MFG-INDU16-04 · Lesson 12 · 15.5 clock hours · practice
Preventive Maintenance Programs and Documentation
Objective. Students will develop a written preventive maintenance (PM) schedule for a pump system, perform a full PM on a training pump following that schedule, and complete all required maintenance documentation including work orders, lubrication records, and parts requisition forms.
⚠ Pending professional review
This lesson, its worked examples and its practice questions has not yet been verified by a licensed engineer or certified journey-level tradesperson or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.
VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.
Why Preventive Maintenance Programs Matter
A preventive maintenance (PM) program is a planned, scheduled set of tasks performed on equipment before failure occurs. For pump systems in manufacturing and marine environments, PM is not optional — unplanned pump failures can halt production lines, flood bilges, or create serious safety hazards. A well-designed PM program extends equipment life, reduces repair costs, and creates a documented history that helps technicians spot trends before they become breakdowns.
The two pillars of any PM program are the schedule and the documentation. The schedule tells you what to do and when. The documentation proves it was done correctly and gives future technicians the data they need.
Building a PM Schedule
Start with the manufacturer service manual. The manual specifies lubrication intervals, grease types, inspection points, and torque values. Never substitute your own judgment for the manufacturer's specifications on lubrication type or quantity — using the wrong grease or overpacking bearings causes premature failure just as surely as neglect does.
Group tasks by interval:
- Daily: Check for leaks at the packing gland or mechanical seal, note unusual noise or vibration, verify discharge pressure and flow are within normal operating range, record motor amperage if metered.
- Weekly: Inspect coupling guard for security, check bearing housing temperature with an infrared thermometer and compare to baseline, visually inspect base plate for corrosion or loose anchor bolts.
- Monthly: Lubricate bearings per manufacturer specification, inspect coupling elastomer (spider insert) for cracking or compression set, check packing gland adjustment, clean strainer or suction screen if present.
- Annual: Full disassembly inspection, replace wear parts per manufacturer schedule, measure shaft runout, inspect impeller for erosion or cavitation damage, replace mechanical seal if hours or condition warrant.
Your PM schedule template should include columns for task description, interval, estimated labor hours, required materials and part numbers, and a sign-off line. Every line must be filled in — blank fields indicate an incomplete plan.
Lubrication: The Most Critical Monthly Task
Bearing failure is the leading cause of centrifugal pump downtime, and incorrect lubrication is the leading cause of bearing failure. Follow these steps every time:
1. Identify the correct grease type from the nameplate or service manual. Common types include lithium-complex and polyurea greases, but they are not interchangeable — mixing incompatible greases destroys the base oil structure.
2. Note the quantity specified. Over-greasing forces grease past seals and into the motor windings or causes churning heat buildup. Under-greasing starves the bearing. Use a calibrated grease gun and count strokes if a stroke-per-ounce rating is marked on the gun.
3. Wipe the grease fitting (Zerk fitting) clean before attaching the gun. Pumping in dirty grease through a contaminated fitting defeats the purpose.
4. After greasing, wipe away any purged excess from the relief plug area.
5. Record grease type, quantity, date, and technician name on the lubrication record card immediately.
Checking and Adjusting the Packing Gland
Pumps with compression packing (rather than mechanical seals) require a controlled, slow drip at the stuffing box — typically a few drops per minute — to lubricate and cool the packing. A completely dry gland overheats and scores the shaft sleeve. A gland dripping freely wastes product and indicates worn packing.
To adjust: with the pump running, turn the gland follower nuts evenly, one flat at a time, until drip rate is within the acceptable range in the service manual. Use a feeler gauge to confirm the follower is not cocked (uneven gap side to side). If adjustment no longer controls leakage, the packing must be replaced.
Measuring Bearing Housing Temperature
An infrared thermometer gives a non-contact surface temperature reading. Point the thermometer at the bearing housing (not the coupling or shaft), hold steady, and record the reading. Compare it to your baseline — most anti-friction bearings in pump service are considered normal when running 20–40 °F (approximately 11–22 °C) above ambient, and alarming when the rise exceeds 80–100 °F (approximately 44–56 °C) above ambient, but always defer to the manufacturer's stated limit. A rising trend over successive readings is more meaningful than any single value.
