MFG-MECH15-09 · Lesson 2 · 180 clock hours · field

Assisted Production Tasks: Robots, PLCs, and Drives

Objective. Working under direct or general supervision, the student will carry out assigned production-support tasks — including robot program calls, teach-pendant jogging, PLC I/O monitoring, drive parameter checks, and basic preventive maintenance — and log each task with enough detail to show the methods and safety precautions used.

⚠ Pending professional review

This lesson, its worked examples and its practice questions has not yet been verified by a licensed engineer or certified journey-level tradesperson or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.

VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.

Assisted Production Tasks: Robots, PLCs, and Drives

During your externship placement you will move from the lab to a live production environment. Your role is to support the site technician — not to work independently — and every task you perform must be authorized by your supervisor before you begin. This lesson prepares you to carry out the three main categories of assigned production-support tasks: robot preventive maintenance (PM), PLC and HMI fault monitoring, and drive setup support. It also reminds you of the safety obligations that apply on any industrial site.

Safety First: Lockout/Tagout and Electrical Hazards

Before touching any machine, confirm which energy-control procedure applies. OSHA 29 CFR 1910.147 (Control of Hazardous Energy) requires that all potentially hazardous energy sources — electrical, pneumatic, hydraulic, gravitational — be isolated, locked, and tagged before any servicing or maintenance activity. You must have your own lock and tag; never rely on someone else's lock to protect you.

For electrical work, NFPA 70E requires you to determine the arc-flash and shock boundaries before approaching exposed conductors. Wear the PPE specified on the site's arc-flash label (at minimum, safety glasses; often a face shield, arc-rated clothing, and insulating gloves for energized-work tasks). Before declaring a circuit de-energized, use a properly rated meter to verify the absence of voltage — test the meter on a known live source first, test the circuit, then test the meter again.

For robot cells, ANSI/RIA R15.06 / ISO 10218 defines safeguarding requirements. Confirm that safety-fence interlocks and light curtains are functional before any cell operation resumes after maintenance. Never defeat or bypass a safety device, even temporarily, without explicit written authorization from the site safety officer.

Machine guarding rules under OSHA 1910.212 also apply: pinch points, rotating shafts, and nip points on conveyors must be guarded whenever the machine is running.

Robot Preventive Maintenance Tasks

Scheduled PM keeps industrial robots reliable and safe. When assisting with FANUC or equivalent robot PM, your responsibilities typically include:

Joint lubrication check. Consult the robot manufacturer's maintenance schedule (found in the controller or a paper log) to confirm whether grease replenishment is due based on operating hours. Record the date of the last service and the current hour count from the controller. Do not add lubricant unless specifically instructed — using the wrong grease type or quantity can damage seals.

Teach-pendant battery backup. The FANUC controller stores programs and system parameters in battery-backed memory. Check the controller alarm log and the pendant display for any low-battery warning. Record the battery installation date from the maintenance log. A dead battery can cause loss of all stored programs, so this check is critical and maps directly to the FCR-T1/T2 curriculum area of program backup.

Safety fence interlock verification. With the site technician supervising and the cell in a safe state, test each gate switch and light curtain: open the gate and confirm the robot enters a safe stop; close the gate and confirm the run-enable signal returns. Record each test result (pass/fail) in your field log. This links to ANSI/RIA R15.06 safeguarding requirements.

I/O and frame notes. Review the program structure with the technician — note which user frame and tool frame are active, and confirm that the I/O signals for the gripper or end-of-arm tool respond correctly during a dry-cycle jog. These topics are core FCR-T curriculum areas.

PLC and HMI Fault Monitoring

In a live facility you will use the site's PLC software or HMI to observe real-time production data. When monitoring I/O in ladder logic (the most common IEC 61131-3 language on manufacturing floors), energized contacts appear highlighted and coils show their true ON/OFF state. To trace a fault:

1. Open the maintenance or alarm log and note the fault code, time stamp, and affected device.

2. Navigate to the rung that controls that device. Look for contacts that should be closed but are open, or coils that are unexpectedly de-energized.

3. Cross-reference the I/O address with the site's wiring diagram to identify the physical sensor or switch involved.

4. Report your finding to the technician before any corrective action is taken.

Record the IEC 61131-3 language observed, the fault code, and the corrective action the technician took. Common corrective actions include clearing a jammed sensor, resetting an overload relay, or correcting a wire connection — each of which must follow the appropriate LOTO procedure.

