BLD-WELD01-08 · Lesson 8 · 11 clock hours · demo
Heat Treatment: Preheat, Interpass Temperature Control, and PWHT
Objective. The student demonstrates verification and control of preheat, interpass temperature, and simulated post-weld heat treatment (PWHT) parameters on a structural steel weld, and documents the thermal record on a standard heat-treatment log.
Why Thermal Control Matters in Structural and Pipe Welding
Steel responds to heat in predictable but unforgiving ways. Weld too cold and hydrogen can crack the heat-affected zone (HAZ). Weld too hot and you coarsen the grain structure, destroy toughness, or distort a carefully fitted joint. Three thermal controls keep those problems in check: preheat, interpass temperature control, and post-weld heat treatment (PWHT). Every major welding standard — AWS D1.1 for structural steel and ASME Section IX for pressure-boundary welds — requires these controls to be specified in the Welding Procedure Specification (WPS) and documented in the record.
Preheat: Starting Warm on Purpose
Preheat is heat applied to the base metal before the arc is struck. Its main jobs are:
- Slow the cooling rate so hydrogen has time to escape the weld metal before it becomes trapped.
- Reduce thermal shock and the hardness spike that forms in the HAZ of hardenable steels.
- Drive off moisture from the joint surface, which is a hydrogen source.
For A572 Grade 50 structural steel in thicker sections (typically 1.5 in. and above), preheat requirements depend on the carbon equivalent of the heat, the process, and filler hydrogen level. Your WPS or the applicable code table tells you the minimum temperature. A common way to apply preheat on the job is a propane rosebud torch or a resistance-heating blanket. The blanket is preferred when a long, uniform soak is needed; the torch is faster for smaller areas.
How to verify: Use a calibrated contact thermometer or a Tempilstik (temperature-indicating crayon) rated to the target temperature. Per standard practice, check the temperature at least 3 inches from the edge of the weld joint on each side. If the Tempilstik melts when touched to the steel, the surface has reached that crayon's rated temperature. The contact thermometer gives you an exact reading you can record on the heat-treatment log. Do not strike an arc until the required preheat is confirmed and the instructor has signed the log — this is a safety gate in this program.
Interpass Temperature: Keeping the Lid On
Once welding begins, each subsequent pass adds heat. The interpass temperature is the temperature of the weld and adjacent base metal measured immediately before a new pass is deposited. Code procedures set both a minimum (same as preheat — the joint must not cool below preheat between passes) and a maximum (to protect the HAZ microstructure and mechanical properties).
Exceeding the maximum interpass temperature can:
- Reduce notch toughness in the HAZ.
- Cause excessive grain growth in low-alloy and alloy steels.
- Alter distortion behavior in precision-fit joints.
Check interpass temperature with a contact thermometer placed on the weld bead or within the joint. If the reading is above the maximum specified in the procedure, stop welding and allow the plate to cool naturally — never quench with water unless the WPS specifically permits it. Record the reading, the time, and your initials on the heat-treatment log. The instructor reviews and co-signs each entry.
Post-Weld Heat Treatment (PWHT): Stress Relief and Tempering
PWHT is a controlled thermal cycle applied after the weld is complete. For pressure-boundary components — such as chrome-moly (Cr-Mo) alloy pipe used in power plants and refineries — PWHT is mandatory under ASME Section IX and the applicable construction code. Its purposes include:
- Stress relief — relaxing residual stresses locked in during cooling.
- Hydrogen bake-out — driving remaining diffusible hydrogen out of thick sections.
- Tempering — softening the hard HAZ martensite in hardenable alloys, restoring ductility and toughness.
A PWHT cycle has three controlled phases recorded on the heat-treatment log:
1. Ramp rate (heat-up rate) — how fast the temperature rises, typically expressed in °F per hour. Heating too fast creates new thermal stresses.
2. Time at temperature (hold time) — the soak period at the target temperature. For P91 Cr-Mo pipe, the hold temperature and duration are critical and specified in the applicable code and the Procedure Qualification Record (PQR).
3. Cooling rate — how fast the assembly is allowed to cool after the hold. Cooling too quickly can re-introduce residual stress or cause cracking in sensitive alloys.
