BLD-MASO04-11 · Lesson 1 · 30 clock hours · theory
Project Planning, Design, and Safety Documentation
Objective. Students produce a complete project packet—scaled elevation and plan drawings, material takeoff, mortar specification, and a written job-site safety plan—before any physical work begins.
⚠ Pending professional review
This lesson, its worked examples and its practice questions has not yet been verified by a licensed professional engineer or master tradesperson or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.
VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.
Why Planning Comes Before the First Brick
In professional masonry, no crew breaks ground—or lays a single unit—until a complete project packet is in the foreman's hands. The packet translates an idea into a buildable, priceable, and safe plan. For your capstone project you will produce three documents: scaled drawings, a material takeoff (MTO), and a written job-site safety plan. Each one protects you: drawings prevent costly rework, the MTO controls budget, and the safety plan keeps everyone healthy.
Scaled Elevation and Plan Drawings
Start on masonry grid paper, where each square represents one course height or one unit length. Sketch the structure freehand first—your minimum 8-ft-long wall with an integrated arch and a veneer section—then letter in dimensions. When the sketch looks right, transfer it to a formal scaled drawing at 1/4 in. = 1 ft. At this scale, your 8-ft wall spans exactly 2 inches on paper.
Every drawing must label:
- Material zones — which areas are brick, concrete masonry unit (CMU), or stone veneer
- Control joints — vertical breaks filled with backer rod and sealant, placed at intervals recommended by the manufacturer and your NCCER trainee guide to relieve thermal and shrinkage stress
- Coursing heights — cumulative dimensions showing the top of each course, including mortar bed thickness (typically 3/8 in.)
- Arch geometry — spring line, rise, span, and skewback angle for the integrated arch
Use an architectural scale rather than a ruler. Check every dimension twice: errors on paper cost nothing; errors in the field cost materials, time, and credibility.
Material Takeoff
A material takeoff translates drawing dimensions into ordered quantities. Work through each material category in order.
Masonry units: Calculate face area (length × height) of each material zone in square feet, subtract openings, then divide by the face area of one unit. Add a waste factor—commonly 5 % for brick and CMU, up to 10 % for cut stone or detailed arch work—and round up to the nearest full unit or pallet.
Mortar: A standard rule of thumb is that one bag of masonry cement (with sand mixed at the bag manufacturer's ratio) covers roughly 25–35 brick or 8–12 CMU in typical running-bond work, depending on unit size and joint thickness. Verify the ratio against the mortar specification you select (Type S is the most common structural choice; Type N suits above-grade, non-load-bearing veneer).
Reinforcing bar and metal ties: Read the drawings for bar size and spacing; calculate linear feet and add lap-splice lengths per your NCCER guide. Count wall ties at the spacing shown—ties are typically required at specified intervals both horizontally and vertically in anchored veneer systems.
Once quantities are established, price the list using the supplier quote sheet your instructor provides. Multiply quantity × unit cost for each line, sum the column, and add applicable sales tax if shown. A professional MTO is the backbone of any bid.
Mortar Specification
Your project packet must state the mortar type (ASTM C270), mix proportions, and the intended use for each zone. Type S mortar (higher strength, moderate flexibility) is appropriate for below-grade work, retaining walls, and areas subject to lateral loads. Type N mortar (lower strength, greater flexibility) suits above-grade, non-structural veneer. The arch keystone area may require a specific mix design—consult your NCCER trainee guide and record the specification clearly so any mason on the job knows exactly what to mix.
Written Job-Site Safety Plan
OSHA 29 CFR 1926 Subpart Q covers masonry construction specifically, and broader Subpart R covers steel erection; however, most hazard controls for a wall project live in Subpart Q and in the general-duty requirements of 29 CFR 1926. Your one-page plan must address four hazard categories:
1. Scaffold hazards. Any scaffold over 10 ft requires guardrails on all open sides and ends. Inspect the scaffold each shift. Never overload a platform—know the rated capacity. PPE: hard hat, non-slip footwear.
2. Silica dust (mortar mixing and cutting). Crystalline silica is released when cutting masonry or mixing dry mortar. Controls include wet suppression (water on the blade or work surface), local exhaust ventilation, and—when engineering controls alone are insufficient—an N95 or higher respirator, selected according to OSHA's Respirable Crystalline Silica standard (29 CFR 1926.1153). Conduct exposure assessment or follow the Table 1 control methods for the specific task.
3. Manual lifting. Masonry units can be heavy; an 8-in. CMU may weigh 35–40 lb. Use a team-lift protocol for units or bags above 50 lb. Instruct the crew: straight back, bent knees, load close to the body, no twisting while loaded.
4. Electric tools. All electric tools used outdoors or in wet/damp locations must be protected by a ground-fault circuit interrupter (GFCI). Inspect cords before each use; remove damaged cords from service. PPE: safety glasses or face shield when operating angle grinders or saws.
For each hazard, your plan lists: the hazard, the engineering or administrative control, and the required PPE. Reference the applicable OSHA subpart by subject area (not just a number) so any inspector or crew member can verify compliance quickly.
Assembling the Project Packet
Collate your packet in this order: (1) scaled drawings, (2) MTO with pricing, (3) mortar specification, (4) safety plan. Include your name, date, and project title on every sheet. A rubric-graded packet is your proof of pre-job planning—the professional standard before any physical work begins.
Key terms10
Material Takeoff (MTO)A systematic calculation of every material type and quantity required to complete a construction project, derived directly from the scaled drawings and used for ordering and pricing.