Drive Setup and Motor Speed Calculations

When a cell changeover involves a VFD or servo drive, you may be asked to record motor nameplate data and verify that the drive parameters match the motor's specifications. Key nameplate values include rated voltage, full-load amps, horsepower or kW, rated RPM, and the number of poles.

From the nameplate pole count and the supply frequency, calculate synchronous speed:

Ns = 120 × f / P

where f is supply frequency in Hz and P is the number of poles. An induction motor always runs slightly below synchronous speed; the difference is slip. Confirm that the speed shown on the HMI is close to (but less than) the calculated Ns at full load — a large deviation may indicate a load or parameter problem. Log the nameplate data, your calculation, and the HMI reading in your field log.

Field Log Requirements

Every task must be logged on the same day it occurs. Each entry must include: date and hours worked, a description of the task, the equipment involved (make, model, tag number if available), the safety steps you followed (LOTO applied, PPE worn, interlocks verified), and a credential-mapping note identifying which FANUC CERT, PMMI, or Siemens SMSCP domain the task relates to. Your school coordinator reviews entries bi-weekly, and your site supervisor completes a midpoint evaluation between weeks 8 and 10 of the placement. A passing result requires a satisfactory or better rating on all evaluated domains.

Key terms9

Lockout/Tagout (LOTO)The energy-isolation procedure required by OSHA 29 CFR 1910.147; each worker applies a personal lock and tag to every energy-isolating device before servicing equipment to prevent unexpected energization.
Synchronous speed (Ns)The theoretical no-load speed of an AC induction motor's rotating magnetic field, calculated as Ns = 120 × f / P, where f is supply frequency (Hz) and P is the number of motor poles.
SlipThe difference between synchronous speed and actual rotor speed in an induction motor, expressed as a percentage; slip produces the torque that drives the load.
IEC 61131-3The international standard defining five PLC programming languages: ladder diagram, function block diagram, structured text, sequential function chart, and instruction list.
Safety fence interlockA gate switch or light curtain wired into the robot cell's safety circuit so that opening the guard or breaking the light-curtain beam causes the robot to enter a safe stop, per ANSI/RIA R15.06.
Arc-flash boundaryA distance defined by NFPA 70E inside which a worker could receive a second-degree burn from an arc-flash incident; appropriate arc-rated PPE must be worn within this boundary.
Program backup (FANUC)The process of saving all robot programs, system variables, and configuration data to an external device (USB or memory card) so that files can be restored after a controller fault or battery failure; a core FCR-T curriculum area.
VFD (Variable Frequency Drive)An electronic drive that controls AC motor speed and torque by varying the output frequency and voltage supplied to the motor; parameters such as acceleration ramp, maximum frequency, and motor nameplate data must be set correctly.
Verify absence of voltageThe NFPA 70E requirement to use a properly rated voltage tester to confirm that a circuit is de-energized before work begins, using the test-before-touch sequence: test meter on known live source, test the circuit, test meter again.

Worked examples4

1. A 4-pole, 60 Hz induction motor drives a conveyor in the robot cell. Calculate its synchronous speed.
  1. Identify the values: f = 60 Hz, P = 4 poles.
  2. Apply the formula: Ns = 120 × f / P.
  3. Substitute: Ns = 120 × 60 / 4.
  4. Calculate the numerator: 120 × 60 = 7,200.
  5. Divide: 7,200 / 4 = 1,800 RPM.
Answer: Synchronous speed Ns = 1,800 RPM. The motor nameplate will show a full-load speed slightly below 1,800 RPM (for example, 1,750 RPM) due to slip.
2. The same 4-pole, 60 Hz motor has a nameplate full-load speed of 1,746 RPM. Calculate the percent slip at full load.
  1. Synchronous speed Ns = 1,800 RPM (from the previous example).
  2. Full-load speed Nr = 1,746 RPM (from nameplate).
  3. Slip = (Ns − Nr) / Ns × 100%.
  4. Numerator: 1,800 − 1,746 = 54 RPM.
  5. Divide: 54 / 1,800 = 0.03.
  6. Convert to percent: 0.03 × 100 = 3%.
Answer: Percent slip at full load = 3%. This is a normal value for a standard induction motor.
3. During drive setup, the HMI shows the motor running at 1,200 RPM. The VFD output frequency is set to 40 Hz instead of 60 Hz. Verify whether 1,200 RPM is the expected synchronous speed at 40 Hz for a 4-pole motor.
  1. Use Ns = 120 × f / P with f = 40 Hz and P = 4.
  2. Ns = 120 × 40 / 4.
  3. Numerator: 120 × 40 = 4,800.
  4. Divide: 4,800 / 4 = 1,200 RPM.
Answer: Synchronous speed at 40 Hz = 1,200 RPM. The HMI reading is consistent with the VFD output frequency; the motor will run slightly below 1,200 RPM at full load due to slip. Record both the calculation and the HMI value in the field log.
4. A 4-20 mA pressure transmitter on a hydraulic circuit is wired to a PLC analog input. The PLC engineering-unit range is scaled 0–3,000 psi for 4–20 mA. The live raw count reads 12 mA. What pressure does this represent?
  1. Determine the current span: 20 − 4 = 16 mA.
  2. Determine the offset above the live zero (4 mA): 12 − 4 = 8 mA.
  3. Calculate the fraction of span: 8 / 16 = 0.5 (50%).
  4. Apply the fraction to the engineering-unit span: 0.5 × 3,000 psi = 1,500 psi.
  5. Add the range minimum (0 psi): 1,500 + 0 = 1,500 psi.
Answer: The transmitter is reporting 1,500 psi. Record the raw mA value, the scaling calculation, and the result in the field log when verifying analog I/O.

