Objective. Students will identify the primary OSHA and ASME B30 standards governing rigging operations and list at least six common rigging hazards with their controls.
This lesson, its worked examples and its practice questions has not yet been verified by a licensed professional engineer or master tradesperson or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.
VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.
Rigging failures are among the most deadly events on a construction site. A single dropped load or a snapped sling can kill workers instantly and destroy equipment worth hundreds of thousands of dollars. To prevent these events, two overlapping frameworks govern rigging: OSHA regulations, which are enforceable federal law, and ASME B30 standards, which are consensus engineering standards widely adopted by employers and referenced by OSHA.
As a craft worker, you are legally required to follow OSHA rules and professionally expected to know the ASME standards. Ignorance of either is not a defense when an inspector writes a citation—or when someone is carried off a jobsite.
OSHA covers construction rigging primarily in 29 CFR 1926, Subpart H (Materials Handling, Storage, Use, and Disposal) and Subpart CC (Cranes and Derricks in Construction). General industry rigging falls under 29 CFR 1910, Subpart N.
OSHA also requires employers to ensure that loads are never moved over workers and that tag lines are used to control swinging loads.
The American Society of Mechanical Engineers publishes the B30 family of standards for lifting devices and rigging hardware.
These standards do not replace OSHA; they add engineering detail. When OSHA says a sling must be inspected, B30.9 tells you exactly what to look for.
Recognizing hazards before a lift is the single most effective way to prevent injuries. The following are six hazards you must be able to identify:
1. Overloaded rigging hardware. Using a shackle or sling beyond its Working Load Limit (WLL) can cause sudden failure. Control: Always check the WLL marked on the hardware and compare it to the calculated load—including the effect of sling angle.
2. Damaged or degraded slings. Cuts, abrasion, kinking, chemical damage, heat damage, and (for wire rope) broken wires all reduce capacity. Control: Inspect every sling before use per B30.9; remove from service any sling that meets rejection criteria.
3. Improper sling angle. As the horizontal angle of a sling decreases below 60°, tension in each leg increases dramatically, often beyond the sling's WLL. Control: Use a sling-angle factor chart; keep angles at 60° or greater whenever possible.
4. Missing or inadequate edge protection. Sharp edges cut synthetic and wire-rope slings during a lift. Control: Use corner pads, softeners, or shackle-based rigging configurations to protect slings from edges.
5. Improper storage. Slings stored in UV sunlight, near chemicals, or piled on the ground become degraded before their first use. Control: Store slings hung on racks, indoors or under cover, away from chemicals and heat sources.
6. Missing PPE. Riggers who do not wear hard hats, safety glasses, and leather gloves risk crush injuries from shifting loads and cuts from wire-rope ends. Control: Enforce PPE requirements at the pre-lift meeting; no PPE, no participation in the lift.
7. Unbalanced or unstable loads. A load whose center of gravity is unknown or shifts during the lift can tip and strike workers. Control: Determine the center of gravity before rigging; use a test lift a few inches off the ground to verify balance.
8. Workers in the fall zone. No worker should stand under a suspended load or in the path a load would travel if released. Control: Establish and enforce a drop zone; use spotters and barriers; never walk under a load.
Before any lift, OSHA requires a pre-lift meeting when lifts are complex or involve multiple crews. Even for routine lifts, experienced riggers follow a mental inspection sequence:
1. Identify the load weight and center of gravity.
2. Select rigging hardware with WLL that exceeds the load on each component.
3. Inspect all slings and hardware visually.
4. Rig the load; perform a trial lift inches off the ground.
5. Verify the fall zone is clear before the load rises.
This sequence, combined with knowledge of applicable standards, is the foundation of safe rigging practice and is tested on NCCER credentials.
When rigging near energized equipment, lockout/tagout (LOTO) procedures must be in place before work begins. Never rig around moving machinery without confirming energy isolation. Minimum PPE for rigging operations includes a hard hat, safety-toed boots, safety glasses, and heavy leather gloves. High-visibility vests are required wherever mobile equipment operates nearby.
Answer each question, then check it. Nothing is recorded; this is your own practice.
A free tech program — complimentary, as our commitment to get America working. Help us build VoTechWorks. Tell us what works, what doesn’t, and what you want to learn.