Discharge Monitoring Reports and Recordkeeping Requirements

Objective. Students will accurately complete a Discharge Monitoring Report (DMR) using provided lab results and permit limits, identifying any exceedances and the required notification steps.

⚠ Pending professional review

This lesson, its worked examples and its practice questions has not yet been verified by a licensed professional in the field or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.

VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.

What Is a Discharge Monitoring Report?

A Discharge Monitoring Report (DMR) is the official document a permitted facility uses to report effluent monitoring data to the regulatory authority, typically the state environmental agency or the U.S. Environmental Protection Agency (EPA). If your facility holds a National Pollutant Discharge Elimination System (NPDES) permit, you are legally required to submit DMRs on the schedule your permit specifies—usually monthly, quarterly, or semi-annually. Submitting an inaccurate or late DMR is a permit violation and can result in fines or enforcement action. An unfiled DMR is treated the same as a violation.

Key Fields on a DMR Form

Every DMR form contains several standard fields you must understand before you can complete one correctly.

Permit Number and Outfall Number: These identify exactly which permit and which discharge point the data covers. Copy them directly from your permit—any mismatch can cause a submission to be rejected or misfiled.

Parameter Name and Units: Each pollutant you must monitor is listed as a parameter (for example, BOD₅, TSS, pH, fecal coliform). Units must match those in your permit exactly. Reporting milligrams per liter when the permit states micrograms per liter is a significant error.

Monitoring Frequency: Your permit states how often you must sample—daily, weekly, or monthly. The number of samples you collect during the reporting period must meet or exceed this requirement. If you collected fewer samples than required, note the shortfall; failing to meet the minimum monitoring frequency is itself a violation.

Quantity or Loading vs. Concentration: Some parameters are reported as concentration (mg/L), others as mass loading (lbs/day), and some as both. Mass loading is calculated from concentration and flow. Know which your permit requires for each parameter.

Monthly Average and Daily Maximum: Most NPDES permits set two limit types. The monthly average limit applies to the arithmetic mean of all samples collected in the calendar month. The daily maximum (or instantaneous maximum) limit applies to any single sample result. Both must be compared to permit limits separately.

Exceedance Notation: If any reported value exceeds the permit limit, you must clearly mark it as an exceedance on the DMR. Many forms use an asterisk or a separate exceedance column. Never leave this blank or unmarked—intentionally hiding an exceedance can result in serious legal consequences.

Calculating Monthly Averages

To find the monthly average for a parameter, add all valid sample results for that parameter collected during the month and divide by the number of samples. Only use results from samples collected and analyzed under your permit's approved methods. If a result is reported as a non-detect below a laboratory method detection limit, consult your permit or state guidance on how to handle it—common practice is to substitute half the detection limit or zero, but your permit or state rules govern.

What Happens When You Find an Exceedance?

Identifying an exceedance on a DMR triggers a specific set of obligations beyond simply marking the form.

1. Immediate oral notification: Most permits require you to notify the regulatory agency by phone within 24 hours of becoming aware of a violation that causes or threatens to cause harm, or within the timeframe your permit specifies.

2. Written report: A written report describing the violation, its cause, and corrective actions taken is typically required within a short window—often five days—though your specific permit controls the deadline.

3. Root cause investigation and corrective action: Document what caused the exceedance and what you are doing to prevent recurrence. Regulators look favorably on proactive corrective action.

4. Mark the DMR accurately: Sign and submit the DMR on time even if it shows violations. Late submission on top of a violation compounds your compliance problems.

Recordkeeping Requirements

NPDES regulations generally require that monitoring records, including lab reports, chain-of-custody forms, calibration logs, and copies of all DMRs, be retained for a minimum of three years from the date of the report or the date the data were collected. Your state may require a longer retention period, and your permit may specify additional requirements—always check both. Store records in a way that keeps them legible, organized, and retrievable during an inspection. Inspectors can and do request records from prior years.

Best practice is to keep hard copies in a labeled binder organized by parameter and date, and to back up digital records in a secure location. Never alter a monitoring record after the fact; falsification of records is a federal and state crime.