Completing Maintenance Documentation
Work order: Describe the work performed in plain language — what was done, what was found, what was replaced, and any deviations from the schedule. The work order must reference the equipment ID, date, technician name, and hours spent.
Lubrication record card: One card per pump, kept with the equipment file. Every lubrication event gets its own line: date, grease type and brand, quantity applied, and technician initials.
Parts requisition form: If inspection revealed a worn coupling insert, low grease supply, or any part needing replacement, a parts requisition documents the part number, description, quantity needed, and equipment it is for. This feeds into inventory control and purchasing.
Peer Review and the Value of a Second Set of Eyes
Before your paperwork goes to the instructor, your lab partner will check it against a completeness checklist. This mirrors real shop practice, where a lead technician or reliability engineer reviews PM records. Common errors to catch: missing equipment ID, undated entries, incorrect grease designation, bearing temperature recorded without units, and parts requisitions missing part numbers. Correct these before submission — maintenance records are legal and warranty documents and must be accurate.
Safety During PM Activities
- Lockout/tagout (LOTO): Any PM task requiring physical contact with the pump — packing gland adjustment on a stopped unit, coupling inspection, or internal inspection — requires full LOTO per your facility's written procedure before work begins. Never reach into a coupling guard while the driver is energized.
- PPE: Safety glasses at minimum throughout the lab. Chemical-resistant gloves when handling lubricants. Hearing protection if the pump is running during temperature checks.
- Infrared thermometer use: Keep the instrument away from rotating parts. Do not lean across a spinning coupling to reach the bearing housing — position yourself to the side.
- Grease gun pressure: Grease guns generate high pressure. Keep fittings fully seated before pumping to prevent grease injection injuries.
Key terms10
Preventive maintenance (PM) scheduleA documented plan listing specific inspection and servicing tasks, the interval at which each must be performed, required materials, and estimated labor hours, designed to prevent equipment failure before it occurs.
Lubrication record cardA per-equipment document that logs every lubrication event with date, lubricant type and quantity, and technician identification, providing a traceable history of bearing care.
Work orderA formal maintenance document that authorizes and records work performed on specific equipment, including description of tasks, findings, parts used, labor hours, and technician sign-off.
Parts requisition formA document submitted to the storeroom or purchasing department to request replacement parts, identifying part number, description, quantity, and the equipment the parts are for.
Packing gland (stuffing box)The assembly at the pump shaft exit that compresses rings of packing material to control leakage; properly adjusted, it allows a slow controlled drip to cool and lubricate the packing.
Coupling elastomer (spider insert)The flexible rubber or urethane element inside a jaw-type flexible coupling that transmits torque between driver and pump while absorbing vibration and misalignment; it must be inspected for cracking or deformation.
Infrared (IR) thermometerA non-contact instrument that measures surface temperature by detecting emitted infrared radiation; used to monitor bearing housing temperature without touching rotating or energized components.
Lockout/tagout (LOTO)An OSHA-required procedure for isolating and de-energizing equipment and verifying zero energy state before maintenance begins, preventing unexpected startup that could injure workers.
Grease compatibilityThe ability of two greases to be mixed without degrading the thickener structure or oil release properties; incompatible greases mixed in a bearing can cause lubrication failure and overheating.
Baseline temperatureThe bearing housing temperature recorded when equipment is known to be in good condition under normal operating load, used as a reference point to evaluate future readings for rising trends.
Worked examples4
1. The manufacturer service manual states the pump bearing requires 1.5 oz of grease at each monthly interval. Your grease gun is rated at 1 oz per 20 strokes. How many strokes should you apply?
- Identify the required quantity: 1.5 oz.
- Identify the gun output rate: 1 oz per 20 strokes.
- Calculate strokes needed: 1.5 oz × 20 strokes/oz = 30 strokes.
