TEC-ELEC48-07 · Lesson 1 · 36 clock hours · theory
Project Scoping, Design, and Planning
Objective. Given a written scope of work, the student produces a complete project design package—schematic, block diagram, bill of materials, and work plan—that is technically accurate and ready for peer review.
⚠ Pending professional review
This lesson, its worked examples and its practice questions has not yet been verified by an industry-certified professional or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.
VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.
Why Project Scoping and Design Come First
Before a single wire is pulled or a component is soldered, a professional technician produces a complete design package. Rushing to the build phase without a solid plan is one of the most common causes of rework, cost overruns, and failed inspections. In this capstone lesson you will learn how to translate a written scope of work into the four documents that make your project reviewable, buildable, and defensible: a design brief, a block diagram and schematic, a bill of materials (BOM), and a work plan.
Reading and Analyzing a Scope of Work
A scope of work (SOW) is a written statement from a customer or project manager that describes what must be delivered, where, and under what conditions. Your first task is to extract every deliverable, identify all signal paths, and flag any compliance requirements before you draw a single line.
Work through the SOW systematically:
1. Deliverables — List every end product the customer expects: installed cabling, a working RF receive chain, a powered subassembly, test reports, and as-built documentation.
2. Signal paths — Trace how each signal travels from source to load. For a small-office telecom and electronics installation this typically includes an RF receive path (antenna → coax → distribution), a structured cabling backbone (patch panel → horizontal runs → work area outlets), fiber optic links (optical line terminal → fiber → optical network terminal or device), and one or more powered circuit subassemblies (power supply → load).
3. Compliance requirements — Note every standard or code the installation must meet. For structured cabling, BICSI's Telecommunications Distribution Methods Manual (TDMM) is the primary design reference. Fiber work must meet EIA/TIA standards for testing and termination. Electrical circuits must conform to applicable electrical codes. Record these in your design brief so reviewers can verify compliance at each milestone.
Organize your findings in a structured design brief: a one- or two-page document that lists deliverables, signal paths, applicable standards, and any constraints (room dimensions, power budget, customer-specified equipment).
Block Diagrams and Schematics
A block diagram uses labeled rectangles and arrows to show the functional relationships between major system elements. It is not a schematic — it shows what connects to what, not exactly how the circuit works at the component level. Draw the RF receive chain, the structured cabling backbone, the fiber optic links, and the powered subassembly as separate subsystems, then show how they interconnect.
Best practice: draw a rough hand sketch first on graph paper, then produce a clean version in a free CAD tool such as KiCad. Check that every signal path in the SOW appears in the diagram.
Once the block diagram is approved, produce a schematic for the circuit portions (the powered subassembly and any active RF components). A proper schematic follows these conventions, which align with ETA CET study guide requirements:
- Each component has a unique reference designator (R1, C1, U1, etc.).
- Every component shows its value (resistance in ohms, capacitance in farads or microfarads, voltage rating, etc.).
- Power rails are clearly labeled (e.g., +12 V, GND).
- Signal flow moves left to right where possible.
- Nets (wires connecting pins) are labeled where they cross the schematic boundary or connect to another sheet.
Building the Bill of Materials
The bill of materials (BOM) is a spreadsheet with one row per unique part. Required columns:
| Column | Purpose |
|---|---|
| Reference Designator(s) | Links the BOM row to the schematic |
| Part Description | Human-readable name |
| Manufacturer Part Number | Uniquely identifies the part |
| Quantity | Total needed for the build |
| Unit Cost | Price per piece |
| Extended Cost | Unit Cost × Quantity |
| Lead Time | Days from order to delivery |
| Supplier | Where you will source the part |
Accuracy in the BOM prevents shortages that stall the build phase. Verify part numbers against a supplier catalog, not just a datasheet title.
Producing the Work Plan
A Gantt-style work plan allocates your remaining capstone hours across phases. Typical phases for this capstone are: build, test, troubleshooting, and documentation. For each phase, identify tasks, estimated hours, dependencies (what must finish before the next task starts), and who is responsible.
Keep your total allocated hours at or under the hours available. If tasks sum to more than the available time, you must reduce scope, increase efficiency, or flag the conflict to your instructor before the build begins — not after.
Safety Points That Apply at the Design Stage
Design decisions made now determine the hazards workers face during the build:
- Lockout/Tagout (LOTO): Any circuit powered from AC mains must include a LOTO point in the work plan. Identify which breaker or disconnect will be locked out before work begins on powered circuits.
- PPE selection: Your work plan should specify the appropriate PPE for each phase. Fiber work requires safety glasses to protect against glass shards. RF work near active transmitters requires awareness of RF exposure limits.
- Wire gauge and fusing: Selecting undersized wire or omitting a fuse in the schematic creates a fire or shock hazard. Verify that every conductor in the schematic is rated for its load current and that overcurrent protection is present.
- Cabling pathways: Per BICSI TDMM guidance, power cables and low-voltage data cables must be separated by adequate distance or barriers to prevent interference and comply with applicable codes.
A design package that ignores these points will not pass peer review and cannot proceed to build.
Key terms10
Scope of Work (SOW)A written document that defines all deliverables, signal paths, constraints, and compliance requirements a technician must satisfy to complete a project.
Design BriefA structured summary document that captures deliverables, signal paths, applicable standards, and constraints extracted from the scope of work.
Block DiagramA diagram that uses labeled rectangles and directional arrows to show functional relationships between major system components without detailing internal circuit topology.