Compliance Calendar

A compliance calendar is a simple scheduling tool that lists every reporting and sampling deadline required by your permit for the entire year. It should include DMR due dates, sampling dates, inspection dates, and records retention milestones. Post it in the control room and review it at the start of each month. Missing a deadline is far easier to prevent than to explain after the fact.

Safety Reminder

When collecting effluent samples near discharge points or wet wells, always wear appropriate PPE: chemical-splash safety glasses, nitrile or chemical-resistant gloves, and slip-resistant boots. Be aware of slippery surfaces and confined-space hazards near wet wells. Never enter a confined space for sampling without following your facility's confined-space entry program, including atmospheric testing and a trained attendant outside.

Key terms9

Discharge Monitoring Report (DMR)The official form submitted to the regulatory authority reporting actual effluent monitoring data for each parameter required by an NPDES permit.
NPDES PermitNational Pollutant Discharge Elimination System permit; the federal authorization required before a facility may legally discharge pollutants into waters of the United States.
Monthly Average LimitA permit limit that applies to the arithmetic mean of all sample results collected for a parameter during a calendar month.
Daily Maximum LimitA permit limit that applies to any single sample result collected on a given day; one exceedance triggers a violation regardless of the monthly average.
ExceedanceA condition in which a reported monitoring value is greater than (or for pH, outside the range of) the applicable permit limit.
OutfallThe specific, permitted point at which treated effluent is discharged from a facility into a receiving water body; each outfall has its own monitoring and reporting requirements.
Records RetentionThe legally required minimum period for which monitoring records, DMRs, lab reports, and related documents must be kept and available for regulatory inspection.
Compliance CalendarA scheduling tool listing all permit-required sampling, reporting, and inspection deadlines throughout the year to help operators avoid missed obligations.
Mass LoadingThe quantity of a pollutant discharged per unit of time, calculated from concentration and flow rate, typically expressed in pounds per day.

Worked examples4

1. A wastewater plant collects five weekly TSS samples during one month with results of 12, 18, 15, 22, and 13 mg/L. The permit monthly average limit is 20 mg/L and the daily maximum limit is 30 mg/L. Calculate the monthly average and determine whether any limit is exceeded.
  1. Add all five sample results: 12 + 18 + 15 + 22 + 13 = 80 mg/L (sum).
  2. Divide the sum by the number of samples: 80 ÷ 5 = 16.0 mg/L (monthly average).
  3. Compare monthly average to limit: 16.0 mg/L is less than 20 mg/L — no monthly average exceedance.
  4. Compare each individual result to the daily maximum limit of 30 mg/L: the highest single result is 22 mg/L, which is less than 30 mg/L — no daily maximum exceedance.
  5. Conclusion: No exceedances; report 16.0 mg/L as the monthly average and 22 mg/L as the reported daily maximum on the DMR.
Answer: Monthly average = 16.0 mg/L (no exceedance); daily maximum reported value = 22 mg/L (no exceedance). No violations to flag.
2. A facility has four BOD₅ results for the month: 28, 34, 31, and 37 mg/L. The permit sets a monthly average limit of 30 mg/L and a daily maximum limit of 45 mg/L. Determine whether any limit is exceeded and describe the required next steps if so.
  1. Add all four results: 28 + 34 + 31 + 37 = 130 mg/L.
  2. Divide by 4: 130 ÷ 4 = 32.5 mg/L (monthly average).
  3. Compare monthly average to limit: 32.5 mg/L exceeds the 30 mg/L monthly average limit — EXCEEDANCE.
  4. Compare each result to the daily maximum limit of 45 mg/L: the highest is 37 mg/L, which is below 45 mg/L — no daily maximum exceedance.
  5. Mark the monthly average field with the exceedance notation on the DMR.
  6. Required next steps: notify the regulatory agency orally as required by the permit timeline; submit a written report describing the violation, probable cause, and corrective action within the permit-specified deadline; document corrective measures taken.
Answer: Monthly average = 32.5 mg/L, which exceeds the 30 mg/L limit. Flag as exceedance on the DMR and initiate notification and reporting procedures per permit requirements.
3. An operator needs to report mass loading for phosphorus. The daily effluent flow is 2.5 million gallons per day (MGD) and the measured phosphorus concentration is 1.8 mg/L. Calculate the mass loading in pounds per day using the standard conversion factor of 8.34 lb/gal.
  1. Identify the formula: Mass loading (lb/day) = Concentration (mg/L) × Flow (MGD) × 8.34 (lb/gal conversion factor).
  2. Substitute values: 1.8 mg/L × 2.5 MGD × 8.34 = ?
  3. First multiply 1.8 × 2.5 = 4.5.
  4. Then multiply 4.5 × 8.34 = 37.53 lb/day.
  5. Round to appropriate significant figures per your facility's reporting practice: 37.5 lb/day.
Answer: Phosphorus mass loading = 37.5 lb/day.
4. A facility collects three pH readings in one day: 6.4, 5.9, and 6.8 standard units (s.u.). The permit requires pH to be maintained between 6.0 and 9.0 s.u. at all times. Identify any exceedances.
  1. Compare each reading individually to the permit range of 6.0–9.0 s.u. (pH limits are instantaneous, not averaged).
  2. Reading 1: 6.4 s.u. — within range, no exceedance.
  3. Reading 2: 5.9 s.u. — below the minimum limit of 6.0 s.u. — EXCEEDANCE.
  4. Reading 3: 6.8 s.u. — within range, no exceedance.
  5. Flag the 5.9 s.u. result as an exceedance on the DMR and follow permit notification requirements.
Answer: The 5.9 s.u. reading is below the 6.0 s.u. minimum; this is a daily maximum (instantaneous) exceedance. Flag it on the DMR and notify the regulatory agency per permit requirements.

