BLD-WELD01-07 · Lesson 8 · 12 clock hours · practice

Field Sketching, Redlines, and Requests for Information

Objective. Students will produce a legible freehand field sketch with correct AWS A2.4 welding symbols and write a formal request for information (RFI) when drawing information is ambiguous or missing.

Why Field Sketching and RFIs Matter

On a structural steel job site, the printed drawing set is the legal document of record. But drawings are created months before steel is cut, and the field rarely matches the office perfectly. Dimensions get omitted, weld symbols conflict with the bill of materials, or a detail simply does not exist for a condition that showed up during erection. When that happens, welders and ironworkers do not guess and they do not proceed on assumption — they document the problem and get an answer in writing. Two tools make that happen: the field sketch and the request for information (RFI).

As a welder in the building and construction sector, you will be expected to read, mark up, and sometimes produce simple freehand drawings. You will also be expected to recognize when something on a drawing is wrong or missing and to communicate that clearly. These skills appear in NCCER Welding Level 2 coursework and are directly relevant to working under AWS D1.1, which requires that welds conform to qualified procedure specifications and approved drawings.

Field Sketching Conventions

A field sketch is a freehand drawing made on-site to record existing conditions, proposed changes, or details that are not shown in the contract documents. It does not need to be artistic, but it must be legible, labeled, and dimensioned.

Use these conventions every time:

AWS A2.4 Welding Symbols on Sketches

Whenever your sketch includes a weld, you must use the symbol system defined in AWS A2.4, Standard Symbols for Welding, Brazing, and Nondestructive Examination. Inventing your own notation is not acceptable on a structural project.

For a fillet weld — the most common weld in structural steel fabrication — the symbol elements you must show are:

1. Reference line: A horizontal line is the backbone of every welding symbol.

2. Arrow: Drawn from one end of the reference line, pointing to the joint. The side of the joint the arrow touches is the arrow side; the opposite side is the other side.

3. Weld symbol: A right triangle placed on the reference line. If it is below the line, the weld is on the arrow side. If above, it is on the other side.

4. Weld size: A number to the left of the weld symbol, indicating leg size in inches (for example, 5/16).

5. Weld length: A number to the right of the weld symbol, indicating the total length of weld in inches. If the weld is continuous and runs the full joint length, the length may be omitted, but it is good practice to include it.

6. Tail (if needed): A fork at the opposite end of the reference line is used to reference a welding procedure specification (WPS) or note.

On a T-joint field sketch, always double-check: Is the weld on one side or both? The symbol must match the physical condition.

Marking Up a Drawing — Redlines

A redline is a markup of a contract drawing done in red ink to show discrepancies, field-installed conditions that differ from the drawing, or proposed changes. Redlines are legal documents on most projects. Follow these rules:

Writing a Formal Request for Information

An RFI is a written question submitted by the contractor or subcontractor to the engineer of record (EOR) or architect when something in the contract documents is unclear, missing, or contradictory. It creates a paper trail and protects everyone.

A standard RFI form includes:

Do not proceed with welding in the discrepant area until you receive a written answer — a verbal answer on the job site is not sufficient.

Safety Note

When walking a structure to gather field measurements for a sketch, you are working in an active construction zone. Wear your full PPE: hard hat, safety glasses, steel-toed boots, and high-visibility vest. Do not remove PPE to handle drawings or write notes. If you are near any welding operations, add appropriate eye protection. Never rest on or step over welded connections that have not been inspected and accepted.

Key terms9

Field sketchA freehand drawing made on-site to record existing conditions, missing details, or proposed changes; must be labeled, dimensioned, and include a north arrow, scale notation, and title block information.
RedlineA markup of a contract drawing done in red ink to show discrepancies or field conditions that differ from the original; each change is enclosed in a cloud with a delta revision mark.
Cloud-and-deltaThe industry-standard revision marking system in which a freehand cloud shape circles a changed area and a numbered triangle (delta, Δ) outside the cloud identifies the revision number.
Request for Information (RFI)A formal written document submitted by the contractor to the engineer of record asking for clarification when drawing information is ambiguous, missing, or contradictory; creates a binding written record.
AWS A2.4The American Welding Society standard that defines the symbols used to specify welding, brazing, and nondestructive examination requirements on engineering drawings.
Reference lineThe horizontal backbone of every AWS A2.4 welding symbol; weld symbols are placed above or below this line to indicate other-side or arrow-side welds respectively.
Arrow side / Other sideThe two sides of a joint as identified by the welding symbol: the arrow side is the surface the arrow touches; the other side is the opposite surface; symbols below the reference line indicate arrow-side welds.
NTS (Not To Scale)A notation written on freehand or modified drawings indicating that dimensions must be read from the written numbers, not estimated by measuring the drawing itself.
Engineer of Record (EOR)The licensed structural engineer whose stamp appears on the contract drawings and who is responsible for issuing official answers to RFIs affecting the structural design.
In class: Instructor demonstrates field sketching conventions — north arrows, grid lines, freehand scale notation, cloud-and-delta revision marks — using a real redline markup of a structural drawing as the example. · Students receive a fabricated steel assembly with three intentional drawing discrepancies (missing weld symbol, conflicting dimension, unlabeled material); they mark up a printed drawing in red and write a formal one-page RFI for one of the discrepancies. · Students produce a freehand field sketch of a physical T-joint assembly on the bench, adding the correct AWS A2.4 fillet weld symbol with size, length, and arrow-side designation; sketches are graded by the instructor.
Materials: Printed structural drawings for markup, red pens, blank sketch paper, assembled steel T-joint specimens, AWS A2.4, RFI form template (contractor-standard format), NCCER Welding Level 2 Module 29201
Check: RFI clearly identifies the discrepancy and references the drawing sheet and detail number; field sketch includes all required AWS A2.4 elements; both graded at 80% or better.

Practice check8

Answer each question, then check it. Nothing is recorded; this is your own practice.

Blueprint Reading & Welding Symbols
1. On a freehand field sketch of a plan view, what is the purpose of including a north arrow?
Blueprint Reading & Welding Symbols
2. According to AWS A2.4, where is the weld size for a fillet weld written on the welding symbol?
Blueprint Reading & Welding Symbols
3. A welder finds that a fillet weld symbol on Detail 3/S2 calls for a 1/2-inch leg size, but the material listed in the bill of materials for that location is 3/16-inch plate. What is the correct first action?
Blueprint Reading & Welding Symbols
4. What does the designation 'NTS' written on a field sketch mean?
Blueprint Reading & Welding Symbols
5. On a redlined structural drawing, a cloud shape is drawn around an area and a triangle containing the number '2' is placed outside the cloud. What does the number '2' inside the triangle signify?
Blueprint Reading & Welding Symbols
6. A fillet weld symbol's triangle is placed ABOVE the reference line. This means the weld is located on which side?
Blueprint Reading & Welding Symbols
7. Which of the following pieces of information is REQUIRED on a formal RFI submitted to an engineer of record?
Blueprint Reading & Welding Symbols
8. A welder is producing a field sketch of a T-joint and wants to specify a 5/16-inch fillet weld, 4 inches long, on the arrow side only. Which arrangement of elements on the welding symbol correctly represents this?