All three values must be filled in on the heat-treatment log. That log becomes a permanent attachment to the Procedure Qualification Record (PQR) under ASME Section IX, providing proof that the qualified procedure was followed on the actual production weld.
Safety Points for This Demo
- Resistance blankets and rosebud torches reach temperatures that cause severe burns instantly. Wear your welding jacket, leather gloves, and face shield whenever handling heated steel or operating the torch.
- Hot plate coupons look identical to cold ones. Use a Tempilstik or thermometer before touching any surface. Mark hot parts clearly.
- Propane torch use requires proper hose, regulator, and flashback-arrestor inspection before ignition. Secure cylinders upright.
- SMAW on preheated plate increases fume generation. Ensure ventilation is operating and position your head out of the fume plume.
- A missed temperature check means an automatic redo of the station — not as a punishment, but because an undocumented thermal record is worthless in the field and can mean a failed weld in a structure.
The Heat-Treatment Log
The log you complete today mirrors what is used on certified projects. Every field matters: joint ID, base metal specification and thickness, preheat method, preheat temperature measured and location, interpass temperatures by pass number, time stamps, and welder ID. Incomplete logs are rejected on ASME-governed work sites. Practice the habit now.
Key terms9
PreheatHeat applied to the base metal before welding begins, used to slow the cooling rate, allow hydrogen to escape, and reduce the risk of HAZ cracking.
Interpass temperatureThe temperature of the weld area measured immediately before depositing a subsequent pass; must stay within the minimum and maximum limits set by the WPS or applicable code.
Post-Weld Heat Treatment (PWHT)A controlled thermal cycle applied after welding is complete to relieve residual stress, bake out hydrogen, and temper the HAZ; required by ASME Section IX for many pressure-boundary applications.
Tempilstik (temperature-indicating crayon)A crayon formulated to melt at a specific temperature; dragged across the steel surface to give a quick visual confirmation that preheat has been reached.
Heat-affected zone (HAZ)The portion of the base metal adjacent to the weld that is not melted but whose microstructure and properties are altered by the heat of welding.
Ramp rateThe controlled rate at which temperature is raised or lowered during PWHT, expressed in degrees per hour, to avoid introducing new thermal stresses.
Procedure Qualification Record (PQR)Under ASME Section IX, the document that records the actual variables used and test results obtained when qualifying a welding procedure; heat-treatment logs are attached as supporting evidence.
Carbon equivalentA calculated value that combines the percentages of carbon and alloying elements in a steel to estimate its hardenability and susceptibility to HAZ hydrogen cracking; used to determine preheat requirements.
P91 steelA 9% chromium, 1% molybdenum alloy steel (ASME P-Number 15E) used in high-temperature piping systems; requires strict PWHT to achieve the required microstructure and creep resistance.
Worked examples4
1. Your WPS requires a minimum preheat of 150 °F for 1.5-in. A572-50 plate. You have Tempilstiks rated at 125 °F and 150 °F. Describe the verification sequence before you strike the arc.
- Step 1 – Apply the 125 °F Tempilstik to the plate surface at least 3 inches from the joint edge. If it does not melt, the plate is below 125 °F; continue heating.
- Step 2 – Continue applying heat with the torch or blanket. Recheck with the 125 °F Tempilstik periodically until it melts, confirming the surface has reached at least 125 °F.
- Step 3 – Apply the 150 °F Tempilstik to the same location (at least 3 inches from the joint). When it melts, the surface has reached at least 150 °F — the minimum required.
- Step 4 – Confirm with the calibrated contact thermometer by pressing the probe to the plate at least 3 inches from the joint. Record the reading, time, and your initials on the heat-treatment log.
- Step 5 – Present the log to the instructor for signature before striking the arc.
Answer: The arc may be struck only after the contact thermometer reads ≥ 150 °F at least 3 inches from the joint on both sides, the reading is logged, and the instructor has signed the log.
2. After completing Pass 1, you measure the interpass temperature at 425 °F. The WPS specifies a maximum interpass temperature of 400 °F. What do you do, and what do you record?
- Step 1 – Stop. Do not begin Pass 2. The measured temperature (425 °F) exceeds the WPS maximum (400 °F) by 25 °F.
- Step 2 – Allow the plate to cool naturally in still air. Do not use water, compressed air, or any quench method unless your WPS explicitly permits it.