Architectural ScaleA triangular drafting tool with multiple scale ratios (e.g., 1/4 in. = 1 ft) used to produce and read proportionally accurate drawings.
Waste FactorA percentage added to the calculated net quantity of a material to account for cuts, breakage, and handling losses; commonly 5 % for standard brick or CMU.
Control JointA vertical, full-depth gap in a masonry wall, filled with flexible backer rod and sealant, designed to relieve and concentrate thermal and shrinkage movement and prevent uncontrolled cracking.
Type S MortarAn ASTM C270 mortar with high compressive strength and moderate flexibility, commonly specified for below-grade masonry, retaining walls, and structural applications subject to lateral loads.
Type N MortarAn ASTM C270 mortar with medium compressive strength and good flexibility, typically used for above-grade, non-load-bearing, or exterior veneer applications.
Ground-Fault Circuit Interrupter (GFCI)An electrical protection device that detects small imbalances in current flow and trips the circuit within milliseconds, required by OSHA for electric tools used in damp or wet conditions.
Respirable Crystalline SilicaFine particles of silicon dioxide released when cutting or grinding masonry materials; a serious respiratory hazard regulated under OSHA 29 CFR 1926.1153 for construction.
Spring LineThe horizontal line at the level where an arch begins to curve, marking the transition from vertical wall to the arch itself; a key reference dimension on arch drawings.
Coursing HeightThe cumulative vertical dimension of masonry units plus mortar joints, used on drawings to dimension the wall at each horizontal course and ensure consistent layout.
Worked examples4
1. Calculate the number of standard modular bricks needed for a running-bond wall section that is 8 ft long and 4 ft tall, using a 5 % waste factor. A standard modular brick laid in running bond has a face area of approximately 32 sq in. (2-2/3 in. tall × 8 in. long, including a 3/8-in. mortar joint on top and one end — actual face area per brick in the wall).
- Step 1 — Find the gross wall face area: 8 ft × 4 ft = 32 sq ft.
- Step 2 — Convert to square inches: 32 sq ft × 144 sq in./sq ft = 4,608 sq in.
- Step 3 — Divide by the face area of one brick: 4,608 ÷ 32 = 144 bricks (net quantity).
- Step 4 — Apply 5 % waste factor: 144 × 1.05 = 151.2 → round up to 152 bricks.
Answer: 152 bricks required.
2. A scaled drawing is made at 1/4 in. = 1 ft. A wall segment measures 3-1/2 inches on the drawing. What is the actual length of the wall in feet and inches?
- Step 1 — Identify the scale: 1/4 in. on paper = 1 ft in the field, so 1 in. on paper = 4 ft in the field.
- Step 2 — Multiply the drawing measurement by the scale factor: 3.5 in. × 4 ft/in. = 14 ft.
- Step 3 — State the answer in feet and inches: 14 ft 0 in.
Answer: 14 ft 0 in.
3. Price the brick quantity from Worked Example 1. The supplier quote sheet shows standard modular brick at $0.85 per brick, with a minimum delivery charge of $75. How much should the MTO budget for brick (material + delivery)?
- Step 1 — Multiply quantity by unit price: 152 bricks × $0.85 = $129.20.
- Step 2 — Add the delivery charge: $129.20 + $75.00 = $204.20.
- Step 3 — Record $204.20 on the MTO pricing sheet as the brick line-item total.
Answer: $204.20 total for brick (material and delivery).
4. A mortar specification calls for Type S mortar. The mason mixes one bag of masonry cement yielding approximately 30 bricks' worth of coverage. How many bags of masonry cement are needed for the 152 bricks in Example 1, rounding up to whole bags?
- Step 1 — Divide total brick count by coverage per bag: 152 ÷ 30 = 5.07 bags.
- Step 2 — Round up to the next whole bag: 6 bags.
- Step 3 — Record 6 bags of masonry cement on the MTO. Note that sand and water must also be listed per the bag manufacturer's mix ratio.
Answer: 6 bags of masonry cement.
The math in this lesson2
Learners count bricks for an 8×4 ft wall with 5% waste, price them at $0.85, scale a drawing, and estimate mortar bags.
6.RP.37.G.1
In class: Sketch and dimension the capstone structure (minimum 8-ft-long wall with integrated arch and veneer section) using masonry grid paper, then transfer to a scaled drawing at 1/4 in. = 1 ft, labeling all material zones, control joints, and coursing heights. · Complete a material takeoff worksheet calculating brick, block, stone, mortar ingredients, metal ties, and reinforcing bar quantities using standard waste factors; price the list using a current supplier quote sheet provided by the instructor. · Draft a one-page written site safety plan identifying hazards (scaffold, mortar silica dust, manual lift weight limits, electric tools), corresponding controls (guardrails, wet suppression/respirator, team-lift protocol, GFCI), and required PPE for each phase, citing OSHA general-industry and construction standards by subject area.
Materials: Masonry grid paper, architectural scale, pencil, calculator, NCCER Masonry L1–3 trainee guides, OSHA 29 CFR 1926 Subpart Q (masonry) reference handout, supplier price sheet, material takeoff form template, project packet rubric
Check: Instructor grades the complete project packet against a 25-point rubric: drawing legibility and dimensional accuracy (8 pts), takeoff within ±5 % of instructor calculation (9 pts), safety plan covering all identified hazards with correct controls (8 pts). Minimum passing score: 20/25 (80 %).
Practice check8
Answer each question, then check it. Nothing is recorded; this is your own practice.