- Verify the answer is a whole number and makes practical sense for one lubrication event.
Answer: Apply 30 strokes of the grease gun to deliver the specified 1.5 oz of grease.
2. During a weekly bearing temperature check, the ambient shop temperature is 72 °F. The infrared thermometer reads 138 °F at the bearing housing. What is the temperature rise above ambient, and does this fall within the typical normal range of 20–40 °F rise?
- Calculate temperature rise: 138 °F − 72 °F = 66 °F rise above ambient.
- Compare to the normal range: 20–40 °F rise is typical for normal operation.
- 66 °F exceeds the upper end of the normal range (40 °F) but is below a commonly cited alarm threshold of 80–100 °F rise.
- Conclude that the reading is elevated and warrants increased monitoring frequency and investigation, but compare to manufacturer's stated limit before making a final call.
Answer: The temperature rise is 66 °F above ambient. This exceeds the typical normal range of 20–40 °F and should be flagged for investigation and more frequent monitoring.
3. A PM schedule lists four task intervals: daily, weekly, monthly, and annual. A pump runs 365 days per year, 52 weeks per year, 12 months per year. A packing gland check takes 10 minutes and is scheduled weekly. A bearing lubrication takes 20 minutes and is scheduled monthly. How many total minutes per year are spent on packing gland checks and bearing lubrication combined?
- Calculate annual packing gland check time: 52 weeks × 10 minutes = 520 minutes per year.
- Calculate annual bearing lubrication time: 12 months × 20 minutes = 240 minutes per year.
- Add both totals: 520 + 240 = 760 minutes per year.
- Convert to hours if needed for work order planning: 760 minutes ÷ 60 = 12.67 hours per year (approximately 12 hours 40 minutes).
Answer: 760 minutes (approximately 12 hours and 40 minutes) per year are spent on packing gland checks and bearing lubrication for one pump.
4. A parts requisition lists three items: two bearing sets at $34.50 each, one coupling elastomer insert at $18.75, and one box of packing rings at $12.00. What is the total cost on the requisition?
- Calculate cost of two bearing sets: 2 × $34.50 = $69.00.
- Add coupling insert: $69.00 + $18.75 = $87.75.
- Add packing rings: $87.75 + $12.00 = $99.75.
Answer: The total parts requisition value is $99.75.
The math in this lesson2
Learners convert 1.5 oz of grease to gun strokes at 20 strokes per ounce and compute annual task counts.
6.RP.37.EE.3
In class: Students are given pump nameplate data, operating conditions, and the manufacturer service manual for a training pump; working individually, they draft a PM schedule listing tasks, intervals (daily, weekly, monthly, annual), required materials, and estimated labor hours, using a provided PM template. · Students execute a complete PM on their assigned training pump following their written schedule: lubricate bearings with correct grease type and quantity per manufacturer specification, check and adjust packing gland, inspect coupling elastomer for wear, measure and record bearing housing temperature with an infrared thermometer, and log all readings on a PM data sheet. · Students complete a full set of maintenance paperwork: a work order describing work performed, a lubrication record card, and a parts requisition for any items needing replacement; documents are reviewed in a peer-review exercise where partners evaluate each other's documentation for completeness and accuracy before instructor review.
Materials: Training centrifugal pumps (one per student or pair), manufacturer service manuals, grease guns with correct grease (per manufacturer spec), infrared thermometer, feeler gauges, PM schedule template, work order forms, lubrication record cards, parts requisition forms, lab notebooks, PPE
Check: Instructor reviews PM schedule for completeness and correct intervals, observes execution of lubrication task for correct technique and quantity, and reviews completed paperwork set; all three documents must be fully complete with no blank required fields and bearing temperature must be recorded—incomplete paperwork or missed lubrication steps require revision and resubmission.
Practice check8
Answer each question, then check it. Nothing is recorded; this is your own practice.
Record this lesson on my transcript. Sign in with your key and enrollment email to record lessons (enroll free if you have no key). This page stays open to read and practise.