Reference DesignatorA unique alphanumeric label (e.g., R1, C3, U2) assigned to each component on a schematic that links the symbol to its entry in the bill of materials.
Bill of Materials (BOM)A spreadsheet listing every component or material needed for a build, including part numbers, quantities, unit costs, extended costs, and lead times.
Gantt-Style Work PlanA project scheduling tool that maps tasks to a timeline, showing durations, dependencies, and phase boundaries so that total hours fit within the available project time.
Signal PathThe complete route a signal travels from its source through all intermediate components (amplifiers, cables, connectors, splitters) to its destination.
Lockout/Tagout (LOTO)An OSHA-regulated procedure that uses physical locks and warning tags to ensure equipment is de-energized and cannot be re-energized while technicians work on it.
BICSI TDMMBICSI's Telecommunications Distribution Methods Manual — the primary industry reference for planning, designing, and documenting structured cabling systems.
Lead TimeThe number of calendar days between placing a purchase order for a component and receiving it, used in the BOM and work plan to avoid build delays.
Worked examples4
1. Calculate the extended cost for a BOM line item: you need 14 RJ-45 keystone jacks at $2.85 each. Also confirm whether your remaining 12 hours is enough if installation of each jack takes an estimated 0.75 hours.
- Extended Cost = Unit Cost × Quantity = $2.85 × 14 = $39.90
- Total installation time = 0.75 hours/jack × 14 jacks = 10.5 hours
- Compare to available time: 10.5 hours required vs. 12 hours available → 12 − 10.5 = 1.5 hours remaining after jack installation
- Conclusion: the budget is sufficient; 1.5 hours remains for other tasks in this phase
Answer: Extended cost is $39.90. The 14 jacks require 10.5 hours to install, which fits within the 12 available hours, leaving 1.5 hours of buffer.
2. A small-office fiber link must connect two points 68 meters apart. The SOW specifies OM3 multimode fiber with a maximum allowable link loss of 3.5 dB. Connector loss is 0.5 dB per mating pair; there are two mating pairs in the link. Splice loss is negligible. OM3 fiber has an attenuation of 3.5 dB/km at 850 nm. Determine whether the link budget is met.
- Calculate fiber attenuation: 68 m = 0.068 km; Fiber loss = 3.5 dB/km × 0.068 km = 0.238 dB
- Calculate total connector loss: 2 mating pairs × 0.5 dB/pair = 1.0 dB
- Total link loss = fiber loss + connector loss = 0.238 dB + 1.0 dB = 1.238 dB
- Compare to allowable loss: 1.238 dB < 3.5 dB allowable
- The link budget is met with margin to spare
Answer: Total calculated link loss is approximately 1.24 dB, well within the 3.5 dB allowable budget. The fiber link design is acceptable.
3. A powered subassembly on the schematic uses a 12 V DC supply and draws a continuous load current of 1.8 A. Select the minimum standard fuse rating using a 125% safety factor, and identify the minimum wire gauge that can carry this current (use the general rule that 18 AWG wire is rated for up to 2.3 A in chassis wiring for reference).
- Calculate the derated fuse current: 1.8 A × 1.25 = 2.25 A
- Select the next standard fuse size at or above 2.25 A: a 2.5 A fuse is the next standard size above 2.25 A
- Check wire gauge: load is 1.8 A; 18 AWG is rated up to 2.3 A for chassis wiring, which is above 1.8 A, so 18 AWG is acceptable
- Record both the fuse value (2.5 A) and wire gauge (18 AWG) as component values on the schematic
Answer: Specify a 2.5 A fuse and 18 AWG wire. Both values must appear on the schematic with reference designators before the design package is submitted for review.
4. A Gantt work plan shows four phases with the following estimated hours: Build = 28 h, Test = 10 h, Troubleshooting = 8 h, Documentation = 6 h. The remaining capstone budget is 48 hours. Determine whether the plan fits, and calculate the surplus or deficit.
- Sum all phase hours: 28 + 10 + 8 + 6 = 52 hours
- Compare to budget: 52 hours needed − 48 hours available = 4-hour deficit
- The plan does not fit. The technician must reduce scope in one or more phases by a total of at least 4 hours before submitting the work plan
Answer: The plan has a 4-hour deficit and must be revised. For example, reducing the Build phase from 28 h to 24 h would bring the total to 48 h and balance the plan.
The math in this lesson2
Learners compute BOM extended cost and total labor hours for 14 jacks against an hour budget.
7.RP.3N-Q.1
In class: Analyze a provided scope of work (simulating a customer request for a small office telecom and electronics installation) and identify all deliverables, signal paths, and compliance requirements; record findings in a structured design brief · Draft a hand-drawn and CAD-assisted block diagram showing the RF receive chain, structured cabling backbone, fiber optic links, and powered circuit subassembly, then transfer the circuit portion to a proper schematic with component values and reference designators · Build a complete bill of materials spreadsheet with part numbers, quantities, unit costs, and lead times, and produce a Gantt-style work plan allocating the remaining capstone hours across build, test, troubleshooting, and documentation phases
Materials: Scope-of-work handout, graph paper, pencils, free CAD tool (KiCad or equivalent), spreadsheet software, BICSI TDMM (current edition) for cabling design reference, ETA CET study guide for circuit design conventions, calculator
Check: Instructor reviews the design package against a 20-point rubric covering completeness, technical accuracy, code compliance references, and BOM accuracy; student must score 15/20 (75%) to proceed to the build phase
Practice check8
Answer each question, then check it. Nothing is recorded; this is your own practice.