MFG-CNC14-02 · Lesson 12 · 16 clock hours · practice

Drawing Discrepancies, Non-Conformance, and Document Control

Objective. Students identify conflicting, ambiguous, or incomplete drawing callouts and document a non-conformance report (NCR) following a standard shop process.

⚠ Pending professional review

This lesson, its worked examples and its practice questions has not yet been verified by a licensed engineer or certified journey-level tradesperson or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.

VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.

Why Drawing Discrepancies Matter

Every part you machine starts with a drawing. If that drawing contains conflicting, ambiguous, or incomplete information, you may spend hours cutting metal only to produce a part that cannot be used. Worse, a bad part that slips into an assembly can cause equipment failure or injury. Catching drawing problems before you start—and documenting them correctly when you find them—is a professional responsibility, not an optional step.

Types of Drawing Errors

Conflicting tolerances occur when two callouts on the same feature disagree. For example, a title block might state a general tolerance of ±0.010 in. while a local callout on the same dimension reads ±0.005 in. Without knowing which controls, you cannot set up the job.

Missing datums create ambiguity in GD&T because every geometric tolerance must reference a datum structure unless it is specifically a form tolerance (such as flatness or cylindricity). A perpendicularity callout with no datum reference tells the machinist nothing about which surface to measure from.

Undefined surface finish means the drawing shows a surface finish symbol with no roughness value (Ra or RMS) filled in. You cannot verify the surface, and an inspector cannot accept or reject it.

Incorrect projection views happen when a third-angle or first-angle projection is mixed up, a view is mislabeled, or a detail view arrow points the wrong direction. Reading the wrong view can cause you to machine a mirror-image feature.

Obsolete revisions are drawings that have been superseded by a newer release. Using an old revision is one of the most common—and most costly—shop-floor errors.

Illegible notes may be caused by poor print quality, overprinting of text, or damage to the drawing file. Any note you cannot read completely must be treated as missing information and flagged before work begins.

Document Control Basics

Document control is the system that ensures only the correct, approved version of a drawing is used for production. Key concepts:

In a simulated document control folder, you should be able to look at the revision block, compare it to the master index, and confirm you have the correct document.

Non-Conformance Reports (NCRs)

A non-conformance report (NCR) is the formal record that a part, material, or process does not meet the applicable requirement. Completing an NCR is not an admission of fault—it is a professional, quality-driven response to a real problem.

A standard NCR typically includes:

1. Part identification: Part number, description, revision level of the drawing used.

2. Description of discrepancy: Which dimension or callout is out of compliance, by how much, and how it was discovered.

3. Affected quantity: How many parts are nonconforming.

4. Root cause (if known): For example, machined to an obsolete drawing revision.

5. Recommended disposition: One of three standard choices:

6. Signatures and dates: Originator, quality review, and (for UAI) engineering approval.

The disposition decision is made by qualified personnel—often a quality engineer or the engineering team—not unilaterally by the machinist. Your job is to document accurately and completely so that decision can be made with full information.

Safety Note

Drawing errors can create safety hazards beyond scrap parts. If a structural or pressure-boundary component is machined to the wrong tolerance, it may fail in service. Always stop work and flag the discrepancy rather than making an assumption and continuing. Never alter a drawing or note on your own authority. Use proper personal protective equipment (PPE) when handling any materials in the shop, and follow lockout/tagout procedures if the machine must be accessed during a hold.

Summary

Before cutting, verify you have the current released drawing revision. Read every callout and check for the six common error types. When you find a problem, document it using the NCR process with accurate part identification, a clear description, affected quantity, and a logical recommended disposition. These habits protect quality, protect you, and protect everyone who uses the finished part.

Key terms9

Non-Conformance Report (NCR)A formal quality document recording that a part, material, or process does not meet a specified requirement, including a description of the discrepancy and a recommended disposition.
Revision ControlThe system that tracks changes to a drawing or document by assigning sequential revision identifiers (letters or numbers) so the current approved version is always distinguishable from older versions.
Engineering Change Order (ECO)The formal authorization document that describes, justifies, and approves a change to a released drawing or specification, resulting in a new revision level.
DispositionThe decision made by qualified personnel regarding what to do with a nonconforming part: use-as-is, rework, or scrap.
Datum Reference FrameThe three mutually perpendicular reference planes (A, B, C) from which GD&T measurements are taken; every applicable geometric tolerance must reference a datum or datum structure.
Obsolete RevisionA drawing version that has been superseded by a newer released revision and must not be used for production; it should be removed from the work area and marked void or superseded.
Third-Angle ProjectionThe drawing projection standard used in the United States, in which the front view is placed in the center, the top view above it, and the right-side view to its right; indicated by the standard projection symbol on the drawing.
Surface Finish SymbolA standardized graphic callout on a drawing that specifies the required surface texture of a feature, including a numerical roughness value (Ra) that must be present to be complete and enforceable.
Drawing ReleaseThe formal approval process that authorizes a drawing for production use, requiring review and sign-off by engineering and quality before the document enters the document control system.
In class: Students analyze a deliberately flawed drawing set (instructor-prepared with six seeded errors: conflicting tolerance, missing datum, undefined surface finish, incorrect projection view, obsolete revision, and an illegible note) and identify all errors in writing. · Instructor explains document control basics: revision control, drawing release, engineering change orders (ECOs), and why only the current released revision may be used on the shop floor; students practice pulling the correct drawing revision from a simulated document control folder. · Students complete a non-conformance report for a part that has been machined to an older drawing revision, documenting the discrepancy, affected dimensions, and recommended disposition (use-as-is, rework, scrap), following a standard NCR template.
Materials: Flawed drawing set (instructor-prepared, 6 seeded errors), simulated document control folder with multiple revisions, NCR template form, standard shop process reference sheet, pens
Check: Error identification: must find at least 5 of 6 seeded drawing errors (83%); NCR form reviewed by instructor for completeness and correct disposition logic—must include all required fields to pass.

Practice check8

Answer each question, then check it. Nothing is recorded; this is your own practice.

Blueprint Reading and Document Control
1. You pick up a job packet and notice the drawing is labeled Rev C, but the document control index shows the current released revision is Rev D. What is the correct action?
GD&T / NIMS Machining
2. A drawing shows a perpendicularity callout of 0.002 in. on a bore, but the feature control frame has no datum letter referenced. This is an example of:
Document Control / Quality
3. Which of the following correctly describes the purpose of an Engineering Change Order (ECO)?
Quality / Non-Conformance
4. A part was machined to Rev B of a drawing. The shop has since released Rev C, which changed a critical hole diameter. The machinist completes an NCR. Which field is NOT a standard required element of that NCR?
Blueprint Reading / GD&T
5. A surface finish symbol on a drawing has a check mark with no Ra value filled in. Which type of drawing error does this represent?
Quality / Non-Conformance
6. Engineering reviews a nonconforming part and determines the deviation does not affect its form, fit, or function. Which disposition will they most likely approve?
Blueprint Reading
7. On a US engineering drawing, the standard projection method used is third-angle projection. If the right-side view is incorrectly placed to the LEFT of the front view, this would be classified as:
Blueprint Reading / Safety
8. A machinist finds an illegible note on a drawing before starting setup. What is the safest and most professionally correct response?