Objective. Students stake all four corners of a simulated building footprint using total station angle-and-distance layout, set batter boards at correct offsets, and verify squareness by diagonal check within 0.02 ft
This lesson, its worked examples and its practice questions has not yet been verified by an industry-certified professional or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.
VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.
Before a single footing is poured, the building's corners must be located on the ground exactly where the design drawings say they should be. Errors at this stage carry forward into every wall, column, and floor that follows. A corner set 0.10 ft off plan can mean torn-out concrete, failed inspections, and costly delays. Your job as a survey technician is to translate numbers on paper into physical points in the field with enough precision that the construction crew can work from them with confidence.
Coordinate geometry (COGO) lets you calculate the angle and distance from a known control point to each design corner using the corners' plan coordinates. Before you touch the instrument, open your field book and work through every computation by hand. Record the control point coordinates, the design corner coordinates, the computed bearing or azimuth, and the horizontal distance to each corner. Use the inverse formula: distance = √((ΔE)² + (ΔN)²) and azimuth = arctan(ΔE / ΔN), adjusting the quadrant as needed. Write the setup point and backsight point at the top of the page. Pre-computed values give you a check: if the instrument readout differs from your book by more than a small amount, something is wrong before any stake goes in the ground.
Center and level the total station over the control point using the tribrach and optical or laser plummet. Plumb to within 1–2 mm. Level the instrument until the plate bubble or electronic tilt display is within tolerance. Backsight the reference azimuth point, set the horizontal circle to the design azimuth of that direction, and lock it. All subsequent angle reads will be referenced to that azimuth. Confirm the backsight by reading the angle — it must match your computed azimuth. If it does not, re-orient before staking anything.
For each corner, key in or manually set the design azimuth and distance. Rotate the instrument to the design azimuth, direct your rodperson left or right until the prism is on line, and measure the slope distance, applying a horizontal distance reduction if the terrain is not flat. Drive a wooden hub flush with the ground, then set a finish tack on the hub at the exact prism center. After all four hubs are set, measure and record the actual angle and distance from the instrument for each — compare to the design values and note any discrepancy. All four corners must fall within 0.05 ft of design position to pass this lab.
A rectangle is square when both diagonals are equal. Measure corner 1 to corner 3, and corner 2 to corner 4 with a 100 ft tape. If the diagonals differ by more than 0.02 ft, the shape is not square. Investigate which corner is off, adjust its hub, and re-measure both diagonals. Repeat until the difference is within tolerance. This check catches both angular error and distance error that might individually seem small.
Batter boards preserve the building lines after the corners are disturbed by excavation. Set them at a uniform height above finish floor elevation (FFE) — your instructor will give you the design FFE. Drive two stakes about 4–6 ft outside each corner (far enough to survive digging), nail a horizontal crosspiece at the target elevation using a hand level or level loop, and mark the building line on each crosspiece with a saw kerf or nail. Stretch string lines from crosspiece to crosspiece over the corner hubs. The intersection of the strings should land directly over the tack. Verify all crosspiece elevations are within 0.02 ft of design using your level rod and instrument. When string lines later sag in heat, builders re-tension them without losing the reference mark.
Always carry the total station in its case between setups; never carry a mounted instrument on a tripod over rough ground. On active construction sites wear a hard hat and high-visibility vest — these are mandatory PPE whenever equipment or overhead hazards are present. Steel-toed boots protect against dropped stakes and hubs. Before stretching string lines across travel paths, warn crew members and flag the lines with flagging tape at eye level. Keep the laser aperture pointed away from people when the total station is in active use. Store hubs, lath, and tools in a bucket when moving so they do not become trip hazards.
Record every setup, orientation, and measurement in pencil in your field book as it happens — never reconstruct notes later. Use a single line strikethrough for corrections; never erase. Sign and date each page. The field book is a legal document and is the primary record if a stakeout is ever disputed. Your COGO pre-computations belong in the same book, on a page immediately before the field observations.
Answer each question, then check it. Nothing is recorded; this is your own practice.