BLD-CONS02-06 · Lesson 5 · 10 clock hours · lab
Light-Gauge Metal-Stud Framing for Non-Load-Bearing Partitions
Objective. Students cut and assemble a 10-foot non-load-bearing metal-stud partition with a door opening using proper layout, fasteners, and deflection head detail, with all studs plumb within 1/8 inch.
⚠ Pending professional review
This lesson, its worked examples and its practice questions has not yet been verified by a licensed professional engineer or master tradesperson or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.
VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.
Light-Gauge Metal-Stud Framing for Non-Load-Bearing Partitions
Light-gauge steel framing is the standard system for interior non-load-bearing partition walls in commercial and multi-family construction. The components are cold-formed from sheet steel, lightweight, dimensionally stable, and non-combustible. This lab builds a 10-foot partition with a door rough opening and a deflection head detail — skills directly tested in NCCER Construction Technology and expected by employers on any commercial jobsite.
What Is Light-Gauge Steel Framing?
For non-load-bearing partitions, the two main components are track (the horizontal channel fastened to floor and ceiling) and studs (the vertical members that slip inside the track). Track looks like a U-channel with no lips; studs have a web, two flanges, and small return lips that add rigidity. In this lab you will use 3-5/8-inch, 25-gauge material — the gauge number refers to the sheet-steel thickness, with higher numbers meaning thinner steel. 25-gauge is common for interior non-structural partitions.
Layout
Accurate layout is the foundation of a plumb, straight wall. Snap a chalk line on the floor for the face of the wall. Use a plumb bob or laser level to transfer the line to the ceiling directly above. Both lines must be perfectly plumb to each other; if they are not, no amount of adjusting individual studs will fix the problem. Cut the floor and ceiling track to length with aviation snips or a chop saw fitted with a metal-cutting blade (carbide-tipped or abrasive). Mark door-opening locations on the floor track before fastening; you will cut the floor track out of the opening area but leave the ceiling track continuous.
Fastening Track to Structure
Floor track is fastened to concrete slabs with concrete screws (such as Tapcon-style anchors) or powder-actuated fasteners (PAF), following the manufacturer's specified spacing. Ceiling track is fastened to the deck or framing above. Drill or punch anchor holes in the track flanges before driving fasteners. Do not fasten within 12 inches of a track splice; overlap splices at least 6 inches.
Stud Installation at 16-Inch On-Center Spacing
Measure and mark stud locations at 16 inches on center along both floor and ceiling track. Cut studs to a length that allows them to slip freely inside the track — typically 3/8 inch to 1/2 inch shorter than the floor-to-ceiling height; this clearance is intentional, not an error. Slide each stud into both tracks, orient the open side (the web opening) consistently in one direction, and twist the stud 90° before releasing so the flanges seat against the track flanges. Attach each stud flange to the track with a No. 8 wafer-head self-drilling screw or a crimping tool at each flange — that is two fasteners per end, four per stud.
Door Rough Opening
A door rough opening requires king studs on each side of the opening, running full height from floor track to ceiling track. A header spans between the king studs above the door. For a non-load-bearing partition, the header is typically a piece of track cut and notched to fit between the king studs, or a clip-angle assembly — it carries no structural load but provides a nailing/screwing surface for the door frame. Install a cripple stud between the header and the ceiling track at 16-inch on-center spacing if the header is not at the ceiling.
The Deflection Head Detail — Critical Concept
In multi-story buildings, floors deflect (move downward) under live load. If the ceiling track is rigidly fastened and cannot move, the wall will be crushed or buckled when the floor above deflects. The solution is a slotted deflection track (also called a slip track) at the ceiling. The slots in the track flanges allow the studs to slide up and down inside the track, absorbing floor-to-floor movement without transferring load into the partition.
The most common installation error is screwing through the slot and into the stud. If a screw pins the stud to the slotted track, the deflection feature is completely defeated and the wall can be damaged under load. The correct method, per Steel Framing Industry Association (SFIA) guidelines, is to fasten the slotted track to the structure above through the track web, and then fasten the stud to the track only at the floor-track end. The top of the stud floats inside the slotted ceiling track with no fastener pinning it in place.
Plumb Tolerance
The pass/fail standard for this lab is all studs plumb within 1/8 inch over the full stud height. Check plumb with a 4-foot or 6-foot level held against the stud flange. A stud out of plumb transfers misalignment to the drywall surface, creating a wavy, unacceptable finish.
Safety Rules for This Lab
- Safety glasses are mandatory at all times — cut steel produces sharp chips and burrs.
- Cut-resistant gloves must be worn when handling cut steel; edges are razor-sharp.
- Hearing protection is required when operating the chop saw.
- When using a powder-actuated fastener tool, only a licensed or trained operator may fire the tool; treat it like a firearm — keep the muzzle pointed at the work surface and never override the contact safety.
- Keep hands clear of the chop saw blade; use clamps or vise jaws, not your hand, to hold short pieces.
- Lock-out/tag-out is not applicable here, but always unplug or disable corded tools before changing blades.
- Dispose of steel scrap in a designated metal bin — loose pieces on the floor are a cut and trip hazard.
Completing the Lab
When your wall is assembled, the instructor will check three studs for plumb with a level and verify the deflection head detail. Record your measurements and observations in your lab log before the end of class.
Key terms10
Light-gauge steel framingCold-formed sheet-steel structural components — track and studs — used primarily for non-load-bearing interior partitions in commercial construction.
TrackHorizontal U-shaped channel fastened to the floor and ceiling; studs slip inside the track flanges to form the wall frame.
Deflection head track (slip track)A ceiling track with slotted flanges that allow studs to move vertically, absorbing floor-to-floor deflection without transferring load to the partition.
