Objective. Students will identify all major flashing types, explain the water-shedding principle that governs installation sequencing, and correctly interpret a standard architectural flashing detail drawing.
This lesson, its worked examples and its practice questions has not yet been verified by a licensed professional engineer or master tradesperson or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.
VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.
Flashing is sheet metal, membrane, or composite material installed at every roof location where two surfaces meet, where a roof surface is interrupted, or where water could enter a building. Improperly installed flashing is one of the leading causes of roof failure and interior water damage. Understanding flashing before you ever climb a ladder is not optional — it is the foundation of every waterproofing decision you will make on the job.
Every flashing installation is governed by one overriding rule: water must always be directed downhill over the next layer, never under it. This is called the water-shedding principle or shingle principle. Each component is lapped so that the piece higher on the slope covers the top edge of the piece below it, just as fish scales or roof shingles overlap. Reversing this sequence — called a reverse lap or back-lap — traps water behind the flashing and guarantees a leak. Sequencing your work correctly before you fasten anything is therefore the single most important habit in flashing installation.
Drip edge is an L-shaped metal strip installed at eaves and rakes. At the eave it goes under the underlayment; at the rake it goes over. It directs water off the roof deck edge and protects fascia from wicking.
Valley flashing covers the internal angle where two roof planes intersect. Open valleys use a continuous metal strip; closed-cut and woven valleys use shingles, but an ice-and-water barrier or metal liner is still required under them.
Step flashing is a series of L-shaped pieces, one per shingle course, installed where a sloped roof meets a vertical wall. Each piece steps up the wall with the shingle courses. A counter flashing (also called cap flashing) is embedded in or fastened to the wall above and laps over the step flashing, keeping the two pieces independent so the wall can move without tearing the roof.
Base flashing is the upturned portion at the bottom of a wall or curb intersection. It ties the flat or low-slope membrane to the vertical surface. Counter flashing laps over it from above.
Pipe boots (pipe flashing collars) seal around round penetrations such as plumbing vents. They consist of a lead, EPDM, or thermoplastic collar over a metal or plastic flange. The flange integrates with the surrounding roofing using the shingle principle.
Skylight curb flashing seals the raised frame of a skylight to the roof. The manufacturer typically provides a self-flashing unit or a separate curb kit; step and counter flashing details apply on the sides, and a saddle or cricket is required on the uphill side of any curb wider than a certain dimension (check current code and manufacturer requirements).
Parapet and coping flashing caps the top of a parapet wall. Coping metal overlaps at joints and turns down both sides to prevent water from sitting on the wall top. End dams — small upturned flanges at coping joints and terminations — stop water from traveling horizontally under the coping and exiting through the wall.
Expansion joint covers bridge building movement joints. They are designed to flex without tearing, using bellows shapes, slip joints, or flexible membrane inserts.
| Material | Typical Use | Notes |
|---|---|---|
| Galvanized steel | Drip edge, valley, step | Low cost; do not use in contact with copper |
| Aluminum | Drip edge, general flashing | Lightweight; avoid contact with concrete/mortar |
| Copper | Valleys, gutters, premium work | Long-lasting; reacts with aluminum and galvanized steel |
| Lead | Pipe boots, custom work | Highly malleable; follow local disposal regulations |
| EPDM / rubberized asphalt | Pipe boots, self-adhering membrane | Excellent flexibility; membrane type bonds directly to substrate |
Material compatibility is a safety and quality issue. When dissimilar metals contact each other in the presence of moisture, galvanic corrosion occurs. Never allow copper and galvanized steel or aluminum to touch directly. Use compatible fasteners (stainless steel or the same metal as the flashing) and consult manufacturer guidance.
Construction drawings include detail drawings that show cross-sections of critical junctions at a large scale, often 3 inches = 1 foot or larger. To read a flashing detail:
1. Identify the view. A section cut shows the interior of a junction sliced perpendicular to the surface.
2. Read the material callouts. Each component is labeled with a keynote number or leader line pointing to a material description in the legend.
3. Trace the water path. Start at the highest point and follow water downward. Every lap should shed water onto the surface below.
4. Note fastener callouts. Details specify fastener type, spacing, and whether exposed fasteners must be sealed.
5. Check for dimensional requirements. Minimum flashing height up a wall, minimum overlap dimensions, and sealant locations are often dimensioned directly on the detail.
If a detail conflicts with the manufacturer's printed instructions, bring the discrepancy to your foreman or the project supervisor before you install anything. Do not guess.
Flashing work places you at roof edges and around penetrations. Always confirm your fall protection system is in place and anchored before beginning any detail work. Sheet metal edges are extremely sharp — wear cut-resistant gloves when handling metal flashing. Self-adhering membranes can be slippery on steep slopes; maintain three points of contact. Dispose of lead flashing scraps according to applicable regulations; do not allow them to enter storm drains.
Answer each question, then check it. Nothing is recorded; this is your own practice.