- Step 3 – Monitor with the contact thermometer. When the reading drops to 400 °F or below, record the new temperature, the time, and your initials in the interpass temperature row for Pass 2 on the heat-treatment log.
- Step 4 – Verify the plate has not dropped below the minimum preheat temperature. If it has, re-apply heat to restore preheat before welding.
- Step 5 – Call the instructor to co-sign the log entry showing the out-of-range reading, the corrective action, and the acceptable re-check temperature.
Answer: Welding stops; the plate cools naturally to ≤ 400 °F; the out-of-range reading, corrective action, and the acceptable temperature are all recorded and co-signed by the instructor before Pass 2 begins.
3. A hypothetical PWHT procedure for a P91 pipe repair specifies: heat-up rate not to exceed 200 °F/hr, hold at the required temperature for 1 hour per inch of thickness for a 0.75-in. wall, and cooling rate not to exceed 300 °F/hr down to 600 °F (then air cool). Calculate the minimum hold time and the maximum allowable temperature drop in the first hour of cooling.
- Step 1 – Calculate hold time: 1 hr/in × 0.75 in = 0.75 hr. Code practice rounds up to a minimum of 0.75 hr (45 minutes); confirm with the applicable code — many codes specify a minimum of 15 minutes regardless, so 0.75 hr applies here.
- Step 2 – Confirm the ramp-up is controlled: starting from ambient (~70 °F), reaching the hold temperature must not occur faster than 200 °F/hr. Record actual ramp-up readings at regular intervals on the log.
- Step 3 – Calculate maximum temperature drop in the first hour of cooling: maximum cooling rate is 300 °F/hr, so in one hour the temperature may fall by no more than 300 °F from the hold temperature.
- Step 4 – Once the temperature reaches 600 °F, controlled cooling is no longer required; the assembly may air cool. Record the time and temperature at which controlled cooling ends.
Answer: Minimum hold time = 0.75 hr (45 minutes). Maximum temperature drop in the first hour of cooling = 300 °F. Controlled cooling ends at 600 °F; all values are entered on the heat-treatment log.
4. The heat-treatment log requires you to calculate the actual heat-up rate achieved. The recorder chart shows the weld went from 70 °F to 470 °F in 2 hours. What was the actual ramp rate, and did it comply with a 200 °F/hr maximum?
- Step 1 – Calculate temperature rise: 470 °F − 70 °F = 400 °F total rise.
- Step 2 – Calculate actual ramp rate: 400 °F ÷ 2 hr = 200 °F/hr.
- Step 3 – Compare to the maximum allowed: 200 °F/hr ≤ 200 °F/hr. The rate exactly meets but does not exceed the limit.
Answer: Actual ramp rate = 200 °F/hr. This is compliant — it equals but does not exceed the 200 °F/hr maximum. Record 200 °F/hr on the PWHT log.
In class: Instructor demonstrates setting up a resistance blanket or propane torch for preheat on a 1.5-in. A572-50 plate and shows how to use a calibrated contact thermometer and Tempilstik to verify temperature at a distance of at least 3 inches from the weld joint per standard practice; students repeat the procedure individually. · Students make a two-pass SMAW weld on preheated plate, monitoring and recording interpass temperature between passes using a contact thermometer; if interpass temperature exceeds the instructor-set maximum (simulating a D1.1 or ASME procedure limit), welding stops until the plate cools—instructor signs the log. · Walk through a PWHT heat-treatment record form (time-at-temperature, ramp rate, cooling rate fields) using a hypothetical scenario for a P91 chrome-moly pipe repair, completing all fields and discussing how the record becomes part of the Procedure Qualification Record under ASME Section IX.
Materials: Resistance heating blanket or propane rosebud torch, calibrated contact thermometer, temperature-indicating sticks, 1.5-in. A572-50 plate coupons, SMAW power source, E7018-H4R electrodes, heat-treatment log form, ASME Section IX PWHT requirements excerpt, PPE (welding jacket, gloves, face shield)
Check: Preheat verified and documented before welding begins (safety gate—instructor signature required); interpass temperature recorded for each pass; PWHT log completed correctly with all fields filled. Instructor signs thermal record. Any missed temperature check = automatic redo of station.
Practice check8