Non-load-bearing partitionAn interior wall that divides space but carries no structural load from floors, roofs, or other framing above it.
King studA full-height stud on either side of a door or window rough opening that provides a fastening surface for the header and the door frame.
On-center (OC) spacingThe distance measured from the center of one stud to the center of the next; 16 inches OC is the standard for light-gauge partition framing.
Powder-actuated fastener (PAF)A tool that uses a powder charge to drive a hardened pin into concrete or steel; requires trained operators and specific PPE.
No. 8 wafer-head self-drilling screwThe standard fastener for attaching light-gauge steel studs to track; the wafer head distributes load across the flange and the self-drilling point eliminates pre-drilling.
25-gauge steelSheet steel at the thinner end of the light-gauge range, commonly used for interior non-load-bearing partitions; higher gauge numbers indicate thinner material.
SFIA (Steel Framing Industry Association)The trade association that publishes prescriptive installation guidelines for light-gauge steel framing, including deflection head details.
Worked examples4
1. The floor-to-ceiling height is 9 feet 1 inch (109 inches). What length should you cut each stud so it fits freely inside the track with the correct clearance?
- Step 1: Identify the required clearance. Standard practice for light-gauge non-load-bearing studs is to cut them 3/8 inch to 1/2 inch shorter than the floor-to-ceiling dimension. Use 3/8 inch for this calculation.
- Step 2: Convert the floor-to-ceiling height to inches. 9 feet × 12 = 108 inches, plus 1 inch = 109 inches total.
- Step 3: Subtract the clearance. 109 inches − 3/8 inch = 108-5/8 inches.
- Step 4: Convert back to feet and inches for the saw setting. 108 inches = 9 feet 0 inches, plus 5/8 inch = 9 feet 0-5/8 inches.
Answer: Cut each stud to 9 feet 0-5/8 inches (108-5/8 inches).
2. You are laying out studs at 16 inches on center along a 10-foot (120-inch) floor track. Starting from the left end, list the center-mark locations for the first five studs.
- Step 1: The first stud center is placed at 16 inches from the starting end of the track.
- Step 2: Each subsequent stud center is 16 inches from the previous one.
- Step 3: Calculate positions: Stud 1 = 16 in; Stud 2 = 16 + 16 = 32 in; Stud 3 = 32 + 16 = 48 in; Stud 4 = 48 + 16 = 64 in; Stud 5 = 64 + 16 = 80 in.
- Step 4: Verify units. All values are in inches from the left end of the track.
Answer: Stud centers at 16 in, 32 in, 48 in, 64 in, and 80 in from the starting end.
3. A stud measures 1/4 inch out of plumb at the top over a stud height of 96 inches. Is this within the 1/8-inch tolerance required for this lab?
- Step 1: State the tolerance. The lab pass/fail standard is all studs plumb within 1/8 inch over the full height.
- Step 2: Compare the measured deviation to the tolerance. The stud is 1/4 inch (0.250 inch) out of plumb.
- Step 3: 1/4 inch is greater than 1/8 inch (0.125 inch).
- Step 4: Conclusion: the stud exceeds the allowable tolerance and must be adjusted before the instructor check.
Answer: No. 1/4 inch exceeds the 1/8-inch tolerance. The stud must be plumbed and re-checked.
4. Your 10-foot partition has a 3-foot rough door opening starting 2 feet from the left end of the wall. How much floor track do you need for this wall (the floor track is cut away at the door opening)?
- Step 1: Total wall length = 10 feet = 120 inches.
- Step 2: Door opening width = 3 feet = 36 inches. The floor track is removed across the full door opening.
- Step 3: Floor track on the left side of the door = 2 feet = 24 inches.
- Step 4: Floor track on the right side of the door = total wall − left section − door opening = 120 − 24 − 36 = 60 inches = 5 feet.
- Step 5: Total floor track needed = left piece + right piece = 24 inches + 60 inches = 84 inches = 7 feet.
Answer: You need 7 feet of floor track total: a 2-foot piece on the left and a 5-foot piece on the right of the door opening.
The math in this lesson1
Learners cut metal studs to height minus clearance, mark 16 in centers, and compute floor track less the door opening.
N-Q.3
In class: Snap layout lines on floor and ceiling for track placement; cut floor and ceiling track to length with aviation snips or a chop saw with a metal-cutting blade, drill or punch anchor holes, and fasten with appropriate concrete screws or powder-actuated fasteners per manufacturer specification. · Insert 25-gauge studs at 16-inch on-center spacing, twist 90° into track, and attach with No. 8 wafer-head screws or crimping tool at each flange; install king studs and clip-angle or structural stud header at the door rough opening. · Install a slotted (deflection) head track at the ceiling to allow for floor-to-floor movement; demonstrate why a standard screw in the top track slot would defeat deflection, then fasten correctly per Steel Framing Industry Association guidelines.
Materials: 25-gauge light-gauge steel studs and track (3-5/8 inch), aviation snips (left, right, straight), No. 8 self-drilling screws, cordless screw gun, chop saw with metal-cutting blade, chalk line, tape measure, level, concrete screws, PPE (safety glasses, cut-resistant gloves, hearing protection), SFIA Prescriptive Method reference
Check: Instructor checks stud plumb at three studs (pass = all within 1/8 inch) and verifies deflection head detail is correctly installed (screw in slot, not pinned); lab log entry required.
Practice check8
Answer each question, then check it. Nothing is recorded; this is your own practice.
Record this lesson on my transcript. Sign in with your key and enrollment email to record lessons (enroll free if you have no key). This page stays open to read and practise.