Objective. Students conduct a radial topographic survey of a designated 0.5-acre area, collecting sufficient ground shots to support a 1-foot contour interval map.
This lesson, its worked examples and its practice questions has not yet been verified by an industry-certified professional or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.
VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.
A topographic survey captures the shape of the ground — its hills, valleys, slopes, and flat areas — along with visible cultural features such as roads, buildings, and trees. The end product is a point dataset that a GIS technician or surveyor uses to generate contour lines and a digital terrain model (DTM). This lesson guides you through conducting a radial topographic survey of a 0.5-acre site using a total station, with enough shots to support a 1-foot contour interval map.
Contour accuracy depends on how many elevation readings you collect and where. The rule of thumb for a 1-foot contour interval is one shot per contour interval per slope break — meaning every time the grade changes direction or rate, you need a point at that transition. On a smooth, uniform slope you can space shots farther apart; on broken, irregular terrain you collect more. A 0.5-acre site at this density will typically require at least 80 coded ground shots to adequately define the surface. Sparse data produces contours that miss ridges, drainage swales, or abrupt grade changes, making the map useless for design or grading work.
Before picking up an instrument, sketch the site boundary and mark your control points on a field sketch. Identify which two (or more) control points you will occupy. Confirm their coordinates and elevations are in your data collector from a prior control traverse or provided control file. Walk the site and note major breaklines — edges of pavement, tops and toes of banks, drainage channels, and building footprints. Mark these features with flagging so you do not miss them once you are behind the instrument. A Job Hazard Analysis (JHA) must be completed and signed before work begins; this is not optional.
Set the total station over the first control point using a plumb bob or optical/laser plummet. Level carefully using the tribrach plate bubble. In the data collector, start a new job (or open the existing project), enter the occupied point coordinates and instrument height, then sight the backsight control point and enter its coordinates. The instrument computes an azimuth; never assume the backsight is correct — verify the angle residual is within your project tolerance before collecting any data.
Each shot is stored with a feature code that describes what was measured — for example, EP for edge of pavement, TBC for top of bank, TOE for toe of slope, TREE for a tree, BLDG for a building corner, or GSPOT for a plain ground shot. Codes let the office software connect points into breaklines automatically and assign the right symbology. Call out the code to your rod person or enter it in the data collector before recording the measurement. Work systematically: start at one boundary and move across the site in a logical pattern rather than jumping randomly. This reduces the chance of missing a slope break.
For each shot:
1. Direct the rod person to the target location.
2. Sight the prism, lock on, and verify the prism height matches what is entered.
3. Record the shot with the correct code.
4. Note any features that the code alone does not fully describe in the field book.
After collecting sufficient shots from the first setup, move the instrument to the second control point. Repeat the setup and backsight procedure. Collect additional shots to cover areas that were obstructed or too far from the first station. A minimum combined total of 80 coded shots across both setups is required for this exercise.
At the close of each occupation, before you break down the instrument, take a foresight to a checkpoint with independently known coordinates. The data collector will display the difference between the measured position and the known position — this is the residual. For third-order work, horizontal and vertical residuals must each be within the tolerance specified by your project control (commonly ±0.1 ft or better for local site surveys at this order). Record the residual in your field book next to the setup number. If the residual exceeds tolerance, investigate: check that the correct point number was used, verify the prism height, and re-level if needed. Data collected from a setup that fails the check shot must be flagged for review and may need to be recollected.
PPE is mandatory at all times: Class II high-visibility vest, hard hat, and safety glasses. Before the survey, complete and file the JHA identifying hazards such as vehicle traffic, uneven terrain, underground utilities, and adverse weather. Never set up in a travel lane without flagging, cones, and advance warning signs per your site-specific traffic control plan. Communicate with your rod person using radio or cell phone — establish check-in intervals so you always know where crew members are. In hot weather, carry water and watch for heat stress. In cold weather, handle the instrument with care; batteries lose capacity rapidly. Never leave the total station unattended on a tripod in windy conditions or where it could be struck by equipment.
Your field book must record: the date, weather, crew names, instrument serial number, control point IDs occupied, backsight IDs, instrument heights, prism heights, and the check-shot residuals for each setup. A printed or sketched site diagram with the approximate locations of major features is also expected. These notes are a legal record of the work performed. Sloppy or incomplete notes are a professional liability.
At the end of the session, download the data collector file and verify that all point codes are present and readable before leaving the site. It is far easier to fill a gap while you are still in the field.
Answer each question, then check it. Nothing is recorded; this is your own practice.
A free tech program — complimentary, as our commitment to get America working. Help us build VoTechWorks. Tell us what works, what doesn’t, and what you want to learn.