The math in this lesson2

Learners scale a raw analog count to hydraulic pressure on a 0–3,000 psi range.
F-LE.1A-CED.4
Brush up in the math halls at newSchoolWorks.com:
In class: Assist the site technician with scheduled preventive maintenance on at least one FANUC or equivalent industrial robot: check joint lubrication schedule entries, verify teach-pendant battery backup status, confirm safety fence interlocks function, and document findings; connect tasks to FCR-T1/T2 curriculum areas (program backup, I/O verification, frames) in the field log. · Under supervision, use the site's PLC programming software or HMI to monitor live I/O, interpret ladder logic rungs related to a current production process, and identify the root cause of at least two minor faults logged in the maintenance system; record the IEC 61131-3 language used, the fault code, and the corrective action taken. · Assist with setup or changeover of an automated cell involving at least one drive (VFD or servo): observe or participate in parameter review, record motor nameplate data, calculate synchronous speed (Ns = 120f / P) and expected slip for the motor in use, and confirm actual speed on the HMI; record the calculation and result in the field log.
Materials: Site production equipment (industrial robots, PLCs, VFDs, HMIs, sensors), teach pendant, laptop with site-approved PLC software access if permitted, multimeter and clamp meter, motor nameplate data sheet, student field log binder, OSHA 29 CFR 1910.147 reference card
Check: School coordinator reviews field log entries bi-weekly; log must include date, hours, task description, equipment involved, safety steps taken, and a credential-mapping note for each entry; site supervisor midpoint evaluation (week 8–10 of placement) must rate the student satisfactory or above on technical task performance and safety compliance; pass = midpoint evaluation average of satisfactory or better on all rated domains.

Practice check8

Answer each question, then check it. Nothing is recorded; this is your own practice.

Safety — LOTO / Hazardous Energy Control
1. Before performing a lubrication check on a robot joint, which OSHA standard requires you to isolate and lock out the robot's energy sources?
Drive Setup — Motor Speed Calculations (FCR-T / PMMI Motor and Motor Controls)
2. A 6-pole induction motor is supplied at 60 Hz. What is its synchronous speed?
Safety — NFPA 70E Electrical Safety
3. When verifying the absence of voltage on a panel before replacing a VFD fuse, the correct sequence using a voltage tester is:
FANUC CERT — Program Backup (FCR-T1/T2)
4. During a FANUC robot PM, you find a low-battery warning on the teach pendant. Why is this critical?
PLC Fault Monitoring — IEC 61131-3 / PMMI Programmable Logic Controllers
5. You are monitoring ladder logic on a live PLC and notice that a normally closed contact addressed to a limit switch is shown as open (not energized) even though the HMI shows the machine should be running. The most logical next step is to:
Robot Safety — ANSI/RIA R15.06 (FCR-T Safeguarding)
6. A robot cell gate switch is opened during a test. According to ANSI/RIA R15.06, what should happen immediately?
PLC Analog I/O — 4-20 mA Scaling (PMMI Industrial Electricity / Siemens SMSCP L1)
7. A 4-20 mA flow transmitter is scaled to 0–500 GPM on the PLC. The live reading is 4 mA. What flow rate does this represent?
Professional Practice — Field Documentation / Externship Requirements
8. Your field log entry for a robot PM task must include which of the following to meet the program's documentation standard?
Record this lesson on my transcript. Sign in with your key and enrollment email to record lessons (enroll free if you have no key). This page stays open to read and practise.