The math in this lesson1

Learners average five results to a 16.0 mg/L monthly mean and compare to permit limits.
S-ID.2
Brush up in the math halls at newSchoolWorks.com:
In class: Instructor demonstrates completion of a paper DMR form using sample effluent monitoring data, explaining each field: permit limit, units, monitoring frequency, calculated average, maximum reported value, and exceedance notation. · Students independently complete two DMR forms from provided sets of effluent lab results; they calculate monthly averages, compare to permit limits, and flag any violations with a written note of required next steps. · Class reviews the federal recordkeeping rule requirements (records must generally be retained for at least three years for NPDES; instructor confirms current requirement without specifying a code section that may vary); students create a compliance calendar showing reporting and records retention deadlines.
Materials: Blank DMR forms (EPA or state version), sample effluent lab result data sets, calculators, permit limits reference sheet, recordkeeping requirements summary, compliance calendar template
Check: Both completed DMRs checked for calculation accuracy and correct exceedance notation; 90% accuracy on numerical calculations required, and all exceedances must be correctly identified.

Practice check8

Answer each question, then check it. Nothing is recorded; this is your own practice.

Regulations and Permit Compliance
1. What is the primary purpose of a Discharge Monitoring Report (DMR)?
Mathematics and Data Analysis
2. A permit sets a monthly average TSS limit of 25 mg/L. An operator collects four samples with results of 20, 28, 22, and 26 mg/L. What is the monthly average, and is there a violation?
Regulations and Permit Compliance
3. Under federal NPDES regulations, monitoring records must generally be retained for a minimum of how long?
Regulations and Permit Compliance
4. An operator discovers that effluent BOD exceeded the daily maximum permit limit yesterday. What should the operator do first?
Regulations and Permit Compliance
5. Which of the following actions regarding DMR recordkeeping could result in federal criminal charges?
Mathematics and Data Analysis
6. A facility's effluent phosphorus concentration is 2.4 mg/L and the daily flow is 1.5 MGD. Using the conversion factor of 8.34 lb/gal, what is the daily mass loading in pounds per day?
Regulations and Permit Compliance
7. Which of the following best describes the purpose of a compliance calendar in a wastewater facility?
Safety and Health
8. When collecting effluent samples at a discharge outfall near a wet well, which of the following safety precautions is most important?