer (Reduced-Pressure Zone Assembly)A mechanical device installed on the water supply main that uses two independently acting check valves and a differential pressure relief valve to protect the potable water supply from both back-siphonage and back-pressure — the highest level of mechanical backflow protection.
Hydrostatic Pressure TestA test in which the piping system is completely filled with water, pressurized to a specified test pressure, and held for a required duration; a passing result is zero visible leaks at any joint, fitting, or valve.
Low-Pressure Air TestA DWV system test in which all openings are plugged, the system is pressurized with air to the pressure specified by the applicable plumbing code, and the gauge is observed for the required duration; a passing result is zero pressure drop.
ManometerAn instrument that measures pressure in inches of water column (in. W.C.), used for gas piping pressure tests where pressures are too low to read accurately on a standard psi gauge.
Lockout/Tagout (LOTO)An OSHA-required safety procedure for controlling hazardous energy: the energy-isolating device (such as a ball valve) is placed in the safe (closed) position, a hasp and personal lock are applied, and a tag identifying the worker is attached so the valve cannot be re-energized until that worker removes the lock.
CSST (Corrugated Stainless Steel Tubing)A flexible, factory-coated gas piping product installed with manufacturer-specific fittings; it must be bonded per the applicable fuel-gas code and must not be used as a connector between rigid piping and an appliance unless the manufacturer's instructions permit it.
No-Hub CouplingA stainless-steel shield and neoprene gasket assembly used to join cast-iron no-hub DWV pipe and fittings; the shield bolts are torqued to the manufacturer's specification to form a watertight, gas-tight joint.
Pressure-Reducing Valve (PRV)A device installed on the water supply main that automatically reduces the incoming water pressure to a safe, preset outlet pressure, protecting downstream piping, valves, and fixtures from damage due to high supply pressure.

Worked examples4

1. A horizontal branch drain is 14 feet long and must slope at exactly 1/4 inch per foot. How many total inches of fall must exist between the high end and the low end of this pipe run?
  1. Identify the slope rate: 1/4 inch of fall per foot of run.
  2. Identify the total run: 14 feet.
  3. Multiply: 14 feet × 0.25 inch/foot = 3.5 inches.
  4. Confirm units: the answer is in inches of total fall over the 14-foot run.
Answer: The low end of the 14-foot drain line must be 3.5 inches lower than the high end.
2. You are hanging PVC DWV pipe and your code reference states that horizontal PVC pipe must be supported at intervals not exceeding 4 feet. Your horizontal branch run is 22 feet long, beginning at a fitting on the stack. How many hangers are required for this run (not counting any support at the stack fitting itself)?
  1. Identify the run length: 22 feet.
  2. Identify the maximum support interval: 4 feet.
  3. Divide the run by the interval: 22 ÷ 4 = 5.5.
  4. Because you cannot have a fraction of a hanger location and you must not exceed 4 feet between supports, round up to the next whole number: 6 hanger positions.
  5. Place hangers at 4-foot intervals: at 4 ft, 8 ft, 12 ft, 16 ft, 20 ft, and one final hanger at the 22-foot end — that is 6 hangers.
Answer: 6 hangers are required along the 22-foot horizontal PVC run (not counting support at the stack fitting).
3. After assembling a gas piping branch, you connect a manometer and pressurize the system. The initial reading is 10 inches of water column (in. W.C.). After the required hold time, the reading is 9.6 in. W.C. What is the pressure drop, and does this system pass or fail the test if the code allows zero measurable pressure drop?
  1. Record initial pressure: 10.0 in. W.C.
  2. Record final pressure: 9.6 in. W.C.
  3. Calculate pressure drop: 10.0 − 9.6 = 0.4 in. W.C.
  4. Compare to the pass criterion: the code allows zero measurable pressure drop.
  5. 0.4 in. W.C. is a measurable drop — the system fails.
Answer: The pressure drop is 0.4 in. W.C. The system fails the test; all joints must be inspected with listed leak-detection solution, the leak located and repaired, and the test repeated.
4. A 3-inch horizontal drain line must have a minimum slope of 1/4 inch per foot. Using a digital level that reads in percent grade, what percent grade corresponds to exactly 1/4 inch per foot?
  1. Express the slope as a fraction of run: 0.25 inch of rise per 12 inches of run.
  2. Convert to the same units: 0.25 in ÷ 12 in = 0.02083 (dimensionless ratio).
  3. Convert ratio to percent grade: 0.02083 × 100 = 2.083%.
  4. Round to a practical precision: approximately 2.08% grade.
Answer: A slope of 1/4 inch per foot equals approximately 2.08% grade on a digital level set to percent.

The math in this lesson2

Learners compute fall over 14 feet at ¼ inch per foot and count hangers at 4-foot spacing.
6.RP.37.RP.3
Brush up in the math halls at newSchoolWorks.com:
In class: Lay out and cut openings, install hangers and supports at code-required intervals, and assemble the DWV system using ABS or PVC solvent-weld fittings and/or cast iron no-hub couplings; perform a plugged air-pressure test (low-pressure air test per code) witnessed by the instructor and record results on the pressure-test log. · Install copper or PEX water supply lines from a simulated meter location through the mock-up bay to each rough-in point, including shutoff valves, pressure-reducing valve if required by scenario, and an RPZ backflow preventer on the cold-water main; perform a hydrostatic pressure test at the pressure specified by the applicable code, hold for the required time, and complete the ASSE-format backflow test report. · Run a CSST or black-iron gas piping branch from a simulated meter stub to two appliance locations, pressure-test with a manometer at the pressure and duration required by the applicable fuel-gas code, check all joints with listed leak-detection solution, and complete the gas pressure-test log; practice lockout/tagout on the simulated gas-meter ball valve before and after testing.
Materials: Full-scale mock-up bays with studded walls and subfloor, ABS/PVC/cast-iron DWV fittings and pipe, copper and PEX water supply pipe and fittings, CSST and black-iron gas pipe and fittings, RPZ backflow preventer (test cock assembly), hangers and supports, pipe cutters, reciprocating saw, PVC solvent cement and primer, ProPress or PEX crimp tool, manometer, test gauges, air compressor, lockout/tagout station with hasp and personal lock, PPE (safety glasses, gloves, knee pads), NCCER Plumbing L1–4 modules, applicable code book
Check: Instructor witnesses each pressure test and signs the test log; pass standard is zero pressure drop on air test and zero leaks on hydrostatic test held for the full code-required duration; slope verified at minimum 1/4 inch per foot on horizontal drain lines with a digital level (no more than one re-do allowed before grade penalty).

Practice check8

Answer each question, then check it. Nothing is recorded; this is your own practice.

NCCER Plumbing — DWV Systems
1. What is the minimum required slope for a 2-inch horizontal PVC drain line serving a lavatory?
NCCER Plumbing — DWV Systems
2. Which type of fitting is correct for connecting a horizontal branch drain to a vertical soil stack in a DWV system?
Safety — Lockout/Tagout (OSHA)
3. Before performing a gas pressure test on the newly assembled branch piping, what is the first required safety step when working with the simulated gas-meter ball valve?
ASSE Backflow — Backflow Prevention Devices
4. An RPZ backflow preventer is required on the potable water main in this scenario. Which statement best describes why an RPZ provides the highest level of mechanical backflow protection?
NCCER Plumbing — Plastic Piping
5. You apply solvent cement to a PVC DWV joint and immediately notice you forgot to apply primer first. What is the correct action?
NCCER Plumbing — Water Supply Systems
6. During the hydrostatic pressure test on the water supply system, a small drip appears at a PEX crimp connection. What is the correct next step?
NCCER Plumbing — Gas Piping Systems
7. When measuring gas distribution pressure with a manometer, in which unit is the pressure typically expressed?
State Journeyman Plumber — Licensing and Legal Requirements
8. A journeyman plumber candidate is completing rough-in work in a jurisdiction that requires a State Journeyman Plumber license. The candidate has passed all NCCER Plumbing L1–4 assessments but has not yet obtained the state license. Which statement is correct?
Record this lesson on my transcript. Sign in with your key and enrollment email to record lessons (enroll free if you have no key). This page stays open to read and practise.